It was agreed that data relating to the contamination of waste collections would be useful information to have so that specific areas could be targeted in order to encourage increased levels of recycling and composting. RESOLVED that the Board endorse the proposed approach to public consultation, as set out in the Project Director’s report, be undertaken by officers from the re3 councils and the re3 Project Team and any comments received be reported by to the Board for consideration.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
2.1That Members endorse the proposed approach to public consultation, as described, to be undertaken by officers from the re3 councils and the re3 Project Team.
3. SUPPORTING INFORMATION
Background
3.1Following agreement of the Project Initiation Document for a Waste Strategy at the October 2012 JWDB meeting, a draft Strategy was developed by officers of the re3 Project Team and presented to the JWDB on 5th September 2013.
3.2Members approved a programme which scheduled the presentation of a further draft and a proposal for further consultations for the JWDB meeting of December 2013.
3.3It was proposed that each Council should consult (internally) on the Strategy document and that suggested amendments should be forwarded to the re3 Project Team.
3.4The re3 Project Team held a briefing with officers from each of the councils on February 19th 2014.
3.5Officers have agreed a format for consulting with stakeholders on key aspects of the joint re3 Waste Strategy.
Proposal for Consultation
3.6Waste collection and management is a strategically important service delivered by the re3 councils both individually and collectively.
3.7As discussed at the officer briefing on February 19th 2014, the councils will agree a common set of consultation questions. Each question will be pertinent to the waste strategy and/or the development of waste services within the re3 area.
3.8Once the consultation is prepared, the re3 councils will then undertake a single consultation or three identical consultations (one in each area) depending on which approach is most efficient. In essence this should be a minor issue and one made necessary only by consideration, for example, of the potential differences in sign-off for consultations that exists between the three councils.
3.9The councils have agreed to incorporate the findings of the consultation in a further draft of the re3 Waste Strategy and/or the relevant waste services. BACKGROUND PAPERS
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.