CORPORATE SERVICES BUDGET MONITORING - SEPTEMBER 2006 Proposed CS and CX In-Year Budget Savings Note Total Explanation
£'000
-20 Commercial Rents The budget for commercial rents received allows for vacancies (5% allowance = £0.100M based on past performance) however for the first time all properties are currently let. If all properties are fully let until 31 December and the "normal" vacancy rate applies for the last three months then additional income of £0.070M will accrue. However a £0.050M budget was anticipated for rental income from Birdsgrove reprovision in the current year which will not now happen in 2006/07. Therefore a £0.020M net saving can be anticipated.
-20 Your Homes The Council has provided for the costs of the preparation for the vote next March in a reserve. It is appropriate that a large element of the DSB costs arising from the development of the financial model, business case etc can be charged to this fund. -15 Members Allowances The number of Executive Members was reduced by two in the past year with a further Champion added saving a net £0.015M this year. Departmental Budgets A review of all departmental budgets based on the past years performance have identified the following potential savings. -20 External Audit The budget includes a provision for public enquiries. The audit of the 2005/06 accounts is almost complete with no enquiries. Therefore the budget may not be required unless an enquiry arises outside of the accounts audit process. -24 Income Civic ceremonies income has continued to increase and since 1st April 2006 the new Nationality Checking Service has proved very popular. It is forecast that an additional £0.014M can be generated this year. In Customer Services, it is forecast that the costs awarded after issueing summons for Council Tax will produce an additional £0.010M. -36 Various budgets DMT analysed the outturn for 2005/06 against budget across all detailed budgets and identified these areas as savings. These are also identified as part of the 2007/08 budget process. The savings are analysed as follows: Travel £0.007M Training £0.013M Consultancy £0.014M Printing £0.002M
-20 CX - Operational Development budget The Chief Executive retains a budget to support operational development within the Council. To date £0.020M has been committed and the remainder of the budget can be frozen for the current year. -10 Consultation A budget of £0.020M has been set up to facilitate the use of the BF 1500 through out the year. £0.005M has already been committed and one further consultation is planned. If subsequent consultations are frozen for the remainder of this year then a saving of £0.010M could be achieved. -30 DSB The current projection for the DSB is showing a shortfall of £0.006M if all current vacant posts were held until the 1 January. Assuming these same posts were held until 1 April then a saving could be achieved at the expense of service delivery. -25 Freezing expenditure on office expenses The Corporate Services and Chief Executives budgets for training, seminars, equipment, and furniture have uncommitted budgets remaining of circa £0.100M (after allowing for the savings identified in the departmental budgets). If these were capped at 75% of the remaining budget for the rest of the year then as saving of £0.025M could be achieved. -220 Total Appendix A2
EDUCATION, CHILDREN'S SERVICES AND LIBRARIES BUDGET MONITORING - SEPTEMBER 2006 Proposed ECS&L In-Year Budget Savings Note Total Explanation
£'000
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Revenue Budget Monitoring: In Year Savings PlanReport | 20 KB | DownloadRead as text |
PDF |
Update on the 2006/07 Revenue Budget MonitoringReport | 45 KB | Download |
Follow Executive at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2024 | Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... | Noted | Open |
| 17 Sep 2024 | Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... | Agreed | Open |
| 17 Sep 2024 | Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. | Approved | Open |
| 17 Sep 2024 | Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... | Noted | Open |
| 17 Sep 2024 | Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.