Resolved
that an extension of the contract for hosting and support for the Oracle eBusiness Suite ( oneOracle ) to Cap Gemini for 2 years from August 2016 be approved.
Cabinet approved this item on Wednesday 20 January 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
that an extension of the contract for hosting and support for the Oracle eBusiness Suite ( oneOracle ) to Cap Gemini for 2 years from August 2016 be approved.
1.1This report seeks authority to extend the contract for hosting and support for the Oracle eBusiness Suite (oneOracle).
2.1That Cabinet approves awarding an extension of the contract for hosting and support for the Oracle eBusiness Suite (oneOracle) to Cap Gemini for 2 years from August 2016.
3.0Detail
3.1During 2012, the boroughs of Brent, Croydon, Barking and Dagenham, Havering, Lambeth and Lewisham procured jointly a solution to provide an ERP solution based on Oracle technology.
3.2This solution was made up of three elements; the software itself, the external hosting and on-going support for the solution and the implementation of the solution. These contracts were provided by Oracle in the first case and Capgemini in the latter cases. The elements with Capgemini were procured as framework agreements, with call off contracts taken by each of the boroughs.
3.3The external hosting and support call-off contracts are due to expire in July 2016 and replacement is required to enable the on-going provision of the solution.
3.4Officers have considered the options going forward, these being
© London Borough of Brent Page 1 Host the system in-house; Go to market to procure a new supplier for hosting and support; and Extend the current contract with Capgemini.
3.5The option to host the system in-house was considered, to either host for just Brent and Lewisham as part of the new ICT Shared Service being established, or on behalf of the group as a whole. This option has the potential to achieve substantial savings. However it was considered that with the work currently taking place to establish the shared service there would be no capacity to undertake a project of this scale on time for the end of the current contract.
3.6There is substantial technical risk in transferring technical platforms of the complexity of this system with a resultant loss of performance of the solution and the councils’ ability to conduct business. Furthermore, there is a substantial cost in the implementation of a system with a new provider and the transfer of existing configurations and data from the current provider. It is likely that in the future the Council will seek to host the solution itself, but the best way to achieve these long-term savings will be once the shared service is fully established.
3.7The Joint Management Board established by the boroughs to manage the solution taking into account the above risks commissioned a soft market test exercise. Following negotiations with Capgemini for the cost of the contract extension performed a value for money test on their proposals to:
Assess the market rates of the service where appropriate; Assess the costs of provision to the provider and allow for reasonable profit margin; and Assess whether the proposed service levels would give rise to a practical level of performance.
3.8The assessment concluded that going to market had the potential to achieve some reductions in cost. However the saving potential was not significant enough to justify the level of risk involved in transferring the service. This is a feature of IT contracts of this nature. The costs of changing from an established provider are relatively high, which in the worst cases can lead to inaction and acceptance of the status quo. This is not the case here. The council has a clear plan to establish itself as a market leader in local government IT services, and is only concerned now with when to take over the hosting services. For the reasons set out above, transferring in 2018 makes much more sense strategically.
3.9This does not mean that the immediate opportunity to deliver savings has not been taken: quite the reverse. The strength of the Oracle Partnership has generated significant opportunities of leverage at some savings despite rising costs in the industry.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Extension of Contract for Hosting and Support for Oracle eBusiness Suite (oneOracle)Report | 89 KB | DownloadRead as text |
Follow Cabinet at Brent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2026 | Apologies for AbsenceApologies for absence were received from Thomas Cattermole (Corporate Director Resident & Housing Services) with Spen... | Decided | Open |
| 9 Nov 2026 | Declarations of InterestCouncillor Grahl declared a personal interest in relation to Agenda Item 10 (Rent Setting Policy Statement) and Agend... | Decided | Open |
| 9 Nov 2026 | Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec... | Approved | Open |
| 9 Nov 2026 | Matters Arising (if any)None identified. | Decided | Open |
| 9 Nov 2026 | Petitions (if any)There were no petitions presented at the meeting. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.