Resolved
RESOLVED that the progress made in the areas of the EPC Contract and Planning since the last meeting of the Board be noted.
Joint Waste Disposal Board noted this item on Wednesday 28 March 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the progress made in the areas of the EPC Contract and Planning since the last meeting of the Board be noted.
Overall progress has been maintained and we are ready to commence piling on 8 March 2007 (subject to confirmation that planning condition 23 has been discharged by the planning authority).
1 HEALTH SAFETY & ENVIRONMENTAL
There have been no reportable accidents in the period.
ACCIDENT and INCIDENT RECORD In Period To date Reportable 0 0 Non reportable 0 0 Near Misses 0 0
Total Site Man Hours to date without a Lost Time Accident (LTA) = 6722
The drainage / discharge of the site pond have been completed.
2 DESIGN
2.1Smallmead
This period has seen the continued development of the site drainage works, methane protection system, reinforced concrete works and structural steelwork design.
In the period we commenced the design of the mechanical works. Overall progress is summarised below:
• The design of the methane protection system has been finalised with drawings showing the position of the positive pressure units submitted to RE3 for comments. • The detailed design of the foul/surface water and road drainage layouts have been finalised with construction issue drawings produced. A manhole schedule is currently being produced along with standard manholes/gulley details. • Design of the site access works and entrance has commenced and will continue to be developed through the coming month. With details submitted to the planning authority once complete. • Design of the reinforced concrete works has continued with detailing of the walls to gridlines 4 & 8 and the pile caps complete and the HWRC floor slab currently in progress. Central Berks Waste PFI Project Date of Issue: 5.3.07 Progress Report 3 Page No: 4 of 6
• General arrangement drawings for the foundation slabs and pushwalls have continued to be developed to suit architectural details. These will be issued to RE3 for information shortly. • Construction issue structural steelwork drawings showing roof fan and louvre positions have been developed for the superstructure of the HWRC, TLS, MRF and office buildings. These drawings have been issued for sub- contractor design, fabrication drawings will be issued to RE3 for approval prior to commencement of fabrication. • Building elevations are currently being updated to show louvre and fan positions, this will be issued shortly to RE3 for approval. • Mechanical design of the ventilation system has been completed with the selection of roof fans and louvers. • The design of the dust suppression and fire protection systems has commenced. • The power requirements for each phase of the works has continued to be reviewed with options for MCC positions during phase one currently being developed prior to submission to RE3 for comments.
MRF – Preliminary design OKLM have now completed their basic design for the plant and issued general arrangement drawings confirming plant floor loadings, plant power requirements, plant access pits etc.
2.2Longshot
A site visit was carried out to make an assessment of appropriate investigation methods and identify any potential problems related to rig access.
3 CONSTRUCTION, PROCUREMENT - COMMISSIONING AND OPERATION
3.1Construction
Compound
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
EPC Contract: February 07 Monthly ReportReport | 102 KB | DownloadRead as text |
PDF |
EPC Contract: January 07 Monthly ReportReport | 102 KB | Download |
PDF |
Works Delivery Progress ReportReport | 24 KB | Download |
Follow Joint Waste Disposal Board at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Jun 2026 | Election of ChairRESOLVED that Councillor Finn McGoldrick be elected Chair of the Board for the municipal year 2026/27. | Decided | Open |
| 11 Jun 2026 | Election of Vice-ChairRESOLVED that Councillor Stephen Newton be elected Vice-Chair of the Board for the municipal year 2026/27. | Decided | Open |
| 11 Jun 2026 | re3 Progress ReportRESOLVED that 1 the contents of this report be noted. 2 a proposal on the simplification of the DIY charging structur... | Noted | Open |
| 11 Jun 2026 | re3 Strategy ReportRESOLVED that 1 the re3 Strategy 2026–2031 be approved and progressed through each partner council’s decision-making ... | Approved | Open |
| 11 Jun 2026 | re3 Finance Report - part oneRESOLVED that the year end financial position for FY25/26 be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.