Office Accommodation Strategy - Progress Report

Noted Executive 1 paper

Executive noted this item on Tuesday 23 September 2014. Below is the council's own wording, with the papers it was decided on.

Item15e

Resolved

RESOLVED that: The progress made on the first phase of the Office Accommodation Strategy be noted The work being undertaken on Phase 2 be endorsed
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Executive

Purpose of report

1.1In order to support the Council’s medium term objective “To build a vibrant Town Centre that residents are proud of”, the Council carried out considerable analysis of the requirements for its customer access points and office accommodation. The result of this work was the Office Accommodation Strategy, agreed by the Executive in July 2011 which outlined a number of actions to be completed to improve the use of the council estate and support regeneration.

Recommendations

2.1That the Executive notes the progress made on the first phase of the Office Accommodation Strategy

2.2That the Executive endorses the work being undertaken on Phase 2

Reasons for recommendations

3.1To allow the rationalisation of the Council’s property portfolio to progress and achieve the changes agreed in the Office Accommodation Strategy.

Alternative options considered

4.1There were a range of options for the phase 2 Easthampstead House works schedule including moving the minority groups room to 2nd floor but there was insufficient free space available. Other options were to move the mayoral suite and use the fourth floor as the space for the Construction and Maintenance team.

5 SUPPORTING INFORMATION

5.1The Office Accommodation Strategy, July 2011 was underpinned by a number of key principles:

Rationalising the amount of accommodation that the Council occupies; Locating customer facing staff in the town centre; Accommodation to be accessible and within the outer town centre ring-road; Modernising customer service delivery and provide one point of contact for the public; Locating the democratic function (Council Chamber and associated meeting/office space) in the town centre to enable public access; Staff working within their service teams; Staff working space allocation of approximately 1:8-9m2 ; The adoption of flexible working practices for staff; Shared meeting spaces to reduce the Council’s overall requirements.

E:\moderngov\Data\AgendaItemDocs\0\7\7\AI00043770\$oohdpsnf.doc Unrestricted

5.2The last year has seen significant progress with the complete refurbishment of Time Square as a cornerstone to achieving many of the agreed principles and actions identified in the Office Accommodation Strategy.

5.3Use of town centre accommodation The strategy set out a number of objectives for the use of the Council’s office accommodation:

 Decommissioning of Seymour House  Space principles for office accommodation  Customer improvements  Efficiency improvements  Maintenance

5.3.1 Decommissioning Seymour House/ Ocean House

Seymour House was required for the redevelopment of the town centre. BRP provided the opportunity to relocate staff temporarily from Seymour House to Ocean House for the duration of the works programme in Time Square. Seymour House was demolished in the first phase of the preparation for the Northern Retail Quarter. CYPL moved to floors 1 and 2 of Ocean House in March 2013 while work progressed in Time Square. Ocean House was vacated in May 2014 and the Property Team are currently in negotiations with the landlord and management team to agree the next stages in the handover.

5.3.2 Space principles for Office Accommodation

Space planning in line with flexible working principles was defined in the Office Accommodation Strategy. These have been complied with to provide a greater capacity in Time Square. As a result of the construction programme and the new offices layouts the number of occupants of the building has risen from 550 to 720.

The desk ratio for flexible staff had been set at 5:4 to provide approximately 8-9m2 per person. There has not been a wholesale replacement of furniture but where there was a need for replacements, the desks purchased are as described in the Strategy. All the departments in Time Square are now compliant with the desk ratio and have reduced their overall desk numbers to ensure that the building is able to accommodate the rise in occupancy comfortably.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Office Accommodation Strategy: Progress ReportReport 253 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 10 attended
KS
Katharine SimpsonClerk, expected
JD
Jemma DurkanClerk, expected
PB
Councillor Paul Bettison CONChair, apologies
AW
Councillor Alan Ward CONVice-Chair, in the Chair, present
DG
Councillor Dr Gareth Barnard CONCommittee Member, present
DB
Councillor Dale Birch CONCommittee Member, apologies
MB
Councillor Marc Brunel-Walker CONCommittee Member, present
MD
Councillor Mrs Dorothy Hayes MBE CONCommittee Member, present
IM
Councillor Iain McCracken CONCommittee Member, present
CT
Councillor Chris Turrell CONCommittee Member, present

More from Bracknell Forest Executive

All decisions
MeetingDecisionOutcome
17 Sep 2024 Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... Noted Open
17 Sep 2024 Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... Agreed Open
17 Sep 2024 Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. Approved Open
17 Sep 2024 Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... Noted Open
17 Sep 2024 Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies