RESOLVED that Cabinet: i. notes the outturn expenditure for 2024/25, subject to audit, of £96.614m, which represents an underspend of -£0.742m compared with the approved budget. ii. approves the budget carry forward of £0.011m (see paragraph 6.9). iii. approves the earmarked reserves as set out in Annexe C. iv. approves the virements up to £0.100m relating to the 2024/25 budget (see Annexe D). RECOMMENDED that Council: i. notes the Treasury Management performance in 2024/25 as set out in Annexe B. ii. approves the virements over £0.100m relating to the 2024/25 budget (see Annexe D).
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
1 Purpose of report 1.1 The Council, at its meeting on 21 February 2024, approved a revenue budget for 2024/25 of £97.356m. This report informs Members of the outturn expenditure position, subject to audit, for the financial year 2024/25 highlighting that the Council underspent by -£0.742m and returned this amount to General Reserves.
1.2The Council continues to face ongoing financial pressures and uncertainty due to delays in the introduction of a new funding system by Central Government and increases in demand led pressures.
1.3The accounts and accounts regulations require the draft accounts to be published by the 30 June 2025 and the audited accounts by 28 February 2026. The draft accounts were signed on 09 June 2025 well ahead of the 30 June deadline.
2 Cabinet Member For Finance And Corporate Improvement 2.1 The report shows that in the financial year 2024/25, the Council underspent by £0.742 million against its approved revenue budget of £97.356 million and this surplus returned to General Reserves. There remains ongoing uncertainty from delayed national funding reforms and increased service demand.
2.2The Council has managed its finances effectively, recording a modest underspend and appropriately utilizing reserves. All statutory deadlines were met or exceeded, with no major restructuring costs incurred.
3 Recommendations It is recommended that Cabinet:
3.1Notes the outturn expenditure for 2024/25, subject to audit, of £96.614m, which represents an underspend of -£0.742m compared with the approved budget.
3.2Approves the budget carry forward of £0.011m (see paragraph 6.9).
3.3Approves the earmarked reserves as set out in Annexe C.
3.4Approves the virements up to £0.100m relating to the 2024/25 budget (see Annexe D).
3.5Recommends that Council note the Treasury Management performance in 2024/25 as set out in Annexe B.
3.6Recommends that Council approves the virements over £0.100m relating to the 2024/25 budget (see Annexe D). Unrestricted
4 Reasons for recommendations 4.1 The recommendations are intended to inform the Cabinet of financial performance against budget in the 2024/25 financial year.
5 Alternative options considered 5.1 The report sets out the Council’s actual financial performance in 2024/25 and the consideration of options is not therefore appropriate.
6 Supporting information General Fund Revenue Expenditure 2024/25
6.1The Council approved a revenue budget of £97.356m for 2024/25. In addition, a number of transfers to and from earmarked reserves have been made as normal during the year. These are shown in Table 1 below and explanations for the use of the reserves are set out in the following paragraphs.
Table 1: Transfers To/From Earmarked Reserves
Directorate Bus Other Structural All Other Total Contract S106 Changes Earmarked (S106) Reserves £’000 £’000 £’000 £’000 £’000 Central 161 561 0 1981 2,703 Communities 0 0 0 71 71 People 0 0 0 2,337 2,337 Non departmental / 0 -1,963 0 -1,084 -3,047 Councill Wide Transfer to/from -161 1,402 0 -3,305 -2,064 Earmarked Reserves Total 0 0 0 0 0
Bus Contract from S106 The bus contract was negotiated during the year with the funding to be provided from S106 resources.
Other S106 Revenue funding for staff and a vehicle involved in the production, co-ordination and monitoring of the Suitable Alternative Natural Green Spaces (SANGS) plans and the maintenance and management of SANGS areas have also been provided from S106 resources, as have transformation savings relating to Special Protection Areas. The non- departmental credit relates to the transfer of unapplied S106 for revenue purposes received in year to reserves.
Structural Changes There were no one-off costs associated with service restructuring proposals met from the Structural Changes Reserve during the year. Unrestricted
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report - Q1RESOLVED that Cabinet: · NOTES the performance of the council over the period from April to June 2026, highlighted in...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.