CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bracknell Forest Council
Joint Waste Disposal Board, Wednesday 20 June 2007 at 6.00pm

Works Delivery Progress Report

Noted Committee 3 papers

Joint Waste Disposal Board noted this item on Wednesday 20 June 2007. Below is the council's own wording, with the papers it was decided on.

Item40

Resolved

RESOLVED that the progress made in the areas of the EPC Contract and Planning since the last meeting on 28 March 2007 be noted.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Joint Waste Disposal Board

Summary

Overall progress has been maintained and the piling works for Phase one are now complete.

Civil works to the building envelope is currently on programme and due to be complete up to Grid line 8, to enable Structural Steel to proceed, in early June as the target programme.

Floor slab works are to proceed in May in the area of grid lines 4- 8

Access has been agreed and area taken on site to grid line 16 to which piling is complete to.

1 HEALTH SAFETY & ENVIRONMENTAL

There have been no reportable accidents in the period.

ACCIDENT and INCIDENT RECORD In Period To date Reportable 0 0 Non reportable 0 0 Near Misses 5 28

Total Site Man Hours to date without a Lost Time Accident (LTA) = 18963

Testing of the discharge point and upstream/down stream testing has been implemented by the JV and it being carried out by German Consulting, all test results are positive as anticipated to date.

1 DESIGN

2.1Smallmead

This period has seen the continued development of the site drainage works, methane protection system, reinforced concrete works and structural steelwork design. Electrical and Mechanical works have also continued.

Overall progress is summarised below:

• Design of the site access works and entrance continue to be developed. Details will be submitted to the planning authority once complete. • Design of the reinforced concrete works has continued with detailing of the HWRC floor slab, bulking bays and wall to gridline 13 complete. Detailing of the transfer station walls and slab nearing completion. • An application for the proposed potable water connection has been submitted to Thames water. • Detail design of the main structural steelwork has continued and is now largely complete. Fabrication drawings are nearing completion and will be issued to RE3 for approval early May 2007. Central Berks Waste PFI Project Date of Issue: 4.5.07 Progress Report 5 Page No: 4 of 7

• Building elevations have now been updated to show louvre and fan positions and will be issued shortly to RE3 for approval. • Enquiries have been submitted to suppliers for the fire protection system and with a view to obtaining RE3 approval for chosen supplier by the end of May 2007. • A composite services drawing has been prepared showing the provisional layout of services required on site. MRF – Preliminary design Following the initial review meeting held on site with RE3, a formal review of the basic design information submitted by OKLM has been carried out. Further development is now taking place to incorporate comments raised, prior to commencement of the detailed design and re-issue of updated drawings. A site visit to OKLM plants in Germany has been arranged for 2-4 May 2007.

2.2Longshot

Revised planning drawings have been prepared and submitted. Further design work is on hold until planning permission has been granted.

3 CONSTRUCTION, PROCUREMENT - COMMISSIONING AND OPERATION

3.1Construction

Phase 1 – Main Site

Access has been agreed and provisions in place for the Existing CA to relocate bins to new areas provided by the JV to allow piling to progress to grid line 16.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
05 -April 07 Monthly ReportReport 103 KB DownloadRead as text
PDF
06 -May 07 Monthly ReportReport 103 KB Download
PDF
Works Delivery Progress ReportReport 21 KB Download

At this meeting

Whole meeting

Who was there

5 of 6 attended
MM
Councillor Mrs Mary Ballin CONCommittee Member, present
DH
Councillor Dorothy Hayes CONCommittee Member, present
RS
Councillor Rob StantonCommittee Member, present
SW
Steve WaiteCommittee Member, present
SW
Councillor Simon WeeksCommittee Member, present
BT
Mrs Bet TicknerCommittee Member, apologies

On this subject at Bracknell Forest

Search all
  1. Works Delivery Progress ReportThis decision
  2. Works Delivery Progress ReportNoted
  3. Works Delivery Progress ReportNoted

More from Bracknell Forest Joint Waste Disposal Board

All decisions
MeetingDecisionOutcome
11 Jun 2026 Election of ChairRESOLVED that Councillor Finn McGoldrick be elected Chair of the Board for the municipal year 2026/27. Decided Open
11 Jun 2026 Election of Vice-ChairRESOLVED that Councillor Stephen Newton be elected Vice-Chair of the Board for the municipal year 2026/27. Decided Open
11 Jun 2026 re3 Progress ReportRESOLVED that 1 the contents of this report be noted. 2 a proposal on the simplification of the DIY charging structur... Noted Open
11 Jun 2026 re3 Strategy ReportRESOLVED that 1 the re3 Strategy 2026–2031 be approved and progressed through each partner council’s decision-making ... Approved Open
11 Jun 2026 re3 Finance Report - part oneRESOLVED that the year end financial position for FY25/26 be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies