Joint Waste Disposal Board, Wednesday 5 September 2007 at 6.00pm

Works Delivery Progress Report

Noted Committee 2 papers

Joint Waste Disposal Board noted this item on Wednesday 5 September 2007. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

RESOLVED that i ) the progress made in the areas of the EPC Contract and Planning since the last meeting on 20 June 2007 be noted; and ii) it be noted that there may be some delay in the commissioning of the Energy from Waste facility at Lakeside.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Joint Waste Disposal Board

Summary

Progress is being maintained throughout the works element with exception to the Cladding element due to delays in the material deliveries, although the roof sections of the cladding works are on critical path for releasing the works to the following trades ie Fire Suppression and M&E, the closing of the building perimeter walls is not yet critical. We are currently reporting a penetration of 18 days into the Phase 1 Buffer, which still reports an anticipated handover of the 1st Phase 4 weeks earlier then the contract Practical completion date.

1 HEALTH SAFETY & ENVIRONMENTAL

There have been no reportable accidents in the period.

ACCIDENT and INCIDENT RECORD In Period To date Reportable 0 0 Non reportable 0 0 Near Misses 20 118

Total Site Man Hours to date without a Lost Time Accident (LTA) = 44995

Testing of the discharge point (upstream/downstream) has been implemented by the JV. All test results are positive as anticipated to date.

1 DESIGN

2.1Smallmead

This period has seen the continued development of the reinforced concrete works and structural steelwork design. Electrical and Mechanical works have also continued.

Overall progress is summarised below:

• Design of the site access works and entrance has been revised following feedback and is currently being updated prior to issue to the planning authority. • Design of the external reinforced concrete works has commenced with detailing of the bulking bay, fire tank and pump house slabs in progress. • The design of the gulley waste apron has been amended to reflect additional comments received from RE3 and will be re-issued shortly. • Piling layouts from gridline 16-19 are in the process of being finalised to enable continuation of the piling works. • The application for the proposed potable water connection continues to be progressed with Thames water. • Detailed design of the Phase 1 Masonry has continued with drawings issued for the bulking bays, HWRC and transfer station. Central Berks Waste PFI Project Date of Issue: 3.08.07 Progress Report 8 Page No: 4 of 7

• Detailed design of the HWRC MCC room and mess facility has been completed. • Detailed design of the fire protection system has continued with layouts for the pump house, fire tank and sprinkler layout submitted for comments.

MRF – Preliminary design The second generation of MRF drawings have now been issued and a review meeting held. The trommel has been delivered to site and erected.

2.2Longshot

The planning conditions are currently being reviewed prior to commencement of design.

3 CONSTRUCTION, PROCUREMENT - COMMISSIONING AND OPERATION

3.1Construction

Phase 1 – Main Site

Clugston are preparing the stone Piling carpet to Grid line 19 and piling works are due to commence on the 13th August Grid lines 16 -19.

Pushwalls and Pilaster are now complete up to grid line 16 for the phase 1 works.

Structural Steel frame is now complete in the HWRC and the bulkbay areas, works are progressing as programmed in the transfer station area.

Concrete floor slab area within the HWRC is due to complete by the early next week and will continue into the transfer floor section.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
08 -July 07 Monthly ReportReport 106 KB DownloadRead as text
PDF
Works Delivery Progress ReportReport 23 KB Download

At this meeting

Whole meeting

Who was there

5 of 6 attended
MM
Councillor Mrs Mary Ballin CONCommittee Member, present
RS
Councillor Rob StantonPublic, present
SW
Steve WaitePublic, present
SW
Councillor Simon WeeksPublic, present
DH
Councillor Dorothy Hayes CONCommittee Member, present
BT
Mrs Bet TicknerSandhurst Town Council, apologies

On this subject at Bracknell Forest

Search all
  1. Works Delivery Progress ReportThis decision
  2. Works Delivery Progress ReportNoted
  3. Works Delivery Progress ReportNoted

More from Bracknell Forest Joint Waste Disposal Board

All decisions
MeetingDecisionOutcome
11 Jun 2026 Election of ChairRESOLVED that Councillor Finn McGoldrick be elected Chair of the Board for the municipal year 2026/27. Decided Open
11 Jun 2026 Election of Vice-ChairRESOLVED that Councillor Stephen Newton be elected Vice-Chair of the Board for the municipal year 2026/27. Decided Open
11 Jun 2026 re3 Progress ReportRESOLVED that 1 the contents of this report be noted. 2 a proposal on the simplification of the DIY charging structur... Noted Open
11 Jun 2026 re3 Strategy ReportRESOLVED that 1 the re3 Strategy 2026–2031 be approved and progressed through each partner council’s decision-making ... Approved Open
11 Jun 2026 re3 Finance Report - part oneRESOLVED that the year end financial position for FY25/26 be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies