RESOLVED that: The work plan for the Business and Enterprise Service (BES) as set out at Annex One of the Assistant Chief Executive’s report be endorsed The draw down of funds from the Economic Development Reserve to fund the plan for the period up to 31 March 2016 be endorsed
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
1.1This report seeks the Executive’s endorsement to the work programme for the newly- established Business and Enterprise Service (BES) and requests authority from members to draw from the Economic Development Reserve to fund the plan for the period up to 31March 2016.
Recommendation
2.1That the Executive endorses the work plan for the Business and Enterprise Service (BES) as set out at Annex One and authorizes funds to be drawn down from the Economic Development Reserve to fund the plan for the period up to 31 March 2016.
Reasons for recommendation
3.1The Council’s sixth strategic priority is to “sustain economic prosperity” for the Borough. The Council has recently created a dedicated team to support the delivery of this priority and the team’s work plan is presented for endorsement.
Alternative options considered
4.1None. The work plan is a fundamental requirement to ensure that the new team has a clear and deliverable programme of work to support economic development within the borough.
5 SUPPORTING INFORMATION
5.1In 2012, members established a task group to better understand the local economy and the drivers of economic success in Bracknell Forest, to develop a council vision for business, and to set a direction to support that vision. Considerable work has been done since then including commissioning MORI research on business perceptions, establishing the member vision (set out in the draft work plan at Annex 1), and developing a practical approach to supporting economic success informed by an all-member workshop. Work has also been done to develop a promotional brand for the area for business.
5.2In December 2013, the Members endorsed the creation of a dedicated team in the Chief Executive’s Office to deliver support for business. Since then, that team has been recruited and is now in place. Their key progress over the past eight months include: securing £7m for the borough through the Local Growth Deal and supporting Honda UK HQ relocation into the borough. Unrestricted
5.3In parallel, the Council was successful in attracting funding from the Local Government Association to support the preparation of an economic development work plan. Consultants, Renaisi, were appointed to do this work which forms the basis for the attached initial work plan at Annex One. Given the importance of this issue to members, approval is sought for this programme of work.
5.4Appendix One sets out the delivery programme for the first thirty months of the new service. A key project within the work plan is to produce a robust, ambitious but achievable Local Economic Framework for the borough which will have a long term (ten-year) perspective. The plan will focus upon retaining existing businesses and helping to bring about the conditions where they can grow and thrive, attracting targeted inward investment, and supporting small and medium sized business and, wherever possible, generate indigenous enterprise, especially in the potentially high growth, technology- and knowledge-based sectors.
5.5It is envisaged that the Local Economic Framework will present five Economic Priorities (EP): These correspond to priorities in the Local Enterprise Partnership recently approved Strategic Economic Plan. For the avoidance of doubt, these are not set out in priority order.
EP ONE: Retention and engagement; EP TWO: Promotion and investment; EP THREE: Generating enterprise; EP FOUR: Skills and learning; EP FIVE: Infrastructure improvement.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.