AI summaryBracknell Forest Cabinet awards an interim nursing and residential care contract, starting in February 2026 for up to three years, after the current provider asked to end its contract.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedNursing and residential services in Bracknell Forest
MoneyFigures held in a confidential annex
What happens nextContract starts February 2026Up to three year interim term
Who it affectsCare home residents and providersTransition from current to new provider
What was decided
Cabinet approved an interim contract for the provision of nursing and residential services in Bracknell Forest, starting in February 2026 and running for no more than three years. Report P4
Authority to approve a change to the start date is delegated to the Executive Director: People, in consultation with the Executive Director: Resources. Report 3.2
Authority to negotiate and approve the exit agreement with the current provider and finalise transition to the new provider is delegated to the two Executive Directors, in consultation with the Cabinet Members for Adults and Public Health and for Finance and Corporate Improvement. Report 3.3
Why
The current provider does not feel able to continue under the existing terms, so a mutual termination has been agreed, and an interim award is needed to keep care running. Report P23, P24
The contract is required to meet the Council's statutory duties under the Care Act, including continuity of care, market shaping and contingency planning. Report P10
Officers from social care, commissioning, finance and procurement assessed the new provider on quality and value for money. Report 6.2
What happens next
Finalise the safe transition to the new provider, with delegated authority sitting with the Executive Directors and the two relevant Cabinet Members. Report 3.3
Run the interim contract under the Light Touch Regime of the Procurement Act 2023 while the Council reviews the longer term requirement. Report 6.3, P22
Alternative options considered during the process are recorded in a Confidential Annex, which was excluded from the public part of the meeting under Schedule 12A of the Local Government Act 1972. Report P11
Options considered
Chosen: Award an interim contract to a new provider so care continues. There is not enough time to complete a full procurement before the current provider's contract ends, and continuity of care is required under the Care Act. Report P24
Rejected: Alternative options considered during the process. Not stated in the public papers; details are in the Confidential Annex. Report P11
Implications
Legal: The award is made under the Light Touch Regime of the Procurement Act 2023 and is treated as above threshold; the existing contract with the current provider continues to be governed by the Public Contract Regulations 2015. Report P22, 7.1
Equalities: An Equalities screening was completed and concluded that a full Equalities Impact Assessment was not required, as eligibility is unchanged and the service model is not significantly changing. Report P26
Climate: The recommendations are expected to have no impact on CO2 emissions. Report P29, 7.6
Risk: Strategic risk management issues were taken into account; full details are in the Confidential Annex. Report P27, 7.5
Other: The service provider must deliver holistic care covering physical, health, emotional and social care needs to support the best possible health and wellbeing outcomes. Report P31, 7.7
Who and where
Adults receiving nursing and residential care arranged by the Council Report P4
The current provider of nursing and residential services, whose contract is being mutually terminated Report P23, P24
The new interim provider of nursing and residential services Report 6.2
Carers and families of people using the service Report P10
Timeline
16th December 2025: Cabinet considers and approves the award of the interim care contract. Report P2
February 2026: Interim contract is anticipated to start. Report P4
Not exceeding three years from start: Maximum term of the interim contract. Report P4
Plain English for the jargon
Care Act: The legislation that sets out the duties of local authorities in England regarding adult social care.
Procurement Act 2023: New UK procurement law that governs how public bodies buy goods, works and services.
Light Touch Regime: A procurement approach under the Procurement Act 2023 for certain health, social care and other service contracts, with more flexible rules.
Light Touch Regime of the Procurement Act 2023: The flexible procurement rules in the Procurement Act 2023 that apply to certain health and social care contracts above the threshold.
Mutual termination: An agreement between the Council and the current provider to end the contract by consent rather than for breach.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item55
Resolved
RESOLVED that I. An interim contract for the provision of nursing and residential services within Bracknell Forest is awarded. The contract is anticipated to start during February 2026, for a term not exceeding three years. II. The authority to approve changes in start date is delegated to the Executive Director: People in consultation with the Executive Director: Resources, should circumstances require a change in the commencement date of the new arrangements. Exclusion of Press and Public For the consideration of the final recommendation it was RESOLVED that pursuant to Regulation 4 of the Local Authorities (Executive Arrangements) (Access to Information) Regulations 2012 and having regard to the public interest, members of the public and press be excluded from the meeting for the consideration of item 10 which involves the likely disclosure of exempt information under the following category of Schedule 12A of the Local Government Act 1972: (3) Information relating to the financial or business affairs of any particular person. Private Session It was RESOLVED that the authority to take necessary actions to finalise the safe transition to a new provider is delegated to the Executive Director: People and Executive Director: Resources in consultation with the Cabinet Members for Adults and Public Health and Finance and Corporate Improvement.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
Award of Care Contract Executive Director: Grainne Siggins
1 Purpose of report 1.1 This report seeks approval to award an interim contract for nursing and residential services, anticipated to start during February 2026, for a term not exceeding three years.
2 Cabinet member for Adults & Public Health Introduction 2.1 As Cabinet Member for Adults & Public Health I fully support the recommendations set out in this report. These will ensure the quality, safety and continuity of care to residents and ensure the Council is meeting its statutory duties under the Care Act.
2.2Borough priorities: This contract contributes to the delivery of the priorities set out in the Council Plan to deliver Engaged and Health Communities and contributes towards the Council’s commitment to ensuring ‘Residents can access appropriate care, suitable for a changing population’.
3 Recommendations 3.1 To award an interim contract for the provision of nursing and residential services within Bracknell Forest. The contract is anticipated to start during February 2026, for a term not exceeding three years.
3.2To delegate authority to approve changes in start date to the Executive Director: People in consultation with the Executive Director: Resources, should circumstances require a change in the commencement date of the new arrangements.
3.3To delegate authority to negotiate and approve the exit agreement with the current provider on mutually accepted terms and finalise the transition arrangements to the new provider to the Executive Director:People and Executive Director: Resources in consultation with the Cabinet Members for Adults and Public Health and Finance and Corporate Improvement.
4 Reasons for recommendations 4.1 The contract will support the Council to deliver its statutory duties under the Care Act. The Care Act requires Local Authorities to: • Meet the needs of people eligible for care, and support them and their carers, and fund care for those people with needs who meet financial eligibility criteria • Shape the adult social care market to encourage quality, choice and sufficiency of provision • Undertake local contingency planning in case of provider failure • Ensure continuity of care where services cease • Work with NHS to promote integration including integrated commissioning and joined up services
5 Alternative options considered 5.1 Alternative options have been considered and are set out in the Confidential Annex.
6 Supporting information 6.1 To ensure the continuity of care and service delivery, and in line with the Council’s responsibilities under the Care Act, a process has been undertaken to identify a provider to delivery residential and nursing services on an interim contract.
6.2The provider was assessed on quality and value for money by Council Officers including social care, commissioning, finance and procurement.
6.3In consideration of the Procurement Act 2023, the interim contract period will ensure the quality and stability of the service is maintained whilst a review is undertaken for the long-term requirement.
6.4Please refer to the Confidential Annex.
7 Consultation and other considerations Legal Advice
7.1The comments of Procurement are noted. Please refer to the Confidential Annex. Appropriate terms and conditions for the new provider must be used.
Financial Advice
7.2The profile of block bed use at the anticipated contract rate per bed would suggest that the Council will benefit from cost avoidance over the duration of the contract. The Confidential Annex provides more detailed information in relation to Value for Money.
Other consultation responses
7.3Procurement
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report - Q1RESOLVED that Cabinet: · NOTES the performance of the council over the period from April to June 2026, highlighted in...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.