Highways Capital Scheme Programme 2019-20

Approved Executive 4 papers

Cabinet approved this item on Monday 15 April 2019. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

i. Cabinet approved the proposed highways maintenance programme for 2019/20 as detailed in Appendix B. ii. Cabinet noted a variation to the current policy for the specification of footway materials for short sections work. iii. Cabinet gave approval for Officers to invite tenders for a framework contract primarily to provide for the £20m investment in footways, over the three years (2019/20, 2020/21 and 2021/22). iv. Cabinet delegated authority to the Strategic Director for Regeneration and Environment in consultation with the Lead Member for Regeneration & Environment to agree relevant pre-tender considerations for the procurement of a suitable contractor(s) and thereafter evaluate tenders on the basis of such pre-tender considerations. v. Cabinet delegated authority to the Strategic Director for Regeneration & Environment, in consultation with the Lead Member for Regeneration & Environment to select contractor(s) and enter into agreement(s) with the contractor(s). i. Cabinet approved the proposed highways maintenance programme for 2019/20 as detailed in Appendix B. ii. Cabinet noted a variation to the current policy for the specification of footway materials for short sections work. iii. Cabinet gave approval for Officers to invite tenders for a framework contract primarily to provide for the £20m investment in footways, over the three years (2019/20, 2020/21 and 2021/22). iv. Cabinet delegated authority to the Strategic Director for Regeneration and Environment in consultation with the Lead Member for Regeneration & Environment to agree relevant pre-tender considerations for the procurement of a suitable contractor(s) and thereafter evaluate tenders on the basis of such pre-tender considerations. v. Cabinet delegated authority to the Strategic Director for Regeneration & Environment, in consultation with the Lead Member for Regeneration & Environment to select contractor(s) and enter into agreement(s) with the contractor(s).
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1.1To approve the Highways Capital Scheme Programme 2019-20. This report also requests approval to invite tenders in respect of a contract/framework for footway maintenance as required by Contract Standing Orders 88 and 89. 2.0 Recommendations

2.1That Cabinet approves the proposed highways maintenance programme for 2019/20 as detailed in Appendix B.

2.2That Cabinet notes a variation to the current policy for the specification of footway materials for short sections work.

2.3That Cabinet gives approval for Officers to invite tenders for a framework / contract primarily to provide for the £20m investment in footways, over the three years (2019/20, 2020/21 and 2021/22).

2.4That Cabinet delegate to the Strategic Director for Regeneration and Environment in consultation with the Lead Member for Regeneration & Environment authority to agree relevant pre-tender considerations for the procurement of a suitable contractor(s) and thereafter evaluate tenders on the basis of such pre-tender considerations.

2.5That Cabinet delegate to the Strategic Director for Regeneration & Environment, in consultation with the Lead Member for Regeneration & Environment authority to select contractor(s) and enter into agreement(s) with the contractor(s).

3.0Detail

Summary

3.1.1 In 2018/19 approximately £4.161m has been spent improving the condition of Brent’s highways, including resurfacing of around 4.2 miles of road and reconstructing about 3.9 miles of pavement. This equates to about 1.3 % of the road network and 0.7% of the pavements.

3.1.2 The £4.161m was made up of £3.5m Brent Capital and a £0.661m DfT grant. In October 2018, the Chancellor announced £420 million for local highways maintenance with priority given to addressing potholes. This additional resource was allocated using the highways maintenance funding formula and £0.661m was Brent’s Allocation.

3.1.3 Condition surveys of the borough’s highways indicate that there is still an imbalance between the roads and the pavements, with the pavements being in a worse condition. Accordingly the Council is minded to implement a major investment in the boroughs footways over the following three years (2019/20, 2020/21 and 2021/22) to improve the condition. Allowing for arrangements to be put in place for the delivery of the programme, it is estimated that Officers will be able to deliver £2m of this by the end of 2019/20 with the balance being delivered in 2020/21 and 2021/22.

3.1.4 Asphalt is the default material for footways. However, like for like replacement is still used for short sections of footway renewal to marry the relatively small areas in with the surrounding materials. This approach will be reviewed as it has been acknowledged that some small locations can be renewed with asphalt without being in conflict with the surrounding environment. The appropriate material for short sections will be determined by the Head of Highways & Infrastructure and considered on a scheme by scheme basis.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
10a. Appendix A: Highways Infrastructure WorksAppendix 70 KB Download
PDF
10b. Appendix B: Proposed Highways Maintenance ProgrammeAppendix 91 KB Download
PDF
10c. Appendix C: Ward AbbreviationsAppendix 32 KB Download
PDF
Highways Capital Scheme Programme 2019-20Report 208 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 15 attended
MB
Councillor Muhammed Butt Leader of the CouncilChair, present
MM
Councillor Margaret McLennan Deputy LeaderVice-Chair, present
AA
Councillor Amer Agha MB BS, MSc, PHCM Lead Member for Schools, Employment and SkillsCommittee Member, present
HF
Councillor Harbi Farah Lead Member for Adult Social CareCommittee Member, present
KH
Councillor Krupesh Hirani Lead Member for Public Health, Culture and LeisureCommittee Member, present
TM
Councillor Tom Miller Lead Member for Community SafetyCommittee Member, present
MP
Councillor Mili Patel Lead Member for Children's Safeguarding, Early Help and Social CareCommittee Member, present
KS
Councillor Krupa Sheth Lead Member for EnvironmentCommittee Member, present
ES
Councillor Eleanor Southwood Lead Member for Housing and Welfare ReformCommittee Member, present
ST
Councillor Shama Tatler Lead Member for Regeneration, Highways and PlanningCommittee Member, present
AA
Councillor Abdirazak AbdiCommittee Member, in attendance
BC
Councillor Bhagwanji ChohanCommittee Member, in attendance

All 15 on the meeting page

On this subject at Brent

Search all
  1. Highways Capital Scheme Programme 2019-20This decision
  2. Highways Capital Maintenance Programme 2023-24Decided
  3. Highways Capital Maintenance Programme 2022-23Approved
  4. Highways Capital Scheme Programme 2021-22Noted
  5. Highways Capital Scheme Programme 2018-19Decided
  6. Highways Capital Scheme Programme 2017-18Noted

More from Brent Cabinet

All decisions
MeetingDecisionOutcome
9 Nov 2026 Apologies for AbsenceApologies for absence were received from Thomas Cattermole (Corporate Director Resident & Housing Services) with Spen... Decided Open
9 Nov 2026 Declarations of InterestCouncillor Grahl declared a personal interest in relation to Agenda Item 10 (Rent Setting Policy Statement) and Agend... Decided Open
9 Nov 2026 Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec... Approved Open
9 Nov 2026 Matters Arising (if any)None identified. Decided Open
9 Nov 2026 Petitions (if any)There were no petitions presented at the meeting. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies