RESOLVED that i ) the progress made since the last meeting on 20 June 2007 be noted; ii) the final version of the joint Municipal Waste Management Strategy would be received at the December meeting; iii) a report and presentation on the subject of the redevelopment of Longshot Lane from re3 Ltd would be received at the next Board Meeting; and iv) the contribution made to the re3 project by Jon Freer be noted.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
2.1To note progress made since the last meeting on 20 June 2007.
2.2That Members agree to receive the final version of the joint Municipal Waste Management Strategy at the December meeting.
2.3That Members agree to receive a report and presentation on the subject of the redevelopment of Longshot Lane from re3 Ltd at the next Board Meeting.
2.4That Members note the contribution made to the re3 project by Jon Freer and record, on behalf of everyone involved in the project, their thanks for all his hard work and dedication.
3. SUPPORTING INFORMATION
Background
3.1The Joint Waste PFI Contract was signed with WRG on 31 October 2006. After a short mobilisation period, the service commenced on 4 December 2006, when WRG took on the management of the two Key Project Facilities in Bracknell and Reading and the Bring Banks within each of the three councils.
Operations
3.2Following the last report to the Joint Waste Board (in which the problems over the Easter period at Longshot Lane were reported), operations at the two main sites have been better with no significant service failures.
3.3WRG have been working on a new bring bank schedule with their sub-contractors. The aim of this new schedule is to match the emptying requirements at sites with the schedule.
3.4Following the last Board meeting, the number of missed emptyings has reduced. The Performance Reports for May and June are appended to this report. The number of missed empytings (at Table D1 in each report) is down from 109 in May to 15 in June.
3.5WRGB Ltd, who operate the facilities and haulage of waste for re3 Ltd, have been managing the inputs of green waste to Planners Farm. In liaison with the site operators at Planners Farm deliveries have been scheduled to minimise problems on site. In particular this involves avoiding deliveries on Mondays and, at short notice, when wind direction is unhelpful. The formal sub contract with the facility is due to be concluded before the end of September.
3.6The Project Director and Project Manager have engaged in a number of discussions with the contractor on the issue of partnership. We’ve felt that communication between, on one hand, re3 Ltd (the Contractor) and their sub-contractors, and on the other, re3 Ltd and the council’s project team can and ought to be improved.
3.7We feel that there needs to be a greater commitment to partnership on their part and that this is the only way in which the necessary relationships can be developed to ensure both parties add value to the project as intended and ensure its success.
Communications, Education and Waste Minimisation
3.8Following the award of funding by DEFRA, secured for the three councils by Janet Dowlman (BFBC), Officers from the three councils and re3 Ltd have been meeting with consultants from Enviros to develop a joint Municipal Waste Management Strategy.
3.9The Strategy is now in a draft form and has been placed on the three council websites and the re3 website (re3.org.uk) for public consultation. The closing date for the consultation is 30 September 2007.
3.10Following the end of the consultation, Officers will revise the strategy and present it to the Joint Waste Disposal Board for consideration. If the Board is able to approve the strategy at that point, it will need to be recommended for adoption by the individual councils.
3.11The councils’ project team requested re3 Ltd to procure the services of a waste consultancy to undertake a waste composition analysis. MEL, the chosen consultant, undertook the work in June of this year. The cost of the analysis was £30,000 to which each council contributed £5,000 the balance being a project cost.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.