( i ) that approval be given to capital investment of £33m to bring forward the development of the London Road scheme, subject to further viability testing, local consultation and planning consent as detailed in paragraph 3.17 of the report from the Strategic Director of Resources; (ii) that the expenditure necessary to progress the project through to grant of planning permission, estimated to be in the region of £500,000 be noted; (iii) that it be noted that the land at Ark Elvin Academy, presently used as temporary parking, is surplus to requirements and approval be given to application to Secretary of State through a section 77 application, to secure agreement that the land is no longer required for educational purposes and can be used for residential.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1The proposed redevelopment of London Road provides a significant opportunity for the council to provide good quality housing for vulnerable households, while also generating significant revenue savings in two key areas of expenditure: Temporary Accommodation and care homes.
In summary, the proposal is to redevelop the site to provide approximately 55 new Temporary Accommodation (TA) units for homeless households, 67 Private Rented Sector (PRS) homes and 14 units of New Accommodation for Independent Living (NAIL) together with replacement non-residential space – see appendix 1 site plan and 2 Pellings feasibility study.
1.2Related cabinet approvals
The Strategic Property Plan 2015-19, sets out a presumption for Brent to retain its limited property assets, utilising them to support regeneration, generating revenue savings, and capital investment for new income generation.
The investment strategy (April 2016)
Temporary Accommodation Reform Plan (March 2016), approved the development of long term Private Rented Sector (PRS) homes which can be let to homeless households at Local Housing Allowance (LHA) rates and states that the London Road site will be used to develop self-contained Temporary Accommodation units for emergency and short term use as an alternative to Bed &Breakfast.
Meeting Version no. rev n Date Date Brent Housing Strategy 2014-19 seeks to significantly increase the supply of affordable housing and minimise the use of Bed & Breakfast accommodation
One Council Strategic Objectives. The development is a strategic fit helping to meet the Council’s statutory duty to provide for homeless families and contribute to the NAIL programme. It delivers Council budget savings from Bed &Breakfast accommodation savings and improved service delivery by improving the quality of TA and NAIL accommodation.
Recommendations
2.1That Cabinet agree to capital investment of £33m to bring forward the development of the London Road scheme, subject to further viability testing, local consultation and planning consent as detailed in paragraph 3.17.
2.2That Cabinet note that the expenditure necessary to progress the project through to grant of planning permission is estimated to be in the region of £500,000.
2.3Cabinet to note the land at Ark Elvin Academy, presently used as temporary parking, is surplus to requirements and Cabinet to authorise application to Secretary of State through a section 77 application, to secure agreement that the land is no longer required for educational purposes and can be used for residential.
3.0Detail
Background
3.1The subject sites as detailed at Appendix 1 comprises:
The former Dennis Jackson Centre, (0.251 hectares). The premises are subject to a D1 (Community) Use Class. The building was demolished in 2013 and has stood vacant since.
The Wembley Youth and Community Centre is an approximately 80 year old timber framed building. It occupies a site of 0.179 hectares. The premises are subject to a D1 use class and are currently being marketed on a short term lease (two years), with a break clause.
A hard surfaced area of 0.396 hectares. This is formally part of the Copeland School, and laid out as car park over 5 years ago. It is presently administered by the Ark Elvin Academy and is in use as a temporary car park whilst redevelopment of the existing school takes place.
A shared access with an area of 0.084 hectares.
Meeting Version no. rev n Date Date 3.2 As former uses of the land have either ended or are about to come to an end, it is an opportunity to look at the land as whole. Redevelopment considerations due to local planning policy will require the re-provision of D1 community space.
Business Case
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.