RESOLVED that approval be given to: 1 Conduct negotiations with the freeholder for the termination of the Enid Wood House lease agreement. 2 A decant strategy to be implemented provided terms for the surrender are agreed and subsequently approved - this strategy to re-house Enid Wood House tenants will be outside the Council’s current Allocations Policy in order to secure vacant possession of the block by 24 June 2008.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
1 Conduct negotiations with the freeholder for the termination of the Enid Wood House lease agreement.
2 A decant strategy to be implemented provided terms for the surrender are agreed and subsequently approved - this strategy to re-house Enid Wood House tenants will be outside the Council’s current Allocations Policy in order to secure vacant possession of the block by 24 June 2008.
Reasons for recommendation
3.1Enid Wood House is a block of 128 bed-sit flats in the town centre. The block is poorly designed and in a very poor condition and requires a significant amount of investment to bring it up to a decent standard. Despite intensive housing management, incidents of anti social behaviour are high.
3.2The vacancies within the block, along with the large capital works required to meet the Decent Homes Standard, result in it not being viable to retain Enid Wood House. A major and comprehensive refurbishment of the building by the freeholder will contribute towards the regeneration of Bracknell Town centre.
3.3The option recommended for achieving the disposal of the lease is considered viable and is considered to be a pragmatic approach to dealing with the unsatisfactory lease.
Alternative options considered
4.1The alternative option is to not conduct negotiations with the freeholder to surrender the lease of EWH. 5 SUPPORTING INFORMATION
Background
5.1EWH was originally leased from Bracknell Development Corporation by Bracknell District Council. The freehold has subsequently been purchased by Golfrate (a property company) and the District Council's interest has subsequently passed to Bracknell Forest Borough Council. The annual rent is £143,928 and the lease expires in 2038, with no break clause provisions. There is also a prohibition on assignment, sub-letting or parting with possession and the user clause restricts the Council from using it as anything other than residential accommodation forming part of the general housing stock. The lease is full repairing and the Council will have to meet the cost of dilapidations at the end of the lease unless the building is re- developed. Also, if the lease remains in place until the end of the term the Council will pay a further £4.6M (approx) in rent from the date of this report.
5.2An opportunity has now arisen to surrender this lease. Preliminary negotiations with the freeholder have been held to agree terms for a surrender of the lease. If successful this will enable the property to be refurbished to provide 1, 2 and 3 bedroom flats which will complement the refurbishment of the Town Centre.
6 DECANTING IMPLICATIONS
6.1Should the principle to surrender the lease be agreed, the Council will be committed to securing vacant possession of Enid Wood House within a 24 month period. The Council will proceed on this basis should there be a positive ballot in March 2007, this timescale will also fit in with the timetable for stock transfer.
6.2At present, there are 45 tenants living in Enid Wood House. Of these, 40 will require re-housing into a one bedroom property and 5 will require re-housing into two bedroom property. In order to re-house these tenants in time to meet the June 2008 timescale, it will be necessary to re-house them outside the Council’s existing Allocations Policy which requires vacant properties to be let to high priority applicants on the Housing Register.
6.3Over the next 24 months, the Council can expect an estimated 150 bedroom units to arise within its own and local RSL housing stock. In overall volume terms, there will be a sufficient supply of vacant properties to achieve the decanting deadline.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.