RESOLVED that the Cabinet: i. notes the outturn capital expenditure as outlined in Table 1. ii. approves carry forwards of £56.770m from the 2024/25 capital programme to 2025/26, including the specific schemes listed in Annex A. iii. notes the financing of capital expenditure as shown in Table 2.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
Capital Programme 2024/25 Outturn Executive Director: Resources
1 Purpose of report 1.1 At its meeting on 21 February 2024, the Council approved a capital programme for 2024/25-2026/27. This report informs Members of the outturn expenditure position, subject to audit, for the financial year 2024/25 and requests approval for the carry forward of the remaining capital programme, the majority of which is committed but not yet spent. The report also sets out how the 2024/25 expenditure is to be financed.
2 Cabinet member for (portfolio) Introduction 2.1 The total capital expenditure for 2024/25 was £38.725 million which is slightly under the budgeted £39.354 million and carry-forwards of £56.770 million requested to continue the work on long-term and multi-year projects. The total budget for the period is £96.124 million. The capital programme for 2024/25 is largely on track, with no significant overspending reported. However, several major projects, particularly in the Place and Communities directorates, require funding carry-forwards due to delays or multi-year execution timelines, such as the Warfield Community Hub, High Street Car park, Bridegwell and Safety Valve schemes. The overall outlook indicates a managed increase in borrowing to fund future capital investments, with careful monitoring of resources. The report highlights a risk to the revenue budget from the capital programme, though the outturn does align with expectations and minimizes that risk.
3 Recommendations 3.1 That the Cabinet:
a) Notes the outturn capital expenditure as outlined in Table 1 b) Approves carry forwards of £56.770m from the 2024/25 capital programme to 2025/26, including the specific schemes listed in Annex A c) Notes the financing of capital expenditure as shown in Table 2.
4 Reasons for recommendations 4.1 The reasons for the recommendations are set out in section 5 below.
5 Alternative options considered 5.1 Cabinet could decide not to support carry-forwards of unspent capital budgets, however that would mean that many schemes that are in progress would need to be aborted.
6 Supporting information Outturn Capital Expenditure Unrestricted
6.1Table 1 summarises the outturn position in 2024/25 for schemes managed by Directorates.
Place (incl. Joint Venture) 43.993 25.167 25.037 18.827 -0.130 Communities 18.906 3.640 3.424 15.266 -0.216 People - Schools 22.807 4.652 4.652 18.154 -0.001 People - Other 10.418 5.895 5.895 4.523 0.000
Total 96.124 39.354 39.008 56.770 -0.347
6.2Within the figures above are a small number of schemes where spending totalling £0.283m was transferred to revenue at the year end. The most significant was £0.275m for the Opladen Way scheme which Cabinet agreed at its meeting in October 2024 should no longer be progressed as it had become unaffordable, meaning previously incurred costs could no longer be funded from capital. As a consequence, the level of capital expenditure to be funded from capital resources in 2024/25 totalled £38.725m.
6.3The Capital Programme includes a mixture of short, medium and long-term projects, some of which will be delivered over more than one year. The approved capital programme budget approved for the period 2024/25 – 2026/27 is £96.124m, with £39.354m being the expected cash budget profile in 2024/25. Outturn expenditure (subject to external audit of the Council’s accounts) totalled £38.725m (40% of the total approved budget), with requested carry forwards to continue delivery of schemes being £56.770m (59% of the total approved budget). A commentary on the most significant carry-forward requests is provided at Annex A.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report - Q1RESOLVED that Cabinet: · NOTES the performance of the council over the period from April to June 2026, highlighted in...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.