What the committee will consider, in order, with every paper attached to its item. South Kilburn Regeneration Programme - Site 18 encompassing Salusbury Road Car Park, Cullen House and adjoining land is the main business.
Members are invited to declare at this stage of the meeting, any relevant personal and prejudicial interests and discloseable pecuniary interests in any matter to be considered at this meeting.
Decision: - that the minutes of the previous meeting held on 27 June 2016 be approved as an accurate record of the meeting. Decision page
In accordance with Contract Standing Orders 88 and 89, this report requests Cabinet approval to award two contracts for Accommodation Based Mental Health (ABMH) services to support people who have mental health needs and are in recovery. This report provides further detail of the of the services, the procurement process followed and provides a recommendation of who the contracts should be awarded to as determined...
Decision: ( i ) that approval be given to the award of Contract 1, an Accommodation Based Mental Health contract to support people with mental health needs as detailed in paragraph 3.2. a to Look Ahead Care and Support for a term of one year with option to extend by up to 2 successive one year periods; (ii) that approval be given to the award of Contract 2, an Accommodation Based Mental Health contract to support people with mental health needs as detailed in paragraph 3.2.b to Metropolitan Housing Trust... Decision page
The Council has completed a thirty days consultation on proposed changes. This report outlines the responses to that consultation, the potential impact on the residents and resulting recommendations taking into account the feedback that has been received from current and future users of Adult Social Care Services.
Decision: ( i ) that the responses received during the thirty days consultation from 25 April to 27 May 2016 be noted; (ii) that approval be given for officers to implement a single charging policy which combines the existing Fairer Charging Policy for housing related support and CRAG related to charging for residential care services; (iii) that it be noted that the new charging policy includes residents supported through the Shared Lives scheme under Fairer Charging; (iv) that agreement be given to the... Decision page
1.1 This report seeks the approval of Cabinet to the terms for the acquisition of a first of these identified sites, that of Ujima House and its car park in order to progress the implementation of the Wembley Housing Zone and agreement to enter into a contract with the Greater London Authority to fund the acquisition of the property.
Decision: ( i ) that approval be given to enter into a contract for the acquisition by the council of Ujima House and its car park on the terms set out in Appendix One to this report, with approval of the final terms to be delegated to the Strategic Director, Resources in consultation with the Strategic Director, Resources in consultation with the Cabinet Member for Housing; (ii) that approval be given to enter into a funding contract with the Greater London Authority to receive Housing Zone grant to... Decision page
Brent Council is committed to providing a high quality parking service and a fair, consistent and transparent approach to parking and traffic enforcement. We hope that the publication of statistical and financial information will support achievement of these objectives. The purpose of the Annual Report is to explain the aims and objectives of the Council’s Parking service and the key achievements of the last...
Decision: ( i ) that approval be given to the publication of the Parking Service’s draft Annual Report 2015/16, set out as the Appendix to the report ; (ii) that responsibility for approval of Parking Annual Reports from 2016/17 onwards be delegated to the Highways Committee; (iii) that it be noted that additional information on the outcome of appeals to the independent appeal service, Environment and Traffic Adjudicators (ETA), will be added to the published Annual Report in September 2016. Decision page
This report updates members on proposals to deliver a new Enterprise Hub and proposes the re-development of the Carlton and Granville Centres as a location for the Enterprise Hub and deliver 95 new home with additional community space.
Decision: ( i ) that approval be given to Option 2 for redeveloping the Carlton & Granville Centres, Granville Road, London, NW6 5RA (the subject site) to deliver 95 new homes, an Enterprise Hub and 3274sqm of additional community use space; (ii) that a further update be provided to formally approve final scheme plans and the required capital investment to bring forward the phased redevelopment of the Carlton and Granville Centres and ensure continuity of occupation for the Enterprise Hub within the... Decision page
This report relates to Hereford House and Exeter Court (being part of ‘Phase 3A’ of the South Kilburn regeneration programme and as shown edged red on Appendix 1). This report seeks the Cabinet’s approval of a procurement strategy for an architecturally led multidisciplinary design team for the comprehensive redevelopment of Hereford House and Exeter Court, being part of Phase 3A of the South Kilburn regeneration...
Decision: (i) that approval be given to the procurement of an architecturally led multidisciplinary design team to develop a detailed planning application for comprehensive redevelopment of Hereford House and Exeter Court by either: calling off the Greater London Authority (GLA) and Transport for London (TfL) Architecture , Design and Urbanism Panel (ADUP) or such other appropriate OJEU compliant framework; and evaluating those tenders in accordance with the relevant Framework; or alternatively inviting... Decision page
This report sets out the approvals required by the Cabinet to further progress this project originally within Phase 2b of the regeneration programme. This report sets out proposals for Salusbury Road Car Park, Cullen House and adjoining land comprising of the spur road, Keniston Press, TfL offices at Premier House and the Falcon Public House (together defined as " Site 18 "), which forms part of Phase 2b of the...
