Declarations of personal and prejudicial interests
Members are invited to declare at this stage of the meeting, any relevant financial or other interest in the items on this agenda.
What the committee will consider, in order, with every paper attached to its item. Highways Asset Management Plan and Capital Schemes Programme 2014-16 is the main business.
Members are invited to declare at this stage of the meeting, any relevant financial or other interest in the items on this agenda.
Decision: that the minutes of the previous meeting held on 13 January 2014 be approved as an accurate record of the meeting. Decision page
A petition has been received in the following terms: “We believe that residents should be able to have the choice of what method they use for visitors’ permits and should not be forced to use the online system only.” Lead petitioner: Joel Davidson.
This report sets out the detail of the budget proposed for 2014/15 and how this has been developed as well as the medium term financial outlook. Members are principally concerned with setting the budget for 2014/15 at this stage, but to do so need to be mindful of the medium term position and of the inherent financial risks in delivering, as Brent does, a complex range of services to its 312,000 residents, spending...
Decision: These recommendations only include a provisional Council Tax level for the GLA as its final budget was not agreed when this report was dispatched. This means that the statutory calculation of the total amount of Council Tax under Section 30(2) of the Local Government Finance Act 1992 may be amended by the final Greater London Authority precept. That subject to the final confirmation of the GLA precept approval be given to the following recommendations for Full Council at its meeting on 3 March... Decision page
Appendix 1 to this report is Brent’s first Market Position Statement (MPS) for providers of Accommodation based care and support services. The purpose of developing this MPS is to signal our intention to share better, more transparent information with the market about our commissioning intentions; for the benefit of both current and potential providers of Accommodation based care and support services . The MPS is...
Decision: ( i ) that approval be given to the MPS for publication; (ii) that approval be given to the development of a Market Development Plan, which will set out how we will deliver the aspirations of the MPS. It is proposed that this will be brought to Executive for approval in June 2014. Decision page
This report sets out a summary of the phase 1 Mental Health Improvement Project and options for taking forward phase 2.
Decision: ( i ) that the results of phase 1 of the Mental Health Improvement Project be noted; (ii) that the Council continues to deliver its adult mental health social care responsibilities in partnership with Central and North-West London NHS Foundation Trust (CNWL) in 2014/15; (iii) that officers not implement the decision taken in April 2013, to progress with the procurement of mental health services by way of a competitive dialogue process; (iv) that it be noted that any proposed future procurement... Decision page
There are 3 properties within the Borough that are leased to 2 providers under 5 year lease arrangements (Appendix A sets out the detail). Two of the leases end on 22/02/16 and the other ends 03/03/2016. The leaseholders, are also the providers of the residential care service for 10 service users. In July 2013 the Corporate Assets Board agreed that all 3 leases be terminated and new leases be negotiated. This...
Decision: ( i ) that approval be given to to the pre - tender considerations and the criteria to be used to evaluate tenders in respect of tenancy management arrangements with associated leases for the 3 properties located in Beechcroft Gardens, Kinch Grove and Manor Drive as set out in paragraph 6.1 of the report; (ii) that approval be given to the invite of tenders in respect of tenancy management arrangements with associated leases and evaluate them in accordance with the approved evaluation criteria... Decision page
This report concerns the procurement of a block contract for supported accommodation for 16+ Looked After Children and Care Leavers aged 18+ for semi-independent living. This report requests approval to invite tenders in respect of a contract for Semi Independent Living as required by Contract Standing Orders 88 and 89 and requests approval to delegate authority to the Acting Director of Children and Families in...
Decision: ( i ) that tenders be invited for a contract for Semi - Independent Living on the basis of the pre - tender considerations set out in paragraph 3.9 of the report. (ii) that officers be authorised to evaluate the tenders referred to in 2.1 above on the basis of the evaluation criteria set out in paragraph 3.9 of the report. (iii) that authority to award the contract for Semi – Independent Living be delegated to the Acting Director of Children and Families in consultation with the Director of... Decision page
This report sets out recommendations for how Brent’s £3.55 million capital budget should be allocated during 2014/15 and 2015/16 through a prioritised programme of: Major and minor pavement upgrades; major road resurfacing; £preventative maintenance; and improvements to the public realm.
Decision: ( i ) that approval be give to investment of £3.55 million of Brent capital funding as summarised in Section 6.0;. (ii) that approval be give to approves the proposed highways maintenance programme for 2014-15 and the provisional programme for 2015-16 as detailed in Appendix B; (iii) that approval be give to the highways asset management strategy for Brent as described in Section 4.0 and appended as background papers to this report; (iv) that approval be give to the proposed division of... Decision page
This report presents to Members the Housing Revenue Account (HRA) forecast outturn for 2013/14 and the draft HRA budget for 2014/15 as required by the Local Government and Housing Act 1989. Members are required to consider these budget estimates and the associated options, taking account of the requirement to set an HRA budget that does not show a debit balance at year end, and in particular Members need to consider...
Decision: ( i ) that the HRA forecast outturn 2013/14 (Appendix 1 Table 1) be noted; (ii) that the savings/budget reductions for 2014/15 as set out in paragraph 3.48.3 be approved; (iii) that the HRA budget growth for 2014-15 of £3.740m as set out in paragraph 3.48.4 be approved; (iv) that approval be given to an average overall rent increase (excluding service charges) from April 2014 of £4.67 per week, which is an average overall increase of 4.39%, as set out in further detail in paragraphs 3.23 to... Decision page
This report seeks approval for the approach and criteria for meeting the temporary school place need and seeks outline approval for a programme of projects to deliver the school places required for September 2014. Approval to start the procurement of a works contractor/s in line with the requirements of the programme is also requested. This report is presented to the Executive ahead of a revised strategy for school...
Decision: ( i ) that the current and future school place demand and projected shortfall of primary school places for 2014-15, as described in paragraphs 3.1-3.25 be noted; (ii) that approval be given to the approach and criteria for the provision of temporary school places outlined in this report, as described in paragraphs 3.26-3.33; (iii) that approval be given to the potential programme of projects to provide temporary school places to meet projected demand for September 2014 including capital... Decision page
This report provides information regarding progress on the redevelopment of the Unisys and Community Leisure Centre (BPCLC) sites. It provides detail on the outcome of the public consultation undertaken at the request of the Executive to gain the public’s preference on a number of facility options for the provision of a replacement leisure centre. The report also provides an update to Members on the current position...
Decision: ( i ) that agreement be given to the vision and objectives of the new leisure centre; (ii) that approval be given to the preferred leisure centre option as (Option 3), as set out at paragraph 3.18; (iii) that it be noted that the large majority of respondents, approximately 95%, selected as their first choice one or more of the four Options that involved change at , while approximately 5% of respondents selected as their first choice the option for leaving as it is and that at the appropriate... Decision page
This report concerns the procurement of bio-fuel supplies for the Civic Centre combined cooling, heat and power (CCHP) plant and requests approval to invite tenders in respect of bio-fuel supplies as required by Contract Standing Orders 88 and 89 and approval of the selection and award criteria.
Decision: ( i ) that approval be given to the invite of tenders for 2 nd generation bio-fuel supplies (or a higher compatible category) for the Civic Centre CCHP plant on the basis of the pre-tender considerations set out in paragraph 3.8 of the report; (ii) that officers evaluate the tenders referred to in 2.1 above on the basis of the evaluation criteria set out in paragraph 3.8 of the report. Decision page
This report details the marketing exercise undertaken for 395 Chapter Road and makes recommendations to the Executive in respect of the disposal.
Decision: ( i ) that approval be given to the leasehold disposal of the Brent Housing Partnership interest at 395 Chapter Road to Iridium Assets Ltd to operate a medical practice from the property, by creating serviced clinics from the commercial premises; (ii) that if the proposed disposal to Iridium Assets Ltd does not proceed, then approval be given to a disposal to Forest & Ray Ltd for the purposes of a dental surgery; (iii) that authority be delegated to the Operational Director Property and... Decision page
Notice of items to be raised under this heading must be given in writing to the Democratic Services Manager or his representative before the meeting in accordance with Standing Order 64.
Item 10 is where most of this meeting's papers sit: 4 papers, about 7.6 MB.
This report sets out recommendations for how Brent’s £3.55 million capital budget should be allocated during 2014/15 and 2015/16 through a prioritised programme of: Major and minor pavement upgrades; major road resurfacing; £preventative maintenance; and improvements to the public realm.
This committee has dealt with the subject before.
Get the decision the day it is recorded, and anything that comes back to the committee on this subject.
All 28 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
The committee last met on 13 January 2014. 1 of its items lead into this meeting; 11 items are new. Point at any item to follow a thread. Procedural items are left out.
Determination proposal to permanently expand Princess Frederica CE Primary School by September 2014, Update on Public Health Contracts, Award of tender for Connexions Service, Tender award for Information Advice and Guidance in Children’s Centres and 6 more do not return this time.
See the 13 January meetingEvery Executive meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
Brent, Executive
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the Executive, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.