RESOLVED 1. That the Commitment Budget for the period 2008/09 to 2010/11, summarised in Table 1 of the Director of Corporate Services’ report, be approved. 2. That the proposed budget process for 2008/09 as set out in section 10 be supported.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
2.1That the Commitment Budget for the period 2008/09 to 2010/11, summarised in Table 1, be approved.
2.2That the proposed budget process for 2008/09 as set out in section 10 be supported.
Reasons for recommendations
3.1The recommendations are designed to allow the Executive to start to consider an appropriate budget strategy for 2008/09 and beyond.
Alternative options considered
4.1Background information relating to the options considered is included in the report.
5 SUPPORTING INFORMATION
Commitment Budget 2008/09-2010/11
5.1The preparation of the Commitment Budget for the coming three year period brings together the Council’s existing expenditure plans and is the first formal stage in planning for the revenue budget for 2008/09. . The Council’s Commitment Budget is shown in detail in Annexe A and summarised in Table 1.
Table 1: Commitment Budget 2008/9-2010/11
Department Plans Base Planned Expenditure Budget 2007/08 2008/09 2009/10 2010/11 £m £m £m £m Base Budget 67,648 67,648 70,622 71,946 Movements in Year 2,974 1,324 1,072 Adjusted Base 62,432 70,622 71,946 73,018 5.2 The table above illustrates the Council’s current planned spending. The Commitment Budget is based upon the approved 2007/08 budget adjusted to exclude the effects of drawings from balances, and takes account of approved existing commitments, including the full-year effect of pressures and economies approved for the 2008/09 budget. The significant changes to those previously agreed are identified as follows:
Customer Contact The planned savings of £0.105m through the expansion of the role of Customer Services across all Departments is linked to the Council’s move into new accommodation which is currently predicted to be in 2010 therefore the savings are forecast in 2010/11;
Landfill Tax/Waste PFI The level of landfill tax has increased from £3 to £8 per tonne and this has now been reflected in the commitment budget - as a result of increased tonnage of waste being recycled the impact of the increased landfill tax has been reduced.
Local Development Framework This is the overall description given to the planning process following the enactment of the Planning and Compulsory Purchase Act 2004. The continuously rolling programme (local Development Scheme) consists of a number of local development/supplementary planning documents. This budget is to produce, consult submit, inspect and adopt these plans. As such the budget profile for 2008/09- 20010/11 has been adjusted to reflect changes to the plans being prepared. In particular the development management document has been split into two parts with the housing /commercial sites being undertaken in 2008/09 and the remainder in 2010/11. In addition the Council plans to complete the development plan document for the area north of Whitegrove in 2010/11.
Invest to Save Capital Schemes The Council in setting it capital programme for 2006-07 and 2007/08 included an allocation of £1m for such Invest to Save schemes. These capital schemes are approved only where the additional revenue income or savings arising from their implementation exceeds the additional revenue costs. To date £668,000 of Invest to Save schemes have been approved and are detailed in the following table:
Table 2 Invest to Save Scheme approved
Scheme Capital Annual Revenue Cost Saving £ £ Easthampstead Park - Bedroom refurbishments 170,000 22,750 Energy Efficiency measures across council 126,000 32,840 buildings Upgrade of SmartConnect 50,000 15,000 Portman Close ( part refurbishment) 85,000 7,500 Automatic power tees at Downshire Golf 45,000 9,250 Course Server refresh & consolidation 192,000 53,000 TOTAL 668,000 140,340
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.