CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Brent
Cabinet, Monday 13 September 2021 at 10.00am

Highways Capital Scheme Programme 2021-22

Noted Executive 4 papers

Cabinet noted this item on Monday 13 September 2021. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

Cabinet NOTED the comments made by a member of the public, Frank Treviss , who had requested to speak on the item. In addressing Cabinet, [name removed] advised that he was speaking in support of a petition previously submitted seeking an upgrade of the pavements in Logan Road. Highlighting what he felt was the dangerous condition of the pavements, in terms of trip and fall hazards for local residents, members were also advised of the lack of any previous upgrade works and importance of the footway as a well-used route to the local school. He also reminded members that the road provided the main pedestrian and vehicle access to a bowling and social club, which was well used by a range of community organisations. He was therefore keen to ensure consideration was given to what he felt was the necessary footway repairs and upgrade required as part of the Council’s ongoing major road and footway resurfacing programme. In responding to the speech, Councillor Krupa Sheth (as Lead Member for Environment), began by thanking [name removed] for his presentation and recognising the impact that the quality of footways had on the local environment for residents. Whilst highlighting the improvement in the overall conditions of footways across the borough as a result of the £20m Highway and Footway Improvement programme over the last two years, she pointed out that this had still left a third of the borough’s footways in need of significant maintenance. Whilst the footways in Logan Road had been surveyed (with 49% by length found to be in poor structural condition) this had unfortunately still not represented a high enough priority within the criteria to be considered for inclusion as part of the 2021/22 programme. Members noted that the footways included for investment as part of the recommended programme had all been assessed with a minimum of 70% in poor condition. [name removed] was reassured, however, that Logan Road’s future inclusion would continue be reviewed on a regular basis, with the next survey due later in 2021 and local; residents encouraged to report any immediate safety concerns of defects. In the meantime it was also reported that the Lead Member for Environment and Strategic Director Regeneration and Environment had agreed to visit Logan Road in order to further examine the pavements and explore options for future improvement works. Having noted the response provided, Councillor M Butt (Leader of the Council) ended by welcoming the contribution made at the meeting and reaffirming the Council’s commitment to improving the condition of Brent’s roads and footways within the financial constraints identified, recognising their importance to local communities. Having noted the comments provided, Cabinet
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1.1To approve the Highways Maintenance Scheme Programme for 2021-22.

Recommendations

2.1That Cabinet approves the proposed Highways Maintenance Scheme Programme 2021- 22 as detailed in Appendix B. 2.2 That the Cabinet notes the receipt of a petition on 9th August 2020 for Logan Road with 52 signatures asking for the renovation and upgrading of the pavements in that road , and comments made in response to the petition ( Section 3.4.2 d) - g))

3.0Detail

Summary

3.1.1 In 2020/21, £3.5m of Brent Capital and £0.239m of TfL funding was spent improving the condition of Brent’s roads and highway structures, including resurfacing of around 6.8 miles of road. This equates to about 2 % of the road network (see Appendix A for details).

3.1.2 In addition, up to the end of 2020/21, £15.4m of Brent Capital had been spent improving the condition of Brent’s footways as part of the £20m footway improvement programme. The programme continues at time of writing (August 2021) but will finish later this year, apart from the Kilburn High Road Project for which £1m of the £20m has been set aside. It is estimated that once complete, around 45 miles of footway will have been resurfaced, which equates to about 8.5% of the footway network. (see Appendix A for details).

3.1.3 As the footways were the subject of their own £20m major investment programme, in 2019/20 and 2020/21 the whole of the £3.5m Brent highways capital was allocated to maintain carriageways and highway structures. As the £20m footway improvement programme draws to a close, the £3.5m annual figure of Brent Capital for 2021/22 reverts to being used for the maintenance of footways as well as carriageways and highway structures.

3.1.4 In previous years, in addition to £3.5m of Brent capital, TfL would add funding for Principal Road (A-road) improvements. However, in November 2017 TfL published details of their new five-year Business Plan and between 2018/19 and 2019/20 investment in proactive planned renewals on both the Borough Principal Road Network (BPRN) and TfL Road Network (TLRN) was “paused”, with only very limited funding available across London; Brent received no funding in 2018/19 and 2019/20. In 2020/21, Brent received £239,000 of TfL funding to resurface Willesden Lane (Sidmouth Road to Coverdale Road)

3.1.5 For 2021/22, there are two possible London-wide PRN funding scenario, a £15m and a £30m allocation, which has yet to be decided upon by TfL. Brent have submitted a bid to TfL for Principal Road (A-road) improvements consisting of five schemes totalling £1.371m corresponding to the £30m funding scenario; a £15m settlement would reduce the Brent allocation commensurately .

3.1.6 This report sets out recommendations for how Brent’s base £3.5m capital budget should be allocated during 2021/22 through prioritised programmes of:

 Major road and footway resurfacing;  Preventative maintenance for roads and footways, including Injection patching  Improvements to Highway Structures  Improvements to the public realm, and  Renewal of Road Markings

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
7a. Appendix A: Highways Maintenance Programme Completed in 2020-21Appendix 377 KB Download
PDF
7b. Appendix B: Major Footway Reconstruction 2021-22Appendix 245 KB Download
PDF
7c. Appendix C: Ward AbbreviationsAppendix 26 KB Download
PDF
Highways Capital Scheme Programme 2021-22Report 857 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 18 attended
MB
Councillor Muhammed Butt Leader of the CouncilChair, present
MM
Councillor Margaret McLennan Deputy LeaderVice-Chair, present
HF
Councillor Harbi Farah Lead Member for Adult Social CareCommittee Member, present
PK
Councillor Promise Knight Lead Member for Community Safety and EngagementCommittee Member, present
NN
Councillor Neil Nerva Lead Member for Public Health, Culture and LeisureCommittee Member, present
MP
Councillor Mili Patel Lead Member for Children's Safeguarding, Early Help and Social CareCommittee Member, present
KS
Councillor Krupa Sheth Lead Member for EnvironmentCommittee Member, present
TS
Councillor Thomas Stephens Lead Member for Schools, Employment and SkillsCommittee Member, present
ES
Councillor Eleanor Southwood Lead Member for Housing and Welfare ReformCommittee Member, present
ST
Councillor Shama Tatler Lead Member for Regeneration, Property and PlanningCommittee Member, present
A
AdministratorOfficer, expected
CD
Carolyn DownsOfficer, expected

All 18 on the meeting page

On this subject at Brent

Search all
  1. Highways Capital Scheme Programme 2021-22This decision
  2. Highways Capital Maintenance Programme 2023-24Decided
  3. Highways Capital Maintenance Programme 2022-23Approved
  4. Highways Capital Scheme Programme 2019-20Approved
  5. Highways Capital Scheme Programme 2018-19Decided
  6. Highways Capital Scheme Programme 2017-18Noted

More from Brent Cabinet

All decisions
MeetingDecisionOutcome
9 Nov 2026 Apologies for AbsenceApologies for absence were received from Thomas Cattermole (Corporate Director Resident & Housing Services) with Spen... Decided Open
9 Nov 2026 Declarations of InterestCouncillor Grahl declared a personal interest in relation to Agenda Item 10 (Rent Setting Policy Statement) and Agend... Decided Open
9 Nov 2026 Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec... Approved Open
9 Nov 2026 Matters Arising (if any)None identified. Decided Open
9 Nov 2026 Petitions (if any)There were no petitions presented at the meeting. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies