Resolved
That the minutes of the meeting held on 21 November 2024 be approved as a true and correct record.
Audit Committee approved this item on Thursday 16 January 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
That the minutes of the meeting held on 21 November 2024 be approved as a true and correct record.
Public Document Pack MINUTES OF AUDIT COMMITTEE MEETING - THURSDAY, 21 NOVEMBER 2024
Present:
Councillor B Mitchell (in the Chair)
Councillors
Cartmell McKevitt Thomas
David Swift, Independent Member
In Attendance:
Councillor Paul Galley, Chair of the Scrutiny Leadership Board
Neil Jack, Chief Executive Steve Thompson, Director of Resources Vicky Gent, Director of Children’s Services Lorraine Hurst, Assistant Chief Executive (Governance)/ Monitoring Officer Tracy Greenhalgh, Head of Audit and Risk Jonathan Pickup, Head of Information Governance/ Data Protection Officer Karen Tomlinson, Corporate Finance Accountant Ken Place, Deputy Head of ICT Services Katy Beavers, Democratic Governance Senior Adviser
Nicola Wright, External Auditor, Deloitte (via Microsoft Teams) Tim Cutler, External Auditor, KPMG Emma Morgan, External Auditor, KPMG
1 DECLARATIONS OF INTEREST
There were no declarations of interest on this occasion.
2 MINUTES OF THE LAST MEETING HELD ON 26 SEPTEMBER 2024
Resolved: That the minutes of the meeting held on 26 September 2024 be approved as a true and correct record.
3 STRATEGIC RISK REGISTER DEEP DIVE - TECHNOLOGY
[name removed], Deputy Head of ICT Services provided an overview of the Strategic Risk Register Deep Dive report into the controls being implemented to manage the strategic risk relating to technology. [name removed] reported that the two main areas of risk were cyber threats and an inability to carry out business critical activity due to unsupported hardware or software systems. MINUTES OF AUDIT COMMITTEE MEETING - THURSDAY, 21 NOVEMBER 2024
In relation to the risk of cyber threats, the greatest focus was on the prevention of cyber- attacks. To manage the risk, Internal Firewall Segmentation was currently in place for all wired connections to the Council network between key buildings and floors. This had recently been enhanced to include Wi-Fi connections. A 24/7 Security Operations Centre (SOC) was also being set up to assist with the identification and monitoring of potential cyber incidents.
[name removed] reported that regarding the second main area of risk, an inability to carry out business critical activity due to unsupported hardware or software systems, various projects were ongoing to refresh the data centres. These included phasing out the outdated copper phone lines, migrating files from the data centres into Sharepoint, removing out-of-date operating systems, and upgrading servers to ensure they remained supported.
The Committee noted that Cyber Awareness staff training was mentioned as a control, and asked whether this training was mandatory. [name removed] confirmed that it was mandatory for all new staff, and all staff completed mandatory annual refresher Cyber Awareness training.
Members questioned whether all of the recommendations from the Cyber Attack exercise facilitated by the Local Government Association (LGA) in February 2024 had been implemented. [name removed] reported that this was a work in progress, noting that the level of communication offered by the Council would increase as the system upgrades progressed. In response to a question, [name removed], Chief Executive stated that some systems such as Vitaline were critical and could not fail. [name removed] reported that there was a clause in the current Supply of Hardware contract stating that the supply chain would not be compromised, should it be needed due to bonded stock availability.
[name removed], Head of Audit and Risk reported that an action plan had been produced following the LGA Cyber Attack exercise, which included areas such as information governance. The action plan was monitored by the Corporate Risk Management Group, chaired by the Head of Audit and Risk.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MINUTES OF THE LAST MEETING HELD ON 21 NOVEMBER 2024Minutes | 8 pages | DownloadRead as text |
Follow Audit Committee at Blackpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Sep 2026 | Minutes of the last meeting held on 11 june 2026That the minutes of the meeting held on 11 June 2026 be approved as a true and correct record. | Approved | Open |
| 24 Sep 2026 | Strategic risk register deep dive - commercialTo note the Strategic Risk Register Deep Diver regarding Commercial risk. To receive an overview of the different typ... | Noted | Open |
| 24 Sep 2026 | Internal audit follow up - creditor payment financial control assurance testingTo note the Internal Audit Follow Up - Creditor Payment Financial Control Assurance Testing. | Noted | Open |
| 24 Sep 2026 | Internal audit follow up - illuminations serviceTo note the Internal Audit Follow Up – Illuminations Service. | Noted | Open |
| 24 Sep 2026 | Updated external audit plan and strategy for the year ending 31 march 2026To note the updated External Audit Plan and Strategy for the Year Ending 31 March 2026. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.