Decision: ( i ) that consent to restart the proposed redevelopment of Site 18 be confirmed and also and that the recommendations made in July 2011, can be relied upon by officers to secure possession of Site 18 and where relevant, following the completion of the statutory consultation exercises as set out below: i ) authorise the Strategic Director of Regeneration and Environment to seek the Secretary of State's Consent to the disposal and development of Cullen House for the purposes of Ground 10A of... Decision page
The proposal is to redevelop the site to provide approximately 55 new Temporary Accommodation (TA) units for homeless households, 67 Private Rented Sector (PRS) homes and 14 units of New Accommodation for Independent Living (NAIL) together with replacement non-residential space – see appendix 1 site plan and 2 Pellings feasibility study.
Decision: ( i ) that approval be given to capital investment of £33m to bring forward the development of the London Road scheme, subject to further viability testing, local consultation and planning consent as detailed in paragraph 3.17 of the report from the Strategic Director of Resources; (ii) that the expenditure necessary to progress the project through to grant of planning permission, estimated to be in the region of £500,000 be noted; (iii) that it be noted that the land at Ark Elvin Academy... Decision page
1.1 The Council has the discretion to award discounts in national non-domestic rates to businesses under section 47 of the Local Government Finance 1988. To award discounts under this provision a business must meet criteria set by the Council’s Cabinet. Any discount scheme needs Cabinet approval. The qualifying criteria is set out in Appendix 1 to this report. The Council has the discretion to award discounts in...
Decision: ( i ) that the discretionary discount scheme for businesses accredited to the London Living Wage Foundation be continued to 31 March 2019 on the basis that the Business Rates discount will continue to be five times the cost of accreditation and will be awarded to businesses in Brent which become accredited with the Living Wage Foundation and who meet the criteria detailed in Appendix 1 to the report from the Strategic Director, Resources; (ii) that it be noted that the approval and continuation... Decision page
Following assessment of 43 applications to the Voluntary Sector Initiative Fund – Local Grants scheme, this report seeks agreement to grant fund 11 projects led by voluntary organisations for two years, subject to performance.
Decision: ( i ) that the grant funding allocations from the Voluntary Sector Initiative Fund – Local Grants scheme to the voluntary sector led projects set out in paragraph 3.12 of the report from the Director Performance, Policy and Partnerships, which would run between 1 October 2016 and 30 September 2018, be approved: (ii) that it be noted that all grant funding allocations referred to in ( i ) above would be made subject to the Council’s Grant Conditions with the organisation required to sign an... Decision page
The following items are not for publication as they relate to the following category of exempt information as specified in the Local Government Act 1972 namely: School Building Project Costs “Information in respect of which a claim to legal professional privilege could be maintained in legal proceedings” “Information relating to the financial or business affairs of any particular person (including the authority...
Decision: that the press and public be now excluded from the meeting as the following report contains the following category of exempt information as specified in the Local Government Act 1972 namely: Information relating to the financial or business affairs of any particular person (including the authority holding that information). Information in respect of which a claim to legal professional privilege could be maintained in legal proceedings. Decision page
Decision: Report recommendations agreed.
Notice of items to be raised under this heading must be given in writing to the Head of Executive and Member Services or his representative before the meeting in accordance with Standing Order 64.
Item 11 is where most of this meeting's papers sit: 4 papers, about 2.9 MB.
This report sets out the approvals required by the Cabinet to further progress this project originally within Phase 2b of the regeneration programme. This report sets out proposals for Salusbury Road Car Park, Cullen House and adjoining land comprising of the spur road, Keniston Press, TfL offices at Premier House and the Falcon Public House (together defined as " Site 18 "), which forms part of Phase 2b of the...
This committee has dealt with the subject before.
Get the decision the day it is recorded, and anything that comes back to the committee on this subject.
All 23 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
The committee last met on 27 June 2016. 5 of its items lead into this meeting; 4 items are new. Point at any item to follow a thread. Procedural items are left out.
Community Asset Transfer at Tenterden Pavilion & Sports Ground, 289 Preston Road HA3 0QQ, marketing outcome and recommendation, BHP and Housing Management Arrangements, Accommodation services for people with learning disabilities, Supply and Demand of Accommodation and 5 more do not return this time.
See the 27 June meetingEvery Cabinet meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
Brent, Cabinet
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the Cabinet, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.