Resolved
The Board noted the report and agreed that the risk register appeared as a separate agenda item for future meetings.
Blackpool, Fylde and Wyre Economic Prosperity Board noted this item on Tuesday 7 January 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
The Board noted the report and agreed that the risk register appeared as a separate agenda item for future meetings.
Report to: Blackpool, Fylde and Wyre Economic Prosperity Board
Report Author: Rob Green, Head of Enterprise Zones, Blackpool Council
Date of Meeting: Tuesday 7th January 2020
Recommendation: That the Committee notes the report.
1. Blackpool Airport Enterprise Zone: Progress Report
a) Masterplan Work to revise the EZ masterplan and delivery plan will commence in the first quarter 2020 pending completion of key work on specific details around phase one, highways and airport design. The new plan will also reflect the impacts of the data centre study recommendations and the changes surrounding the Squires Gate Industrial Estate. A procurement process is underway to revise the plan and thereafter re-work the delivery plan, which will provide new estimates of cost retained rates revenue, jobs and impact upon GVA over the lifetime of the EZ. It is hoped that the revised plan and delivery plan can be completed and presented for approval to EPB by March 2020. The approved Marketing Strategy will continue to be implemented for the Enterprise Zone and where appropriate will be updated upon completion of the masterplan update.
b) Fiscal Incentives The clock continues to tick with regards the EZ fiscal benefits with the business rates relief due to expire on 31st March 2022 and the enhanced capital allowances (ECA) due to expire in November 2023, which will leave only a very short window of opportunity to capitalise once new development sites are released upon completion of key enabling infrastructure.
Agreement has been reached at the LEP EZGC for action to approach MHCLG and HMT on behalf of the four Lancashire and other Northern EZ’s to seek extensions of the Fiscal benefits.
To progress matters it is therefore intended, to prepare a draft formal proposal seeking an extension of the fiscal incentives available to EZ’s and circulate this to all northern EZ’s seeking their support in principle. Thereafter calling a meeting of EZ’s to be hosted in Lancashire to confirm the basis of a collective approach to MHCLG and HMT.
Preparatory work is underway to identify contacts for all other Northern Enterprise Zones for a combined approach to government as well as ongoing discussions with other LAMEC Enterprise Zones on next steps.
c) Current Activity - Phase One A revised hybrid planning application for phase one is in the final stages of preparation and on target to be submitted at the end of January, once a few minor outstanding issues relating surrender and renewal of sports leases have been concluded. The new application will reflect a revised location for the eastern gateway road and changed aspirations in respect of replacement sports provision which will satisfy previous objections raised by Sport England.
8 Work commenced with dispensation under airport permitted development rights on Monday 9th December, to provide a new boundary fence to Blackpool Airport to carve off the land needed to accommodate new grass sports pitches, with an engineering contract due to commence in the new year, to provide a new airport perimeter track and crash gates prior to the engineering contract beginning in March to create the playing surface and drainage.
A further informal public consultation, will take place in January with a decision in principle, subject to Secretary of State consideration as it is Green Belt, anticipated in late Spring 2020.
The hybrid planning application will also include provision for a new primary electricity substation required to support anticipated increased power demand from early development of the phase one sites including the potential for possible data centres.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
BLACKPOOL AIRPORT EZ PROGRESS REPORT (STANDING ITEM)Report | 6 pages | DownloadRead as text |
Follow Blackpool, Fylde and Wyre Economic Prosperity Board at Blackpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Mar 2024 | Appointment of chairmanThat Councillor Mark Smith be appointed Chairman for the meeting. | Decided | Open |
| 14 Mar 2024 | Exclusion of public and pressThat the public and press be excluded from the meeting whilst the agenda items 7 and 8 are considered, on the ground ... | Decided | Open |
| 14 Mar 2024 | Minutes of the last meeting held on 7 december 2023That the minutes of the meeting held on 7 December 2023 be approved and signed by the Chair as a correct record. | Approved | Open |
| 14 Mar 2024 | Fylde coast green growth updateThat the update be noted. | Noted | Open |
| 7 Dec 2023 | Appointment of chairThat Councillor Mark Smith be appointed Chair of the Blackpool Fylde and Wyre Economic Prosperity Board for the meeting | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.