Reactive Maintenance & Repair Contract Award

Decided Executive 1 paper

Executive decided this item on Tuesday 22 September 2015. Below is the council's own wording, with the papers it was decided on.

Item10f

Resolved

RESOLVED that the Measured Term Contract for Building & Engineering Maintenance and Repairs due to commence on 1 December 2015 be awarded to Tenderer B.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Executive

Purpose of report

1.1The current contract for Reactive Maintenance has been performed by Graham Facilities Management since taking over the contract from Rok Building Group in 2011 after Rok went into administration.

1.2The value of the contract has been estimated at approximately £700k per annum historically, but with certain elements now procured separately (as identified in 4.3 below) the actual annual contract value is likely to be more in the order of £350k - £500k per annum and therefore Public Contracts Regulations 2015 required that the contract be advertised in the Official Journal of the European Union (OJEU). This value can only be given as an estimate based on a model of the work likely to be carried out during the period. This is due to the nature of reactive maintenance work.

1.3Following advertising in OJEU using the Restricted Procedure, and a robust evaluation of tenders submitted from short-listed candidates, the purpose of this report is now to seek approval to award the new contract.

2 RECOMMENDATION 2.1 That the Measured Term Contract for Building & Engineering Maintenance and Repairs due to commence on 1 December 2015 is awarded to Tenderer B.

3 REASONS FOR RECOMMENDATION 3.1 To ensure that the Council has an effective and reliable contractor in place to deal with any ‘reactive’ maintenance issues that may arise.

3.2Failure to do so could result in costly implications for the Council, and could also impact on the services we are able to offer individuals within the Borough. A large number of schools have bought into the services provided by Construction and Maintenance and therefore benefit from the reactive maintenance service arising from this award. This links to Priority Four of the Council’s Medium Term objectives which seeks to ensure that the people within the Borough are safe at all times.

Alternative options considered

4.1The current operational model has been reviewed as part of the Facilities Category Strategy.

4.2One alternative option considered was a contractor framework for reactive maintenance consisting of local small to medium sized building contractors. However it became apparent, while investigating the feasibility of the contractor framework, that the creation of such a framework (i.e. marking and ranking the suppliers fairly and transparently as the Council is obliged to do under the Public Contracts Regulations) proved to be impractical in terms of supplier management for a contract of this nature which requires a quick response, often out of hours. Unrestricted

4.3As set out in the agreed Procurement Plan, it was considered prudent to procure a full reactive maintenance term contract as it ensures that the Council complies with the Public Contracts Regulations and has the necessary level of emergency cover in place. It was however considered important that the problems encountered with the current contract, (mainly associated with central office functions including failure to supply management reports and inefficient invoice processes), are addressed going forward as far as possible. The intention is to place greater emphasis on contract management and reporting and, to ensure greater flexibility, some specialist works have been removed from the new contract and are being tendered separately. These are as follows:-

1) PAT testing 2) Fixed electrical and emergency lighting testing 3) Fire alarm testing

This action has the added benefit of offering opportunities to the local business community to tender for these areas each of which is likely to appeal to a different list of specialist suppliers.

4.4The project team also evaluated the possibility of using an existing framework agreement, however no suitable framework agreements were identified.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Reactive Maintenance & Repair Contract AwardReport 251 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 8 attended
PB
Councillor Paul Bettison CONChair, apologies
DG
Councillor Dr Gareth Barnard CONVice-Chair, in the Chair, present
DB
Councillor Dale Birch CONCommittee Member, present
MB
Councillor Marc Brunel-Walker CONCommittee Member, present
MD
Councillor Mrs Dorothy Hayes MBE CONCommittee Member, present
PH
Councillor Peter Heydon CONCommittee Member, present
IM
Councillor Iain McCracken CONCommittee Member, present
CT
Councillor Chris Turrell CONCommittee Member, present

On this subject at Bracknell Forest

Search all
  1. Reactive Maintenance & Repair Contract AwardThis decision
  2. School Reactive MaintenanceNoted
  3. School Reactive MaintenanceNoted

More from Bracknell Forest Executive

All decisions
MeetingDecisionOutcome
17 Sep 2024 Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... Noted Open
17 Sep 2024 Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... Agreed Open
17 Sep 2024 Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. Approved Open
17 Sep 2024 Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... Noted Open
17 Sep 2024 Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies