What the committee will consider, in order, with every paper attached to its item. Willesden Green Redevelopment Project is the main business.
Decision: - that the minutes of the previous meeting held on 12 December 2011 be approved as an accurate record of the meeting. Decision page
This report summarises the procurement process undertaken by the Council to procure a developer partner to redevelop the Willesden Green Library Centre site and requests delegation to the Director of Regeneration and Major Projects in consultation with the Director of Legal & Procurement to award and enter into a Development Agreement with the preferred developer partner. It also summarises the structure of the...
Decision: (i) that the Director of Regeneration and Major Projects in consultation with Director of Legal & Procurement be authorised to award and enter into a Development Agreement with Galliford Try Plc in respect of the Willesden Green Library Centre site as shown crossed hatched black in the plan A at Appendix 1; such agreement to provide for the acquisition of the land as shown edged blue and green in the plan B at Appendix 1 and the development of a new cultural centre within the land as shown... Decision page
This report requests approval, as required by Contract Standing Order 85, to participate in collaborative procurement to set up a pan-London contract for Highway Services.
Decision: (i) that approval be given to the Council to participate in a collaborative procurement exercise known as the London Highways Alliance Collaborative which would lead to the establishment of a framework agreement by Transport for London for the supply of an extensive range of highways orientated services from 1 April 2013. (ii) that approval be given to the collaborative procurement exercise as described in paragraph 2.1 to exempt from the normal requirements of Brent’s Contract Standing Orders... Decision page
This report sets out the proposals for the future delivery of leisure services at Vale Farm Sports Centre and seeks Executive approval to carry out a shared procurement exercise with Ealing and Harrow as part of the West London Alliance. The programme seeks to get the best possible price for the service whilst maintaining quality and service standards through a collaborative procurement exercise.
Decision: (i) that approval be given for the council to participate in a collaborative procurement exercise that would lead to the establishment of a framework agreement for leisure services at Vale Farm Sports Centre. (ii) that approval be given to the collaborative procurement exercise detailed in 2.1 above to be exempted from the normal requirements of Brent’s Contract Standing Orders in accordance with Contract Standing Orders 85(c) and 84(a) on the basis that there are good financial and operational... Decision page
This report accompanies the Annual Audit Letter for 2010/11. The Letter is issued by the Audit Commission.
Decision: (i) that the contents of the Annual Audit Letter be noted; (ii) that it be noted that the Audit Committee will monitor progress against the main features highlighted and delivery of the Action Plan Decision page
This report details the revised Code of Practice in Treasury Management.
Decision: that the revised Treasury Policy Statement to Full Council for approval be recommended. Decision page
This report updates members on recent treasury activity.
Decision: that the report, which has also gone to the Audit Committee, be noted and that it be recommended to Full Council. Decision page
The Council has the discretion to award rate relief to charities or non-profit making bodies. It also has the discretion to remit an individual National Non-Domestic Rate (NNDR) liability in whole or in part on the grounds of hardship. This report includes applications received for discretionary rate relief since the Executive Committee last considered such applications in October 2011. Applications have also been...
Decision: (i) that the discretionary rate relief applications in Appendix 2 be agreed; (ii) that the granting to Meanwhile Space CIC 100% discretionary rate relief in respect of their short term occupation of units in Willesden as detailed in Appendix 3 be agreed. Decision page
This report seeks agreement to the creation of a newly named from existing Main Programme Grant and Advice Services Budgets; maintaining the overall level of funding as detailed in Section 6. As existing grant terms come to an end, the report proposes allocating the Main Programme Grant budget to grant-funded Borough Plan aligned projects, enhancing infrastructure support for the voluntary sector and some advice...
Decision: (i) that the creation of a newly named from the existing Main Programme Grant and the Advice Services budgets be agreed; (ii) that the creation of three funding streams within the Voluntary Sector Initiative Fund in the financial year 2012 – 2013 be agreed, which are as follows: a funding stream using existing Main Programme Grant Budget forprojects which run for two year and nine months aligned to Borough Plan priorities excluding crime and regeneration as set out in paragraph 4.3 of this... Decision page
This report seeks agreement to London Councils Grants Committee budget for 2012/13 and the associated reduction in the level of contribution by Brent Council to the London Borough Grants Scheme.
Decision: (i) that the recommended budget for the London Councils Grant Scheme and the contribution of £377,097 to be paid by the Council towards the London Boroughs Grants Scheme for 2012/13 be agreed. (ii) that the reallocation of the sum of £83,832, which is no longer paid towards the London Boroughs Grant Scheme, be agreed by:- (a) allocating the sum of £24,583 to cover the overspend created by the increase in the contribution sought from London Councils during 2011/2012 (as set out in paragraph 4.3... Decision page
Notice of items to be raised under this heading must be given in writing to the Democratic Services Manager or his representative before the meeting in accordance with Standing Order 64.
Item 5 is where most of this meeting's papers sit: 6 papers, about 10 MB.
This report summarises the procurement process undertaken by the Council to procure a developer partner to redevelop the Willesden Green Library Centre site and requests delegation to the Director of Regeneration and Major Projects in consultation with the Director of Legal & Procurement to award and enter into a Development Agreement with the preferred developer partner. It also summarises the structure of the...
This committee has dealt with the subject before.
Get the decision the day it is recorded, and anything that comes back to the committee on this subject.
All 23 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
The committee last met on 12 December 2011. 1 of its items lead into this meeting; 9 items are new. Point at any item to follow a thread. Procedural items are left out.
Arboricultural Services, Parking contract extension, South Kilburn Neighbourhood Trust - proposed constitutional amendments, LDF - submission of Joint West London Waste Plan and 4 more do not return this time.
See the 12 December meetingEvery Executive meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
Brent, Executive
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the Executive, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.