(i) that the draft highways asset management strategy for Brent as described in section 5.0 of the report and appended as background papers to this report be recommended to the Executive for approval; (ii) that the proposed prioritisation process and criteria for programme development described in section 5.14 of the report be recommended to the Executive for approval; and (iii) that the proposed 2014-16 highways capital programme, as detailed in Appendix B and summarised in the table in section 2.4 of the report which will be reported to the Executive for approval on 17 February 2014, be recommended to the Executive for approval.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1This report describes highway maintenance works carried out during 2013/14 and presents a proposal to adopt a new systematic long term approach to maintaining the borough’s highways through Highway Asset Management Planning (HAMP).
1.2It is proposed to get best value from the total spend on highways assets throughout their life by beginning to deliver a programme of preventative maintenance schemes, instead of only treating roads and pavements in the worst condition first.
1.3The HAMP approach will deliver better value for money through adoption of a sensible and forward thinking maintenance plan. Our customers will see more miles of road maintained each year and have greater visibility as to the relative status of their roads in the maintenance programme. We will deliver more on the ground and help to meet many of our corporate and strategic transport objectives by doing so.
1.4During 2014/15 it is proposed to allocate £3.55 million of Brent capital to maintain the highway network, subject to approval of the Executive and the Budget and Council Tax report on 17th February 2013 and; full Council approval on 3rd March 2013.
1.5Assuming that this level of highway maintenance investment is approved, during 2014/15 the application of HAMP principles will increase the length of Brent’s roads to be resurfaced by over 2 miles, from 8.65 miles during 2013/14 to 11.1 miles in 2014/15.
Recommendations
2.1That the Highways Committee notes the draft highways asset management strategy for Brent as described in Section 5.0 and appended as background papers to this report. Executive Version 3 20th January 14 2.3 That the Highways Committee notes the proposed prioritisation process and criteria for programme development described in Section 5.14
2.4That the Committee notes the proposed 2014-16 highways capital programme, which will be reported to the Executive for approval on 17th February 2014, as detailed in Appendix B and summarised in the table below;
% of Brent capital Budget Percentage Allocation of Highways Capital 2014/15 to Maintenance Budget Value 2013/14 2016/17 (£m) (provisional) Footways Major footway improvements 44% 44.08% 1,565 Other footway improvements 4% 4.23% 150 Public realm improvements 3% 3.52% 125 Sub-total 51% 51.83% 1,840 Carriageways Major resurfacing unclassified roads 38% 27.89% 990 Preventative maintenance works 0 11.83% 420 Major resurfacing of B & C Class roads 4% 4.23% 150 Major resurfacing of short sections 4% 4.23% 150 Sub-total 46% 48.17% 1,710 Contingencies for TfL schemes 3% 0 0 Total 100% 100% 3,550
Background
3.1Brent’s annual transportation investment programme consists of; Brent capital funding, which is used to fund the roads maintenance programme for local roads; capital funding provided by Transport for London, which is used to deliver principal (strategic) road maintenance and; a programme of highway improvement schemes and sustainable transport projects delivered through the LIP (TFL funded Local Implementation Plan programme).
3.2During 2013/14 the Executive approved £3.5 million of Brent capital funding to maintain and improve the local highway network.
3.3Members will recall that Brent entered into a new 8 year contract on 1st April 2013 to provide a range of highway services, including planned and reactive maintenance works. Our new provider was procured through the London Highways Alliance Contract (LoHAC).
3.4As a direct result of the competitive LoHAC rates that we now enjoy, and through close partnership working with our new provider, we have this year delivered our entire carriageway resurfacing scheme programme plus our entire 2013/14 reserve scheme programme. This has meant that we have resurfaced over 1.5 more miles of Borough roads than was envisaged at the beginning of the year.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingIt was RESOLVED that the minutes of the previous meeting held on 27 June 2017 be approved as an accurate record of th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.