Resolved
Granted planning permission as recommended and an informative
Planning Committee decided this item on Wednesday 9 March 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
Granted planning permission as recommended and an informative
Case Ref: 15/5240 Page 1 of 2 Supplementary Information 9 March, 2016
Agenda Item 11 Supplementary Information Planning Committee on 9 March, 2016 Case No. 15/5240 __________________________________________________ Location Uxendon Manor Primary School, Vista Way, Harrow, HA3 0UX Description Expansion of current 2FE to 4FE primary school with associated landscape works and including:
1. Demolition of two classroom blocks, sports hall, toilet wing and staff room. 2. Construction of new 2 storey block providing 16 classrooms and associated spaces linking to existing building, new single storey providing 4 classrooms and associated spaces in SE corner of the site and a new larger sports hall. 3. Internal alterations and remodelling to main school building providing enlarged reception and main entrance, converting existing reception classrooms into new music/dance studio space and upgrading and remodelling of the existing kitchen and dining hall. 4. New incoming electrical connection 5. Provision of temporary classrooms and toilets for the duration of the works, including creation of services connections
Agenda Page Number: 215
Members Site Visit
Members visited the site on Saturday 5 March 2016. The following queries have been raised:
· Is there any potential for grey-water re-use?
The agent has advised that grey-water use was discounted as an option within the sustainability strategy for Uxendon Manor Primary School because of the relatively low water volume used in the kitchen and sinks. Add to this the intermittent use of the facilities (for example limited by the length of school day and holiday periods) grey-water recycling would not merit the capital cost and use of area for storage/treatment/pump plant. Above all the environmental benefits are low impact in this setting.
Similarly, rain-water harvesting for toilet flushing would require substantial storage and may not serve its purpose as the school WCs flushes are not used on a regular basis, restricted by the school day and school term. In other words, water would be stored that is not required and would eventually overflow to attenuation tanks already providing sustainable drainage.
The scheme does achieve carbon reduction 40% improvement on Part L 2010 Building Regulation, which is comparable to a target of 35% reduction from 2013 Building Regulations, and will achieve BREEEAM 'Very Good'. This has been discussed within paragraphs 56 to 68 of the main committee report.
· Have the effects on sewerage infrastructure been considered
This matter is discussed in more detail below.
Additional comments received
An objection has been received by an Urban Drainage consultant raising the following concerns:
· Surcharging of the sewer network above cover levels in this area is well known. The main area affected within the School is cordoned off and sewage litter is present within that area. This area is close to the proposed footpath and the proposed Orchard. Public Health and Sanitation is an issue to be addressed.
· Works carried out directly above the crown of the Sewer i.e. demolition of buildings and subsequent backfilling and soil compacting will impose stresses into the crown of the sewer.
The Lead Local Flooding Authority has provided the following information At Uxendon Manor School, the applicant has taken into consideration flooding risks and are providing suitable DocSuppF Document Imaged Ref: 15/5240 Page 1 of 2 SuDS and proposed discharge from the new school is considerably less then existing. This will reduce the flooding risks. As part of the Flood and Water Management Act 2010, we are required to manage flood risks arising from surface water, ordinary watercourses and ground water but not from foul sewer as this is the responsibility of Water Company.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
11 Uxendon Manor Primary SchoolReport | 102 KB | DownloadRead as text |
PDF |
Uxendon Manor Primary School, Vista Way, Harrow, HA3 0UX (Ref.15/5240)Report | 1.5 MB | Download |
Follow Planning Committee at Brent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Aug 2026 | Apologies for AbsenceApologies for absence were received from Councillor Gallagher with Councillor Ahmadi-Moghaddam substituting. Apologie... | Decided | Open |
| 5 Aug 2026 | Declarations of interestsNo declarations of interest were made during the meeting. | Decided | Open |
| 5 Aug 2026 | Minutes of the previous meetingRESOLVED that the minutes of the previous meeting held on Thursday 2 July 2026 be approved as a correct record of the... | Approved | Open |
| 5 Aug 2026 | 26/0225 - Brent NHS Primary Care Trust, Wembley Centre For Health & Care, 116 Chaplin Road, Wembley, HA0 4UZGranted planning permission subject to: (1) The prior completion of a satisfactory legal agreement; and (2) The condi... | Agreed | Open |
| 5 Aug 2026 | Any Other Urgent BusinessThere was no other urgent business. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.