Bracknell Forest Council
Cabinet, Tuesday 23 June 2026 at 6.30pm

Strategic Procurement Plan - contractor framework

Approved Executive 2 papers

AI summaryBracknell Forest Cabinet approves plan to set up an eight year Capital Works Framework of eight contractors for property and public realm projects, with an estimated ceiling of £80m.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedStrategic Procurement Plan and delegated authority approved
MoneyUp to £80m over 8 yearsIndicative framework ceiling, not guaranteed spend
What happens nextInvitation to tender expected 27/07/2026Contract start planned for 01/04/2027
Who it affectsCouncil buildings, schools, public realmConstruction contractors and property suppliers

What was decided

Cabinet approved the Strategic Procurement Plan in confidential Appendix A and delegated authority to the Executive Director of Place, in consultation with the Cabinet Member for Adults, Economy and Regeneration, to award and manage the framework. Report 3.1, 3.2, P10, P11, P12

The framework will be set up through a competitive tender as a single lot with eight appointed contractors, operating over eight years with formal opportunities to reopen the framework at years three and five. Report 6.2, P11

Bids will be evaluated on Price 60%, Quality 35% and Social Value 5%, with quality covering methodology, capacity, programme, risk, sustainability and cost certainty. Report 6.3

Why

The Council needs a consistent route to market to deliver its capital programme safely, on time and within governance rules, with better cost certainty and transparency than project by project procurement. Report P13, 4.2

A pre qualified supply chain is expected to cut lead in times, enable earlier contractor engagement, and standardise contract terms, KPIs and reporting. Report 4.3, 4.4

The framework embeds carbon reduction, sustainable construction, social value such as apprenticeships and local employment, and opportunities for SMEs and voluntary, community and social enterprises. Report 4.5, P18

What happens next

Corporate Procurement and the allocated Procurement Officer will finalise tender questions and scoring; the framework specification and call off process will be run under the Council's contract standing orders. Report P43, P12

Indicative timetable: ITT issued 27/07/2026, clarification deadline 10/08/2026, bids close 14/09/2026, evaluation to 14/10/2026, standstill ends 18/11/2026, contract award w/c 23/11/2026, contract starts 01/04/2027. Report 6.4, P29

Individual call offs will only proceed where there is an approved budget, and where required an approved business case, with affordability kept under review given construction cost volatility. Report 7.2, P36, 7.6

The money

  • £80m Estimated framework value over up to eight years, treated as an enabling ceiling rather than guaranteed spend Report P36
  • £2.5m 2026 to 2027 council funded capital for maintaining and investing in council buildings (excludes schools) Report P34
  • £1.1m Department for Education schools condition allocation capital maintenance grant for schools Report P34
  • £0.100m Typical upper size of revenue funded projects the framework may be used for Report P35

Options considered

  • Rejected: Do nothing or continue with project by project procurement. Resource intensive, longer lead in times, inconsistent market engagement and reduced programme certainty Report P19, 5.1
  • Rejected: Use existing public sector frameworks. Limited flexibility on local priorities, pricing, performance management and social value Report P21, 5.2
  • Rejected: Single supplier contract. Reduces resilience, limits market capacity and increases impact of supplier failure given the scale of the programme Report P23, 5.3
  • Rejected: In house delivery. Council lacks the internal capacity and specialist construction capability for the range and scale of works Report P25, 5.4
  • Chosen: Run a Council controlled eight year open Capital Works Framework with eight contractors in a single lot, reopened at years three and five. Provides value for money, transparency, resilience, SME access and ability to refresh competition in volatile construction markets Report 6.2, P40

Implications

  • Financial: No guaranteed spend is created; the £80m is an enabling ceiling, and call offs depend on approved capital and revenue budgets each year. Report 7.2, 6.2, P36
  • Risk: Key risks are construction cost volatility, market capacity and supply chain constraints, and variable contractor performance; mitigated through framework rates, KPIs, audit rights, multiple contractors, and reopening the framework at years three and five. Report 7.6, P48
  • Equalities: An Integrated Impact Assessment Screening Tool Report in Appendix B covers equalities, climate, ecology and wellbeing impacts; the framework supports inclusive procurement and local supplier and SME opportunities. Report 7.5, 7.7, 7.8, P46, P50, P52
  • Legal: Appropriate legal documentation must be put in place for the open framework and call off contracts, on advice from the Corporate Business Partner. Report 7.1, P31
  • Climate: Framework specification embeds carbon reduction, sustainable construction, efficient resource use, and whole life cost considerations. Report P18, 4.5
  • Staffing: Council officers rather than members will run call offs and awards, under delegated authority to the Executive Director of Place. Report 3.2, P10, P11, P12

Who and where

  • Bracknell Forest Council Property and Place teams, who will call off capital works through the framework Report 7.4, P44
  • Construction contractors and supply chain firms, including SMEs, Voluntary, Community and Social Enterprises, bidding for places on the framework Report 4.5, P18, P39
  • Schools, community facility users and building occupants, who will see planned works carried out under health and safety standards Report 7.8, P52
  • Residents and local communities, through engagement requirements and local employment opportunities Report P18, 7.5

Timeline

  • 27/07/2026: Invitation to Tender issued via ProContract Report 6.4, P29
  • 10/08/2026: Deadline for clarification questions via ProContract Report 6.4
  • 17/08/2026: Council responds to clarification questions Report 6.4
  • 14/09/2026: Closing date for receipt of bidder responses to the ITT Report 6.4
  • 15/09/2026 to 14/10/2026: Evaluation of ITT responses by the tender panel Report 6.4
  • Week commencing 02/11/2026: Bidders notified of award decision Report 6.4
  • 18/11/2026: Expiry of standstill period Report 6.4
  • Week commencing 23/11/2026: Contract award concluded Report 6.4
  • 30/11/2026: Contract details notice published Report 6.4
  • 01/04/2027: Commencement date of contract Report 6.4
  • Year 3 and year 5 of the framework: Formal opportunities to reopen the framework to new suppliers Report 6.2, P11
  • Eight year term: Overall length of the framework Report 6.2, P11

Plain English for the jargon

  • Capital Works Framework: An umbrella agreement with pre qualified contractors from which the Council can call off individual construction projects.
  • Open framework: A framework that can be reopened during its term to let new suppliers compete and join, used here at years three and five.
  • Call off: Awarding a specific project to a contractor already on the framework, rather than running a new tender.
  • ProContract: The Council's electronic tendering system used for the procurement.
  • ITT: Invitation to Tender, the formal request for suppliers to submit bids.
  • Standstill period: A pause after an award decision during which unsuccessful bidders can challenge the result before the contract is signed.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item111

Resolved

RESOLVED That the Cabinet: · Approves the Strategic Procurement Plan in confidential Appendix A. · Delegates authority to the Executive Director of Place, in consultation with the Cabinet Member for Adults, Economy and Regeneration, to o award and enter into a Capital Works Framework with the successful tenderers following completion of the procurement process o re-award the Capital Works Framework to new suppliers when there are new openings in the existing framework period of 8 years o approve project call?offs in accordance with the framework terms and Council governance arrangements via its contract standing orders.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Cabinet

To: Cabinet Member for Adults, Economy and Regeneration 23 June 2026

Capital Works Framework – Strategic Procurement Plan Executive Director: Place

1 Purpose of report 1.1 The purpose of this report is to seek approval to procure and establish a Capital Works Framework. The report sets out the strategic need, proposed scope, and procurement approach. It also seeks delegation of authority to officers to implement, award, and manage the framework arrangements.

2 Cabinet Member for Adults, Economy & Regeneration Introduction

2.1The Council seeks to appoint contractors capable of delivering capital works through an umbrella framework. Over the proposed contract term, the total contract value is expected to exceed the applicable threshold, requiring my recommendation for decision of Cabinet to the proposed confidential Strategic Procurement Plan.

2.2The Strategic Procurement Plan is provided in confidential Appendix A of this report and I am satisfied provides a well-reasoned and robust approach to the procurement of this essential service.

3 Recommendations That Cabinet:

3.1Approve the Strategic Procurement Plan in confidential Appendix A.

3.2Delegate authority to the Executive Director of Place, in consultation with the Cabinet Member for Adults, Economy and Regeneration, to

3.2.1 award and enter into a Capital Works Framework with the successful tenderers following completion of the procurement process

3.3.2 re-award the Capital Works Framework to new suppliers when there are new openings in the existing framework period of 8 years

3.2.3 approve project call-offs in accordance with the framework terms and Council governance arrangements via its contract standing orders.

4 Reasons for recommendations 4.1 The Council must maintain the ability to deliver its capital programme in a safe, compliant and timely manner across its estate and public realm, in accordance with statutory, contractual and governance obligations.

4.2The Strategic Procurement Plan sets out how the proposed Capital Works Framework will meet the Council’s value for money and transparency objectives through a compliant competitive procurement process and a strengthened commercial model, providing improved cost certainty and assurance.

4.3The establishment of a framework will ensure service continuity and consistent quality by providing access to a pre-qualified supply chain, reducing procurement lead-in times and enabling earlier contractor engagement on individual projects.

4.4The framework will support improved risk management and delivery performance by standardising contract terms, performance management arrangements, and reporting requirements across capital projects.

4.5The Council seeks to maximise diversity and inclusion, sustainability and social value outcomes through its procurement activity. The framework specification embeds requirements relating to:

• carbon reduction and sustainable construction practices; • efficient use of resources and whole-life cost considerations; • delivery of measurable social value, including apprenticeships, local employment, and supply-chain opportunities for Small and Medium Enterprises and Voluntary, Community and Social Enterprises; and • engagement with local communities and alignment with wider Council priorities.

5 Alternative options considered. Do nothing / Continue with project-by-project procurement

5.1This option has been discounted as continuing with individual procurement exercises for each capital project is resource intensive and leads to extended lead-in times, inconsistent market engagement, and reduced programme certainty. It does not provide a sustainable, inclusive or efficient approach for delivering the Council’s capital programme.

Use of existing public sector frameworks

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Integrated Impact Assessment Screening Tool ReportAppendix B 276 KB Download
PDF
Strategic Procurement Plan: contractor frameworkDecisions 125 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 9 attended
HP
Councillor Helen Purnell LABChair, present
GG
Councillor Guy Gillbe LABVice-Chair, present
PB
Councillor Paul Bidwell LABCommittee Member, present
IJ
Councillor Iskandar Jefferies LABCommittee Member, apologies
MW
Councillor Megan Wright LABCommittee Member, present
GP
Councillor Georgia Pickering LABCommittee Member, present
RF
Councillor Ryan Frost LABCommittee Member, present
SO
Councillor Stephen O'Regan LABCommittee Member, present
JB
Jamie BeardsmoreClerk, expected

On this subject at Bracknell Forest

Search all
  1. Strategic Procurement Plan - contractor frameworkThis decision
  2. Parking Management & Enforcement Strategic Procurement PlanApproved
  3. Casualty Insurance Tender Strategic Procurement PlanApproved
  4. Short Breaks for Children and Young People with Disabilities Strategic Procurement PlanApproved
  5. Education Transport Framework Strategic Procurement PlanApproved
  6. Bus Shelter Provision and Maintenance - Strategic Procurement PlanApproved

More from Bracknell Forest Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Children and Young Persons Participation Strategy 2026 - 31RESOLVED that Cabinet: APPROVES the Children and Young Persons Participation Strategy 2026-31 and action plan followi... Approved Open
22 Sep 2026 Council Plan Overview Report - Q1RESOLVED that Cabinet: · NOTES the performance of the council over the period from April to June 2026, highlighted in... Decided Open
22 Sep 2026 Forestcare Digital Telecare & Telecare & ARCRESOLVED that Cabinet: · APPROVES the procurement of digital telecare equipment required to support the transition fr... Approved Open
22 Sep 2026 Parking Management & Enforcement Strategic Procurement PlanRESOLVED that Cabinet: · APPROVES the approach detailed in the confidential annex for procuring the parking managemen... Approved Open