London Borough of Brent
Executive, Monday 16 January 2012 at 7.00pm

Willesden Green Redevelopment Project

Agreed Executive 6 papers

Executive agreed this item on Monday 16 January 2012. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

(i) that the Director of Regeneration and Major Projects in consultation with Director of Legal & Procurement be authorised to award and enter into a Development Agreement with Galliford Try Plc in respect of the Willesden Green Library Centre site as shown crossed hatched black in the plan A at Appendix 1; such agreement to provide for the acquisition of the land as shown edged blue and green in the plan B at Appendix 1 and the development of a new cultural centre within the land as shown edged orange in the plan B at Appendix 1; (ii) that the Director of Regeneration and Major Projects be authorised to dispose of the land at Chambers Lane Willesden Green shown crossed hatched black on Plan C at Appendix 1 to Galliford Try Plc to form part of the Willesden Green Library Centre site as shown crossed hatched black in the plan A at Appendix 1; (iii) that the Director of Regeneration and Major Projects (where the Director of Regeneration and Major Projects in conjunction with the Director of Legal and Procurement consider applicable) be authorised to take the necessary steps to override or where requisite extinguish rights and interests in the land which might otherwise act to constrain the development by:- (a) appropriating the land shown crossed hatched black in the plan A at Appendix 1 for planning purposes when it is no longer required for the purposes for which it is currently held (b) taking any other legal steps as may be necessary to achieve this objective; (iv) that authority be delegated to the Director of Regeneration and Major Projects in consultation with the Director of Finance and Corporate Services to authorise the detailed design and detailed costs for the “Council Works” as detailed in Section 5.2, 7.5 and 7.6; (v) that the proposed interim service delivery strategy as detailed in paragraphs 6.4 -6.36 below for the services currently provided at the Willesden Green Library Centre be endorsed; (vi) that the detailed Impact Needs/Requirements Assessment in Appendix 15 and the detailed Equality Strand Analysis, key issues and proposed mitigation in Annex 15.1 be noted; (vii) that the proposed consultation strategy outlined in Appendix 2 be endorsed.
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Executive

Summary

1.1This report summarises the procurement process undertaken by the Council to procure a developer partner to redevelop the Willesden Green Library Centre site and requests delegation to the Director of Regeneration and Major Projects in consultation with the Director of Legal & Procurement to award and enter into a Development Agreement with the preferred developer partner.

1.2This report summarises the structure of the development agreement to be entered into with the preferred developer partner and requests delegation to the Director of Regeneration and Major Projects in consultation with the Director of Finance and Corporate Services to approve the detailed design and detailed cost for the “Council Works”; defined as; a new cultural centre which will include a library, museum, archive and customer contact centre on a designated plot, associated public realm, community amenity spaces and designated car parking.

1.3Finally a general update and overview of the project is provided, demonstrating that all the pieces are now in place to redevelop the Willesden Green Library Centre site and deliver a new cultural centre in the south of the Borough, equivalent in quality to the new civic centre in the north, at net zero capital cost to the Council.

Recommendations

2.1That the Executive delegate authority to the Director of Regeneration & Major Projects in consultation with Director of Legal & Procurement to award and enter into a Development Agreement with Galliford Try Plc in respect of the Willesden Green Library Centre site as shown crossed hatched black in the plan A at Appendix 1; such agreement to provide for the acquisition of the

Executive Version no.2.6 th 16 January 2012 land as shown edged blue and green in the plan B at Appendix 1 and the development of a new cultural centre within the land as shown edged orange in the plan B at Appendix 1.

2.2The Executive authorise the Director of Regeneration and Major Projects to dispose of the land at Chambers Lane Willesden Green shown crossed hatched black on Plan C at Appendix 1 to Galliford Try Plc to form part of the Willesden Green Library Centre site as shown crossed hatched black in the plan A at Appendix 1.

2.3That the Executive authorise the Director of Regeneration & Major Projects (where the Director of Regeneration & Major Projects in conjunction with the Director of Legal and Procurement consider applicable ) to take the necessary steps to override or where requisite extinguish rights and interests in the land which might otherwise act to constrain the development by

(i) appropriating the land shown crossed hatched black in the plan A at Appendix 1 for planning purposes when it is no longer required for the purposes for which it is currently held (ii) taking any other legal steps as may be necessary to achieve this objective.

2.4That the Executive delegates authority to the Director of Regeneration & Major Projects in consultation with the Director of Finance and Corporate Services to authorise the detailed design and detailed costs for the “Council Works” as detailed in Section 5.2, 7.5 and 7.6.

2.5That the Executive endorses the proposed interim service delivery strategy as detailed in paragraphs 6.4 -6.36 below for the services currently provided at the Willesden Green Library Centre.

2.6That the Executive notes the detailed Impact Needs/Requirements Assessment in Appendix 15 and the detailed Equality Strand Analysis, key issues and proposed mitigation in Annex 15.1.

2.7That the Executive endorses the proposed consultation strategy outlined in Appendix 2.

Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Willesden Green Redevelopment ProjectReport 314 KB DownloadRead as text
PDF
rmp-app1planaReport 276 KB Download
PDF
rmp-app1planbReport 4.6 MB Download
PDF
rmp-app1plancReport 191 KB Download
PDF
willesden-green-appendix-2Appendix 5 MB Download
PDF
willesden-green-appendix-3Appendix 46 KB Download

At this meeting

Whole meeting

Who was there

10 of 22 attended
AJ
Councillor Ann John OBEChair, present
MB
Councillor Muhammed ButtVice-Chair, present
MA
Councillor Mary ArnoldCommittee Member, present
LB
Councillor Lincoln Beswick MBECommittee Member, present
GC
Councillor George CraneCommittee Member, present
LJ
Councillor Lesley JonesCommittee Member, present
JL
Councillor Janice LongCommittee Member, present
JM
Councillor Jim MoherCommittee Member, present
RM
Councillor Ruth MoherCommittee Member, present
JP
Councillor James PowneyCommittee Member, present
EA
Councillor Emad Al-EbadiCouncillor, in attendance
BC
Councillor Barry CheeseCouncillor, in attendance

All 22 on the meeting page

On this subject at Brent

Search all
  1. Willesden Green Redevelopment ProjectThis decision
  2. Willesden Green Health and Wellbeing Integrated HubNoted
  3. Approval to Proceed with Alternative Heat Supply for Willesden Green Library- Public Sector Decarbonisation Scheme (PSDS) Phase 4Approved
  4. 20/3149 - Willesden Green Garage, St Pauls Avenue, London, NW2 5TGRefused
  5. 20/2257 - Willesden Green Garage, St Pauls Avenue, London, NW2 5TGDecided
  6. Willesden Green Baptist Church, High Road, London, NW10 2PR (Ref.18/4746)Decided

More from Brent Executive

All decisions
MeetingDecisionOutcome
16 Jun 2014 Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ... Approved Open
16 Jun 2014 Adult Home Care Services - framework appointments(i) that approval be given to the appointment to the West London Alliance Framework to provide Home Support of those ... Approved Open
16 Jun 2014 Advocacy Services - Learning Disabilities, Safeguarding, Mental Health and Older People and Young People with Physical Disabilities( i ) t hat Voiceability Limited be awarded a contract as lead organisation for a consortium for Advocacy Services fo... Noted Open
16 Jun 2014 Safer Lorry Scheme( i ) that the principle of creating a new pan-London traffic order requiring minimum safety features for all HGVs ov... Agreed Open
16 Jun 2014 Leasing of Office Accommodation Brent Civic Centre, Engineers Way, Wembley, HA9 0FJthat a lease of up to 10 years be entered into on office accommodation in the Civic Centre in accordance with the det... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies