( i ) that agreement be given to the vision and objectives of the new leisure centre; (ii) that approval be given to the preferred leisure centre option as (Option 3), as set out at paragraph 3.18; (iii) that it be noted that the large majority of respondents, approximately 95%, selected as their first choice one or more of the four Options that involved change at , while approximately 5% of respondents selected as their first choice the option for leaving as it is and that at the appropriate time GMH will lead on further planning related public consultation; (iv) that the proposed appointment of project consultants be noted; (v) that the land value and CIL receipt risks and the implications on the affordability of the different leisure centre facility options be noted. Should the sale of land not elicit the necessary capital receipt and advanced CIL, officers will return to Members to agree an alternate way forward. (vi) that it be noted that a further report will be submitted to the Executive prior to the tender for a Design and Build Contractor.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
2.1Agree the vision and objectives of the new leisure centre
Meeting Executive Version no.5 Date 17/02/14 Date 27/01/14 2.2 Approve the preferred leisure centre option as (Option 3), as set out at paragraph 3.18 below.
2.3Note the large majority of respondents, approximately 95%, selected as their first choice one or more of the four Options that involved change at Bridge Park, while approximately 5% of respondents selected as their first choice the option for leaving Bridge Park as it is and that at the appropriate time GMH will lead on further planning related public consultation.
2.4Note the proposed appointment of project consultants.
2.5Note the land value and CIL receipt risks and the implications on the affordability of the different leisure centre facility options. Should the sale of land not elicit the necessary capital receipt and advanced CIL, officers will return to Members to agree an alternate way forward.
2.7Note that a further report will be submitted to the Executive prior to the tender for a Design and Build Contractor.
3.0Detail
3.1Bridge Park Community Leisure Centre (BPCLC) is a former bus depot that was converted into a Leisure Centre in the 1980’s using GLA funding. It has been managed by the Council for at least the last 12 years and offers business units, dryside sports, function hall, conferencing and meeting rooms. The Bridge Park site had a covenant on it that sports and community uses should be protected and around half of any value of any development would have to be paid to the LB Bromley (as successor body to the GLC). However officers have successfully removed this covenant.
Current usage at BPCLC 3.2 The number of visits to BPCLC has varied over the last three years, often influenced significantly by the closure and opening of other gyms in the near vicinity. The table below shows the number of visits to BPCLC over the last three years to the sports facilities and to the meeting / function rooms.
Year Sports Visits Meeting / Total visits (inc health suite) function visits 2012/13 79,188 52,521 131,709 2011/12 80,969 55,951 136,920 2010/11 76,794 48,416 125,210 *Source: Brent Sports and Parks
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.