Executive, Tuesday 20 June 2023 at 5.30pm

Strategic Procurement Plan Opladen Way Development

Approved Executive 2 papers

Executive approved this item on Tuesday 20 June 2023. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

RESOLVED that i. That the Executive approves this Strategic Procurement Plan (Appendix A) to tender the appointment of a main contractor under a Traditional building Contract to create up to seven new temporary homes. ii. The Executive delegates the award of the works contract to the Executive Member for Finance & Business Change in consultation with Executive Director Delivery.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Executive

Alternative options considered

4.1Discussions have been held with our JV partner, Countryside where they have advised that the project is too small to be developed under the Cambium Partnership.

5. Supporting Information

5.1Background Information

5.2During February 2023 the Executive approved the capital expenditure for the implementation of a temporary homes facility

5.2.1. This is a council-led development to provide up to seven new temporary homes for homeless households (refer to Appendix D). The proposal includes a mix of single person and family homes which will be provided at affordable rents. The council has access to a small stock of temporary accommodation to meet the needs of homeless households.

5.2.2. Currently there is a lack of one-bedroom units within this stock for temporary placement of single homeless people and increasing pressure on the available 3-bedroom properties for larger households. This can create accommodation and cost pressures resulting from the use of nightly paid accommodation. It is anticipated that because of the ongoing cost of living crisis, homelessness demand and temporary accommodation demand will increase. 5.2.3. There is an opportunity to develop additional temporary accommodation on vacant council-owned land at Opladen Way to help alleviate these pressures and avoid additional revenue costs to the council The proposal is for all properties on the site to be used as short-term temporary accommodation for homeless households, rather than permanent housing. The dwellings will be let on temporary homeless licences to single people and families until longer term housing is sourced, typically between 3 months and 2 years.

5.2.4. The design and amenities of the dwellings have been developed with this short-term use in mind, for example, by providing modest and low maintenance gardens, built in storage, and effective soundproofing between neighbouring properties. The proposed housing development has been designed to achieve net zero operational carbon and aims to achieve BREEAM very good rating. The final proposed development will be subject to further planning input via the planning application process.

5.3Timescales

Milestone Approximate Date Publish adverts in Contracts Finder and Southeast July 2023 Business Portal Deadline for returning Selection Questionnaires August 2023 Issue Invitation to Tender to shortlisted suppliers December 2023 Receive Response from Tenderers January 2023 Contract Award/Preferred Bidder March 2024 End of standstill period March 2024 Mobilisation Period from March 2024 Contract Start Date * April 2024 Contract Start Completion Date * May 2025 *start and completion dates for construction will be subject to the successful bid and approval of planning permission.

5.4Financial Analysis

Estimated Cost Breakdown – included within the strategic procurement plan (Appendix A).

6. Consultation and Other Considerations Legal Advice 6.1. Comments are included within the procurement plan (Appendix A).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Initial equalities screening record form (Final)Appendix B 90 KB Download
PDF
Strategic Procurement Plan Opladen Way DevelopmentReport 82 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
MT
Councillor Mary Temperton LabChair, present
KN
Councillor Kathryn Neil LabVice-Chair, present
RB
Councillor Roy Bailey LabCommittee Member, present
PB
Councillor Paul Bidwell LabCommittee Member, present
GG
Councillor Guy Gillbe LABCommittee Member, present
KJ
Councillor Kandy Jefferies LabCommittee Member, present
HP
Councillor Helen Purnell LabCommittee Member, present
MW
Councillor Megan Wright LabCommittee Member, present

On this subject at Bracknell Forest

Search all
  1. Strategic Procurement Plan Opladen Way DevelopmentThis decision
  2. Parking Management & Enforcement Strategic Procurement PlanApproved
  3. Casualty Insurance Tender Strategic Procurement PlanApproved
  4. Short Breaks for Children and Young People with Disabilities Strategic Procurement PlanApproved
  5. Strategic Procurement Plan - contractor frameworkApproved
  6. Education Transport Framework Strategic Procurement PlanApproved

More from Bracknell Forest Executive

All decisions
MeetingDecisionOutcome
17 Sep 2024 Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... Noted Open
17 Sep 2024 Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... Agreed Open
17 Sep 2024 Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. Approved Open
17 Sep 2024 Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... Noted Open
17 Sep 2024 Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies