Resolved
that the report on Harlesden Town Centre Major Scheme be noted.
Highways Committee noted this item on Wednesday 27 July 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
that the report on Harlesden Town Centre Major Scheme be noted.
1.1This report informs members of the current progress on the Harlesden Town Centre “Major Scheme”.
1.2Transport for London’s (major scheme) funding regime provides an opportunity for Council’s to develop and implement schemes to improve the operation and appearance of town centres so as to support the vibrancy and vitality of those town centres.
Officers are currently working on a scheme for Harlesden Town Centre with the aim of securing up to £4 million to deliver the proposals. The aim of the scheme is support the development of an economically, socially and environmentally sustainable town centre which contributes to the wider objectives of reducing the need to travel (by motorised means) and where travel is necessary, to maximise the attractiveness of public transport by improving its reliability and speed.
1.4As a precursor to the main project funding has already been secured to implement a pedestrian accessibility scheme on Station Road linking Willesden Junction Station to the Town Centre this financial year.
1.5This report sets out the background to the scheme, the progress made to date and the programme towards completion.
Highways Committee Version 2 27 July 2011 Date 15/07/11 2.0 Recommendation
2.1That the Committee notes the contents of this report.
3.1Harlesden town centre is at the centre of its diverse community, yet like many places its’ status has been progressively reduced so that it has increasingly become a place of motor traffic domination, congestion, broken pedestrian desire lines and road danger with a poor public realm.
3.2An opportunity to address the challenges facing Harlesden exists through Transport for London’s (TfL) funding regime.
TfL’s “Major Schemes” budget (formerly the Area Based Scheme budget) affords an opportunity for Council’s to develop and implement schemes to improve the operation and appearance of Town Centres so as to support the vibrancy and vitality of those town centres.
Subject to securing the necessary investment from TfL, there is an opportunity, through re-shaping the public realm, to provide a catalyst for a major shift in the commercial ranking and quality of Harlesden town centre so as to enable it to better serve and contribute to the regeneration of the residential and industrial hinterland, and to become an attractive place that people will want to visit, linger, socialise and spend money.
3.3In relation to transport, there is an opportunity to create a town centre which contributes to the wider objectives of reducing the need to travel (by motorised means) and where travel is necessary, to maximise the attractiveness of public transport by improving its reliability and speed.
3.4There is an increasing recognition that any proposals aimed at changing the “look and feel” need to be understood and owned by the local community. In developing proposals for Harlesden, officers have developed and are working within an engagement framework that is radically different from the approach traditionally employed for transport/public realm schemes.
At the outset of the project a community engagement consultant was appointed to help form and develop capacity of the Harlesden Town Team. The Town Team comprises: local residents, businesses, Council officers, ward members and TfL representatives. The Team is led and managed by members of the local community with support officers. The Town Team concept provides a “middle ground” where the community, the Council and other stakeholders operate as equal partners moving towards a common goal.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Harlesden Town Centre Major SchemesReport | 1.6 MB | DownloadRead as text |
Follow Highways Committee at Brent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Jan 2018 | On- Street Parking Management Review - 2017/18 ProgrammeIt was RESOLVED :- ( i ) That the responses to the public consultations undertaken in the borough between 28 th Novem... | Noted | Open |
| 16 Oct 2017 | Declarations of InterestsCouncillor Tatler declared a personal interest in respect of agenda item number 7, The Mall Petition, in that she was... | Decided | Open |
| 16 Oct 2017 | Minutes of the Previous MeetingIt was RESOLVED that the minutes of the previous meeting held on 27 June 2017 be approved as an accurate record of th... | Approved | Open |
| 16 Oct 2017 | Reeves Avenue PetitionRESOLVED that: ( i ) The petition regarding the condition of the pavements and road surface of Reeves Avenue (NW9), b... | Noted | Open |
| 16 Oct 2017 | The Mall PetitionRESOLVED that: ( i ) The petition which asked the Council to put an end to the Infrastructure problem on The Mall, Ha... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.