RESOLVED that i ) the progress made in the areas of the EPC Contract and Planning since the last meeting on 20 June 2007 be noted; and ii) it be noted that there may be some delay in the commissioning of the Energy from Waste facility at Lakeside.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
Progress is being maintained throughout the works element with exception to the Cladding element due to delays in the material deliveries, although the roof sections of the cladding works are on critical path for releasing the works to the following trades ie Fire Suppression and M&E, the closing of the building perimeter walls is not yet critical. We are currently reporting a penetration of 18 days into the Phase 1 Buffer, which still reports an anticipated handover of the 1st Phase 4 weeks earlier then the contract Practical completion date.
1 HEALTH SAFETY & ENVIRONMENTAL
There have been no reportable accidents in the period.
ACCIDENT and INCIDENT RECORD In Period To date Reportable 0 0 Non reportable 0 0 Near Misses 20 118
Total Site Man Hours to date without a Lost Time Accident (LTA) = 44995
Testing of the discharge point (upstream/downstream) has been implemented by the JV. All test results are positive as anticipated to date.
1 DESIGN
2.1Smallmead
This period has seen the continued development of the reinforced concrete works and structural steelwork design. Electrical and Mechanical works have also continued.
Overall progress is summarised below:
• Design of the site access works and entrance has been revised following feedback and is currently being updated prior to issue to the planning authority. • Design of the external reinforced concrete works has commenced with detailing of the bulking bay, fire tank and pump house slabs in progress. • The design of the gulley waste apron has been amended to reflect additional comments received from RE3 and will be re-issued shortly. • Piling layouts from gridline 16-19 are in the process of being finalised to enable continuation of the piling works. • The application for the proposed potable water connection continues to be progressed with Thames water. • Detailed design of the Phase 1 Masonry has continued with drawings issued for the bulking bays, HWRC and transfer station. Central Berks Waste PFI Project Date of Issue: 3.08.07 Progress Report 8 Page No: 4 of 7
• Detailed design of the HWRC MCC room and mess facility has been completed. • Detailed design of the fire protection system has continued with layouts for the pump house, fire tank and sprinkler layout submitted for comments.
MRF – Preliminary design The second generation of MRF drawings have now been issued and a review meeting held. The trommel has been delivered to site and erected.
2.2Longshot
The planning conditions are currently being reviewed prior to commencement of design.
3 CONSTRUCTION, PROCUREMENT - COMMISSIONING AND OPERATION
3.1Construction
Phase 1 – Main Site
Clugston are preparing the stone Piling carpet to Grid line 19 and piling works are due to commence on the 13th August Grid lines 16 -19.
Pushwalls and Pilaster are now complete up to grid line 16 for the phase 1 works.
Structural Steel frame is now complete in the HWRC and the bulkbay areas, works are progressing as programmed in the transfer station area.
Concrete floor slab area within the HWRC is due to complete by the early next week and will continue into the transfer floor section.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.