Cabinet RESOLVED : (1) To note the background and current project position as set out in paragraphs 3.1 – 3.8 of the report and the way forward set out in paragraphs 3.9 – 3.12 of the report. (2) To note the increased forecast project costs of £17.3m as set out in paragraph 4.1 of the report as a result of the original contractor failure and the proposed resolution. (3) To approve the virement of the sum of up to £6.0m from the basic need capital grant to this project as set out in paragraphs 4.1 – 4.4 of the report to meet the increased forecast project costs. (4) To note that it was intended that such losses and costs, including the costs of re-procurement that had arisen as a result of the original Contractor’s default of its obligation, would be pursued to the extent possible under the Parent Company Guarantee. This value stood at £6.3m and was set out in paragraph 4.6 of the report. (5) To note that subject to (3) above the Strategic Director of Regeneration & Environment in consultation with the Cabinet Members for Schools, Employment and Skills would approve the award of a Medium Value Works Contract as set out in section 5.1 of the report.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1This report provides an update on the current position of the expansion project at Uxendon Manor Primary School. It also requests approval of the virement of a sum of £6.0m to increase the project budget, notes a revised procurement strategy and the intention to pursue the claim through a commercial settlement against the contractor’s Parent Company Guarantee (PCG) for such losses and costs as have arisen as a result of the original contractor’s default.
2.0Recommendation(s)
That Cabinet:
2.1Note the background and current project position as set out in paragraphs 3.1 – 3.8 and the way forward in paragraphs 3.9 – 3.12. 2.2 Note the increased forecast project costs of £17.3m as set out in paragraph 4.1 as a result of the original contractor failure and the proposed resolution.
2.3Approve the virement of the sum of up to £6.0m from the basic need capital grant to this project as set out in paragraphs 4.1 – 4.4 to meet the increased forecast project costs.
2.4Note that it is intended that such losses and costs, including the costs of re- procurement that have arisen as a result of the original Contractor’s default of its obligation, will be pursued to the extent possible under the Parent Company Guarantee. This value stands at £6.3m and is set out in paragraph 4.6.
2.5Note that subject to Recommendation 2.3 above the Strategic Director of Regeneration & Environment in consultation with the Cabinet Members for Schools, Employment and Skills would approve the award of a Medium Value Works Contract as set out in section 5.1.
3.0Background and Proposed Way Forward
Background
3.1On 26 January 2017, the Council entered into a design and build contract with Lakehouse Contracts Limited (“Lakehouse”) for Uxendon Manor Primary School as part of the Phase 3 Primary School Expansion Programme. This contract was subsequently executed on 15 January 2018 at a value of £6.5m.
3.2On 8th October 2018, sectional completion of the new buildings was due to be delivered and external areas on 8th February 2019. However, there were significant contractor delays resulting in sectional completion not being achieved. On 9th October 2018, the Council made financial deductions (Liquidated and Ascertained Damages (`LADs`).
3.3In November 2019, the contractor significantly reduced activity on site and effectively stopped work on site in December 2018 without completing the project. The original expansion project included three areas of new build which consisted of a new reception classroom block, hall and the main teaching block. The new reception classroom block has been completed and is operational. The new hall and main teaching block are built but not sufficiently complete to be occupied.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.