Resolved
RESOLVED that the contract for Phase 2 of the expansion of Meadow Vale Primary School be awarded to Tenderer B subject to the final lump sum not exceeding the amount set out in section 22 of the Restricted Appendix.
Executive decided this item on Tuesday 21 May 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the contract for Phase 2 of the expansion of Meadow Vale Primary School be awarded to Tenderer B subject to the final lump sum not exceeding the amount set out in section 22 of the Restricted Appendix.
1.1The purpose of the report is to seek approval to award the contract for the final Phase 2 of the expansion of Meadow Vale Primary School under the Education Capital Programme previously approved by the Executive.
2.1That the Executive approves the award of contract for Phase 2 of the expansion of Meadow Vale Primary School to Tender B subject to the final lump sum not exceeding the amount set out in section 22 of the attached Restricted Appendix.
3.1The value of this contract requires Executive approval under the Council’s Contract Standing Orders.
4.1A masterplan has been undertaken to identify different options for the expansion of the school buildings which has been subject to consultation and agreement with the Headteacher and Governing Body.
4.2Doing nothing is not an option because the Council has a statutory duty to provide sufficient pupil places.
5. SUPPORTING INFORMATION
5.1The expansion of Meadow Vale primary school from 2FE to 3FE (630 places) forms part of the Education Capital Programme approved by the Executive in February 2012 and is also set out in the school Capacity Strategy approved by the Executive in October 2012.
5.2The expansion of Meadow Vale Primary School commenced in 2012 with the Phase 1 works to create 3 additional Key Stage 1 classrooms, which completed in time for the start of the 2012 autumn term. Unrestricted
Meadow Vale Phase 2
5.3The final Phase 2 works, which are the subject of this report, includes construction of 3 new classrooms, group spaces and an SEN room to complete the expansion of this school from 2FE to 3FE in all year groups, for a total of 210 additional school places. This additional form of entry will be in place for many years to come.
5.4Pupil numbers have already justified the expansion of the school which was full to its Published Admission Number of 90 in September 2012 and is forecast to be full again to 90 for September 2013, and in the foreseeable future.
5.5The recommended contractor has been selected on the basis of best value for money through the Council’s established procurement and tender evaluation process. The tender returns have been evaluated 40% quality and 60% price. The final evaluation score summaries can be found in Table Four of the attached Restricted Appendix A.
Timescales
5.6The programme for the Phase 2 Works is set out on Table One below:
Table One: Meadow Vale Programme Executive approval of Capital programme, including funding February 2012 for expansion of Primary schools Education Capital Programme Board approves plans for May 2012 proposed expansion Executive approval of Capacity Strategy to complete the October 2012 expansion of Meadow Vale Primary Executive Member approval of the Procurement Plan October 2012 Competitive Tenders February-March 2013 Executive approval to Award of Contract May 2013 Contract mobilisation May 2013 Works on Site June-December 2013 Handover and commissioning December 2013
Costs and Funding
5.7Funding for this contract has already been approved by the Executive as part of the Education Capital Programme and utilising funds from the 2012 / 2013 Basic Need Grant allocation.
6. ADVICE RECEIVED FROM STATUTORY AND OTHER OFFICERS
Borough Solicitor
6.1The Procurement has been carried out in accordance with the Council's contract standing orders and as the contract value is below the relevant statutory threshold, the Public Contracts regulations are not engaged. Unrestricted
Borough Treasurer
6.2The Borough Treasurer is satisfied that the Council has allocated sufficient resources to the Meadow Vale Scheme to finance the proposed contract.
Equalities Impact Assessment
6.3All new construction will be fully accessible to disabled pupils, staff and visitors.
Strategic Risk Management Issues
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Education Capital Programme: Meadow Vale Primary School Award of ContractReport | 76 KB | DownloadRead as text |
Follow Executive at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2024 | Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... | Noted | Open |
| 17 Sep 2024 | Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... | Agreed | Open |
| 17 Sep 2024 | Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. | Approved | Open |
| 17 Sep 2024 | Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... | Noted | Open |
| 17 Sep 2024 | Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.