Blackpool Borough Council
Audit Committee, Thursday 16 January 2025 at 6.00pm

INTERNAL AUDIT FOLLOW-UP - CAPITAL PROJECT MANAGEMENT

Noted Finance 1 paper

Audit Committee noted this item on Thursday 16 January 2025. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

To note the actions being implemented to address the audit recommendations relating to the Capital Project Management audit.
Word for word from the decision Blackpool published for this meeting. Source: democracy.blackpool.gov.uk

Follow this further

Built from Blackpool's papers

What the report saysPro

Report to Audit Committee, 10 pages

Purpose of the report

1.1To consider a progress report on the recommendations made in the internal audit report relating to capital project management issued on 10 January 2024.

2.0Recommendation(s):

2.1To consider the actions being implemented to address the audit recommendations relating to the Capital Project Management audit.

3.0Reasons for recommendation(s):

3.1To enable Audit Committee to consider an update and progress report on the audit recommendations.

3.2Is the recommendation contrary to a plan or strategy adopted or approved by the Council? No

3.3Is the recommendation in accordance with the Council’s approved budget? Yes

4.0Other alternative options to be considered:

4.1N/A

5.0Council priority:

5.1This audit impacts on the Council’s community and economic priorities.

6.0Background information

6.1The Council is delivering an ambitious regeneration programme with a number of capital projects contributing to the overall programme of work. A Capital Strategy and Programme are in place which set out the schemes which the Council has committed to with funding for schemes supplemented by external funding bids, prudential borrowing and private sector investment. 6.2 The scope and assurance statement of the audit was as follows:

Scope The scope of the audit included:  The current approach to the management of the Council’s capital projects and whether it is sufficiently robust;  Whether internal Project Management capabilities, experience and training requirements are appropriately considered; and  Whether there are areas of improvement which can be made. Assurance Statement A number of capital projects delivered by the Council have been delivered late and overspent however this can be attributed to a number of external factors such as increased inflation, the Covid pandemic, interest rates and supply chain issues. There are lessons which can be learned from these past experiences to further strengthen the Council’s approach to capital project management.

Notwithstanding the significant challenges which capital projects have faced when delivering the regeneration programme across the town, overall we consider that the internal project management arrangements are adequate however we have made a number of recommendations to further strengthen the approach.

6.3Does the information submitted include any exempt information? No

7.0List of Appendices:

7.1Appendix 4(a): Internal Audit Recommendations and Agreed Actions.

8.0Financial considerations:

8.1The controls being implemented will be done so within current budget constraints.

9.0Legal considerations:

9.1Risks need to be effectively managed in order to comply with relevant legislation.

10.0Risk management considerations:

10.1To enable Audit Committee to gain assurance that risks are being effectively managed.

11.0Equalities considerations and the impact of this decision for our children and young people:

11.1Where equality analysis is appropriate these will have been undertaken whilst making decisions relating to the subject.

12.0Sustainability, climate change and environmental considerations: 12.1 Any matters relating to sustainability, climate change and environmental considerations will be considered when making decisions relating to the subject.

13.0Internal/external consultation undertaken:

13.1The progress report has been prepared in conjunction with the relevant Head of Service and Chief Officer.

Background papers

14.1N/A Appendix 4(a) - Agreed Action Plan

Recommendation Priority Agreed Action Responsible Target Date Revised Progress officer Target Date for outstanding actions

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
INTERNAL AUDIT FOLLOW-UP: CAPITAL PROJECT MANAGEMENTReport 10 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 15 attended
KB
Katy BeaversSecretary, present
JB
John BlackledgeOfficer, present
SC
Councillor Simon CartmellCommittee Member, present
MF
Councillor Mel FenlonCommittee Member, present
NG
Nick GerrardOfficer, present
TG
Tracy GreenhalghOfficer, present
AH
Councillor Alistair HumphreysVice Chair, present
LH
Lorraine HurstSecretary, present
NJ
Neil JackOfficer, present
JJ
Councillor Julie JonesCommittee Member, present
PJ
Paul JonesOfficer, present
BM
Councillor Bradley MitchellChair, present

All 15 on the meeting page

On this subject at Blackpool

Search all
  1. INTERNAL AUDIT FOLLOW-UP - CAPITAL PROJECT MANAGEMENTThis decision
  2. Internal audit follow up - creditor payment financial control assurance testingNoted
  3. Internal audit follow up - illuminations serviceNoted
  4. Global internal audit standards self assessmentNoted
  5. Internal audit follow-up - operational function of securityNoted
  6. Internal audit plan 2026/27Approved

More from Blackpool Audit Committee

All decisions
MeetingDecisionOutcome
24 Sep 2026 Minutes of the last meeting held on 11 june 2026That the minutes of the meeting held on 11 June 2026 be approved as a true and correct record. Approved Open
24 Sep 2026 Strategic risk register deep dive - commercialTo note the Strategic Risk Register Deep Diver regarding Commercial risk. To receive an overview of the different typ... Noted Open
24 Sep 2026 Internal audit follow up - creditor payment financial control assurance testingTo note the Internal Audit Follow Up - Creditor Payment Financial Control Assurance Testing. Noted Open
24 Sep 2026 Internal audit follow up - illuminations serviceTo note the Internal Audit Follow Up – Illuminations Service. Noted Open
24 Sep 2026 Updated external audit plan and strategy for the year ending 31 march 2026To note the updated External Audit Plan and Strategy for the Year Ending 31 March 2026. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies