Parking and waiting restrictions review programme 2013-14

Approved Committee 1 paper

Highways Committee approved this item on Tuesday 12 March 2013. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

( i ) that the proposed parking and waiting restrictions review programme for 2013/14 be approved. (ii) that a 2013/14 LIP capital funding allocation of £60,000 be used to investigate and amend parking and waiting restrictions listed in the programme. (iii) that the £60,000 budget be allocated as follows; · £40,000 to investigate and implement short sections of waiting and loading restrictions (SSWR) borough wide; and · £20,000 to review parking waiting and loading restrictions in controlled parking zone areas. (iv) that delegated authority be granted to the Head of Transportation to consider objections and representations to statutory and other consultations undertaken on schemes within the works programme, to report back to the Committee if those objections are substantial, but otherwise to implement the schemes with minor modifications, if appropriate.
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Highways Committee

Summary

1.1This report informs and seeks the approval of the Committee to deliver a parking and waiting restrictions review programme during 2013/14 utilising Local Implementation Plan (LIP) funds allocated during that financial year for amendments to loading and waiting restrictions.

Recommendations

2.1That Committee approves the proposed parking and waiting restrictions review programme for 2013/14.

2.2That a 2013/14 LIP capital funding allocation of £60k is used to investigate and amend parking and waiting restrictions listed in the programme.

2.3That the £60k budget is allocated as follows; • £40k to investigate and implement short sections of waiting and loading restrictions (SSWR) borough wide; and • £20k to review parking waiting and loading restrictions in controlled parking zone areas.

2.4That the Committee delegates authority to the Head of Transportation to consider objections and representations to statutory and other consultations undertaken on schemes within the works programme, to report back to the Committee if those objections are substantial, but otherwise to implement the schemes with minor modifications, if appropriate.

Background

3.1At the Full Council meeting of 28th February 2011, a report titled “2011/12 Budget and Council Tax” was approved and a £300k revenue budget used for periodic review and amendment of the boroughs CPZ’s was reduced by £240k for 2011/12 and by a further £60k for 2012/13. In this report members agreed to reduce the revenue funding available, the effect of which would be to cease work to introduce new, and review or adjust existing CPZ schemes. Members are therefore reminded that there is currently no revenue budget available to introduce or amend controlled parking zones (CPZ).

3.2Since withdrawal of the CPZ review budget, the Council has received a number of requests for changes to existing parking zones to address disparities in operational hours. Officers were unable to action investigations into these proposals, or to action any changes to CPZ operations, in the absence of a review budget.

3.3In addition to requests to amend CPZs, the Council regularly receives requests for site-specific parking and loading restrictions to deal with a variety of parking issues on the Brent network, including: • Commuter parking near train stations; • Parking on narrow streets including grass verges; • Short term parking near schools; • Short term parking for customers outside shops; • Short term loading provision outside shops; • Short and long term parking in industrial areas; and • Hazardous parking near junctions and on bends.

4.0Proposed Review Programme

4.1In a report to Highways Committee on 7th February 2013 “2013/14 Capital Programme – Local Implementation Plan: TfL Allocation”, members noted that the Council has secured an infrastructure improvement fund of £60k for “site specific waiting and loading restriction reviews”. This fund is for the purpose of investigating the need for, and delivering where appropriate, new or existing waiting and loading restrictions where problems have been identified. This funding is within the scope of the LIP allocation

4.2Use of this element of LIP funding is ring-fenced for waiting and loading restriction reviews and will be used to introduce short sections of waiting and loading restrictions where there are notable hazards, congestion, obstructions or inconvenience to road users resulting from on-street parking or loading. Although ring-fenced for parking and loading reviews, use of this fund is discretionary at a local level and it is proposed to allocate a proportion of the fund for the specific purpose of investigating and reviewing potential changes to CPZ controls through a priority assessment process described in Section 4.4 below.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Parking and waiting restrictions review programme 2013-14Report 235 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 6 attended
PC
Paul ChandlerCouncil Staff, present
JM
Councillor Jim MoherChair, present
JP
Councillor James PowneyVice-Chair, present
LB
Councillor Lincoln Beswick MBECommittee Member, present
LJ
Councillor Lesley JonesCommittee Member, present
JL
Councillor Janice LongCommittee Member, present

More from Brent Highways Committee

All decisions
MeetingDecisionOutcome
24 Jan 2018 On- Street Parking Management Review - 2017/18 ProgrammeIt was RESOLVED :- ( i ) That the responses to the public consultations undertaken in the borough between 28 th Novem... Noted Open
16 Oct 2017 Declarations of InterestsCouncillor Tatler declared a personal interest in respect of agenda item number 7, The Mall Petition, in that she was... Decided Open
16 Oct 2017 Minutes of the Previous MeetingIt was RESOLVED that the minutes of the previous meeting held on 27 June 2017 be approved as an accurate record of th... Approved Open
16 Oct 2017 Reeves Avenue PetitionRESOLVED that: ( i ) The petition regarding the condition of the pavements and road surface of Reeves Avenue (NW9), b... Noted Open
16 Oct 2017 The Mall PetitionRESOLVED that: ( i ) The petition which asked the Council to put an end to the Infrastructure problem on The Mall, Ha... Noted Open