RESOLVED that the self balancing capital virement of £50,000 from the under spending on Garth Hill College Modulars to pay for urgent unforeseen fire safety works at the Brakenhale School be approved. (NB: Councillor McCracken declared a personal interest in this matter being a governor of Brakenhale School and took no part in the discussion.)
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
2.1That the self balancing capital virement of £50,000 from the under spending on Garth Hill College Modulars to pay for urgent unforeseen fire safety works at the Brakenhale School be approved
Reasons for recommendations
3.1Under the Council’s financial regulations virements in excess of £25,000 must be approved by the full Executive.
3.2The fire safety works at Brakenhale are urgent and unavoidable, following a deficiency notice served upon the school by the Royal Berkshire Fire & Rescue Service.
3.3The Council has a duty of care to safeguard the pupils and adults in the school.
Alternative options considered
4.1In this case there are no alternative options, and the fire safety works must be implemented as soon as possible to avoid enforcement action, which could include prosecution and/or closure of parts of the school buildings.
4.2Closure is not an option because of the disruption to teaching and learning that this would bring about.
4.3In addition the Council’s insurers have indicated that failure to meet the requirements of the Deficiency Notice could result in an excess of as much as £275,000 being imposed on the school.
5 SUPPORTING INFORMATION
Arson Attacks
5.1The Brakenhale School has experienced four instances of small internal fires over the last two years, which have been evaluated as having been started deliberately (arson). The fires were minor in nature - the toilet paper in WC cubicles having been set alight. The actual damage has been slight, however in view of the previous occurrences, the most recent fire prompted a subsequent inspection by the Fire & Rescue Service.
Deficiency Notice
5.2Following the inspection the Fire & Rescue service served a statutory Deficiency Notice on the school identifying 31 fire safety compliance issues. In response the school has reviewed its security and fire safety procedures with the Borough Safety Adviser. The school has also undertaken a new fire risk assessment with an independent professional consultant. The outcome of this is a thirty four point action plan to address the compliance issues, which has been approved by the Fire & Rescue service and is currently being implemented by the school.
The Council’s Liability
5.3Responsibility for the management of health & safety, including fire safety, is largely delegated to schools however as the employer and owner of the buildings the Council is also liable.
5.4A capital budget is required to implement six of the thirty four action points that are the Council's responsibility under the Scheme of Delegation for the Local Management of Schools. These include upgrading and extensions to the fire alarm and emergency lights and works to an external (structural) fire escape staircase. These works are programmed for implementation via the Borough Surveyors before the end of this term and are estimated to cost £50,000.
Garth Hill College Modulars Underspend
5.5The 2006/07 capital programme included a project to provide two additional modular buildings at Garth Hill College, which were erected during the 2006 summer holidays. This project is under spent against its original budget because the number of additional classrooms to be provided in the buildings was reduced from five to four. The under spend on the Garth Hill project is sufficient to cover the cost of the fire safety works at Brakenhale at 5.4 above.
6 ADVICE RECEIVED FROM STATUTORY AND OTHER OFFICERS
Borough Solicitor
6.1The relevant legal provisions are contained within the main body of the report. The advice offered by the relevant regulator and insurers should be followed.
Borough Treasurer
6.2The financial implications arising from this report are set out in the supporting information.
Impact Assessment
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.