Resolved
RESOLVED that progress on risk management at the Council be noted.
Governance & Audit Committee noted this item on Monday 29 June 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that progress on risk management at the Council be noted.
1.1Risk management forms a key part of the Council’s corporate governance and internal control framework and should form part of all decision-making and policy- making. The purpose of this report is to provide the Governance and Audit Committee with an update on the progress on risk management at the Council.
2.1The Governance and Audit Committee to note the progress on risk management at the Council.
3 ADVICE RECEIVED FROM STATUTORY OFFICERS
Borough Solicitor
3.1There are no legal implications to this report.
Borough Treasurer
3.2Nothing to add to this report.
Strategic Risk Management
3.3A robust Risk Management Strategy and Toolkit provides a sold basis for effective risk management. Risks recorded in registers support risk assessment for the decision making process and it is therefore vital to ensure that the Strategic Risk Register is reviewed and updated on a regular basis and reported to Members and that there are action plans in place to address risks.
Equalities Impact Assessment
3.4Not applicable.
4 SUPPORTING INFORMATION
Strategic Risk Register
4.1The 2007/08 Internal Audit review of the Council’s risk management arrangements reported weaknesses prior to 2008 in procedures for reviewing strategic risks and reporting these to Members. The Strategic Risk Register has been updated, reviewed by the Strategic Risk Management Group (SRMG) and agreed by the Corporate Management Team (CMT) on a quarterly basis since January 2008. The Executive now reviews and approves the Register twice a year and the approved Register is available on the Council’s intranet for staff to refer to when making risk assessments. 4.2 The Register was last updated in April 2009 and following review by SRMG on 29 April was considered by CMT on 20 May 2009 before being approved by the Executive on 16 June 2009.
4.3During 2008/09, the risk register for the Bracknell Forest Partnership was updated with the assistance of a strategic risk consultant from Zurich and actions plans to address the risks identified were agreed in early 2009.
Strategic Risk Action Plans
4.4To ensure effective risk management, once risks above our tolerance level have been identified we need to consider how we can respond to manage these risks, develop plans to set out proposed actions and responsibilities and monitor progress on actions. Risks may be managed by:
• Controlling the risk • Transferring the risk • Modifying the risk • Avoidance; or • Acceptance
4.5The need to develop and document action plans for our strategic risks over the tolerance level determined by CMT was included in Zurich Municipal’s report on the development of the Strategic Risk Register and in the 2007/08 Internal Audit report on risk management. Risk owners first completed documenting their action plans for the strategic risks assigned to them in October 2008 with the assistance of the Head of Audit and Risk Management and these were reviewed at CMT on 26th November and by the Executive on 16th December 2008. Service Plans for 2009/10 now include an annexe with each risk owner’s strategic risk action plans.
4.6Risk owners were asked to provide details of the progress on their risk action plans as at 31 December 2008. These were reported to the Overview and Scrutiny Commission on 19 March 2009. Quarterly Performance Monitoring Reports have included updates on progress against strategic risk action plans since quarter 4 of 2008/09.
Risk Management Strategy and Toolkit
4.7The Risk Management Strategy incorporating the Risk Management Policy has been revised and a Risk Management Toolkit has been developed to assist managers in identifying, evaluating and managing risks. Both documents were reviewed by SRMG on 5th January 2009 and by CMT on 25th March 2009 and were amended to take on board suggested amendments. The Risk Management Strategy was approved by the Executive on 14 April 2009 and together with the Toolkit was publicised in the June edition of Forest News.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Risk Management UpdateReport | 57 KB | DownloadRead as text |
Follow Governance & Audit Committee at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Minutes of previous meetingRESOLVED that, the minutes of the meeting of the committee held on the 17 June 2026 be approved as a correct record, ... | Approved | Open |
| 16 Sep 2026 | External Audit Update 2025/26 Financial StatementsThat the update be noted. | Noted | Open |
| 17 Jun 2026 | Minutes of previous meetingRESOLVED that, subject to the amendments above, the minutes of the meeting of the committee held on the 18 March 2026... | Approved | Open |
| 17 Jun 2026 | Annual Governance Statement 2026RESOLVED that the draft Annual Governance Statement (“AGS”) and Action plan appended to this report be approved. | Approved | Open |
| 17 Jun 2026 | Annual Standards Report 2025-2026RESOLVED that the Standards outputs in 2025/26 as set out in Appendix B be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.