Highways Committee, Tuesday 12 March 2013 at 7.00pm

Transportation capital schemes programme 20013/14

Approved Committee 2 papers

Highways Committee approved this item on Tuesday 12 March 2013. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

that the decision by the Executive to approve the Brent funded highways capital programme for 2013/14 of £3.5 million as set out in appendices to the report from the Head of Transportation be noted.
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Highways Committee

Summary

1.1This report is for information only. It advises members of the Highway Committee of the decision of the Executive Committee on 11th February to approve the 2013-14 Capital schemes programme.

1.2The report to the Executive asked members to approve £3.5 million of Brent capital to maintain and improve the highway network, subject to the approval of the Budget and Council Tax report on 11 February 2013 and full Council approval on 25 February 2013.

1.3The Executive report sets out how Brent’s £3.5 million capital budget should be allocated through a prioritised programme of:

• Major and minor pavement upgrades; • Road resurfacing; and • Improvements to the public realm.

1.4In 2013-14 over £10.2 million of capital funding will be spent improving Brent’s roads, footways and transport infrastructure. This is a 36% increase and will be funded by Brent Council, Transport for London (TfL) and Section 106 funds from developers.

1.5Of the total £10.2 million investment, £5.1 million has been allocated to Brent by TfL to support Brent’s Local Implementation Plan (LIP) with a further £724,000 for Principal (A) roads. Details of the Principal (A) road programme are provided in this report.

1.6The report to the Highways Committee on 7th February 2013 titled; Capital Programme, Local Implementation Plan – TfL Allocation detailed this £5.871

Highways Committee Version 1.0 12 March 2013 9 February 2013 million programme and instructed the Head of Transportation to implement these schemes and initiatives using the allocated budget and resources..

1.7The Highways Committee on 7th February also authorised the Head of Transportation to undertake any necessary non-statutory and statutory consultation, to consider any objections or representations and to implement the necessary Traffic Management Orders if there are no objections or representations, or if the Head Transportation considers the objections or representations are groundless or insignificant and otherwise to refer objections or representations to the Committee for further consideration

Recommendations

2.1That the Highways Committee note that the Executive have approved the Brent funded highways capital programme for 2013/14 of £3.5 million as listed in Appendices 2 to 4 and summarised as follows:

Amount % of Brent (£ 000’s) capital Budget Footways Major footway improvements (long sections) 44% 1,525 Footway improvements (short sections) 4% 150 Public realm improvements 3% 125 Sub-total 51% 1,800 Carriageways Resurfacing of unclassified roads 38% 1,300 Resurfacing of B & C Class roads 4% 150 Resurfacing of short sections 4% 150 Sub-total 46% 1,600 Contingencies for TfL schemes 3% 100 Total 100% 3,500

3.0DETAIL

3.1Highway Improvements in 2012-13

3.1.1 Our focus is to improve and maintain the roads, footways and transportation network to enhance the environment and improve the safety of Brent residents, and those passing through the Borough.

3.1.2 By 31 March 2013, roughly £7.5 Million (funded by Brent, TfL and S106) will have been spent on improving Brent’s transport infrastructure, including 7 miles of road resurfacing, 4 miles of footway resurfacing and associated improvements, and over 20 major improvement schemes will have been be delivered.

3.1.3 Appendix 1 lists major footway upgrades and road resurfacing works carried out in the borough during 2012/13.

3.2Improving the condition of Brent’s roads in 2013-14 Highways Committee Version 1.0 12 March 2013 9 February 2013 3.2.1 Brent’s roads are one of its most important physical assets. The table below sets out their condition by indicating the percentage of each length of road type where maintenance should be considered.

% of roads where maintenance should be considered Year A class roads B and C class roads Unclassified roads 2008/2009 8% 9% 23% 2009/2010 11% 9% 23% 2010/2011 9% 7% 27% 2011/2012 9% 6% 26%

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Transportation capital schemes programme 20013/14Report 177 KB DownloadRead as text
PDF
capital-schemes-app5Report 851 KB Download

At this meeting

Whole meeting

Who was there

6 of 6 attended
PC
Paul ChandlerCouncil Staff, present
JM
Councillor Jim MoherChair, present
JP
Councillor James PowneyVice-Chair, present
LB
Councillor Lincoln Beswick MBECommittee Member, present
LJ
Councillor Lesley JonesCommittee Member, present
JL
Councillor Janice LongCommittee Member, present

On this subject at Brent

Search all
  1. Transportation capital schemes programme 20013/14This decision
  2. Transportation Local Implementation Plan - Transport for London Capital Allocation 2010-2011Noted

More from Brent Highways Committee

All decisions
MeetingDecisionOutcome
24 Jan 2018 On- Street Parking Management Review - 2017/18 ProgrammeIt was RESOLVED :- ( i ) That the responses to the public consultations undertaken in the borough between 28 th Novem... Noted Open
16 Oct 2017 Declarations of InterestsCouncillor Tatler declared a personal interest in respect of agenda item number 7, The Mall Petition, in that she was... Decided Open
16 Oct 2017 Minutes of the Previous MeetingIt was RESOLVED that the minutes of the previous meeting held on 27 June 2017 be approved as an accurate record of th... Approved Open
16 Oct 2017 Reeves Avenue PetitionRESOLVED that: ( i ) The petition regarding the condition of the pavements and road surface of Reeves Avenue (NW9), b... Noted Open
16 Oct 2017 The Mall PetitionRESOLVED that: ( i ) The petition which asked the Council to put an end to the Infrastructure problem on The Mall, Ha... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies