( i ) that approval be given to the investment of £3.55m of Brent capital funding as summarised in Section 6.0 of the report from the Strategic Director of Environment and Neighbourhoods, subject to approval of the Budget and Council Tax report in February 2015 and full council approval of that report in March 2015; (ii) that approval be given the proposed highways maintenance programme for 2015-16 and the provisional programme for 2016-17 as detailed in Appendix B to the report from the Strategic Director of Environment and Neighbourhoods.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1In 2014-15 approximately £5.346m will be spent improving the condition of Brent’s highways, including resurfacing of 12.8 miles of road and 3.9 miles of footway. This investment includes £3.55m of Brent capital, £1.497k of TfL capital funding for principal (A road) maintenance and £299k allocated by the Department for Transport as a result of the Council’s bid to the Pothole Fund
1.2During 2015/16 it is proposed to allocate £3.55m of Brent capital to maintain the highway network, subject to approval of the Cabinet and the Budget and Council Tax report in February 2015 and; full Council approval in March 2015.
1.3In addition to £3.55 million of Brent capital, Tfl have on 12th December 2014 confirmed funding of £1.079m of Principal Road (A-road) improvements. This is a decrease against the final 2014/15 Principal road programme value when the total value of the programme (including in-year increases totalling £646 k) was £1,497 m
1.4This report sets out recommendations for how Brent’s £3.55m capital budget should be allocated during 2015/16 and 2016/17 through a prioritised programme of: • Major and minor pavement upgrades; • Major Road resurfacing; • Preventative maintenance; • Improvements to the public realm , and • Renewal of Road Markings
1.5This programme will be delivered using Brent’s Highway Asset Management Planning (HAMP) approach, which provides a systematic long term methodology for maintaining the borough’s highways. The HAMP approach, which was started in 2014/15, will deliver better value for money through adoption of a sensible and forward thinking maintenance plan. Our customers see more miles of road maintained each year and have greater visibility as to the relative status of their Version no.8 Cabinet: 16 March 2015 Date 18 February 2015 roads. We are delivering more on the ground and help to meet many of our corporate and strategic transport objectives by doing so.
Recommendations
2.1That the Cabinet approves investment of £3.55m of Brent capital funding as summarised in Section 6.0, subject to approval of the Budget and Council Tax report in February 2015 and full council approval of that report in March 2015
2.2That the Cabinet approves the proposed highways maintenance programme for 2015-16 and the provisional programme for 2016-17 as detailed in Appendix B.
3.0HIGHWAYS INVESTMENT DURING 2014/15
3.1Brent’s annual transportation investment programme consists of; Brent capital funding, which is used to fund the roads maintenance programme for local roads; capital funding provided by Transport for London, which is used to deliver principal (strategic) road maintenance and; a programme of highway improvement schemes and sustainable transport projects delivered through the LIP (TFL funded Local Implementation Plan programme).
3.2By 31 March 2015, approximately £5,346m will have been spent on maintaining Brent’s highway infrastructure funded through £3.55m of Brent capital , £1.497million of principal road maintenance investment and a £299k DfT Grant. Appendix A provides details of the works delivered, which will result in: • 12.8 miles of roads being resurfaced; and • 4.28 miles of footways being resurfaced and improved.
3.3Members will recall that Brent entered into a new 8 year contract on 1st April 2013 to provide a range of highway services, including planned and reactive maintenance works. Our new provider was procured through the London Highways Alliance Contract (LoHAC).
3.4Through the 2014/15 LIP programme and combined with Section 106 developer contributions, an additional £6.029m is being invested in improving Brent’s roads, footways and transport infrastructure. This includes: • £4.857m of Local Implementation Plan LIP funding; and • £1.172m S106 developer contributions.
An additional £0.299m was also allocated by the Department for Transport (DfT) under the Pothole Fund.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.