(i) that approval be given to the procurement of an architecturally led multidisciplinary design team to develop a detailed planning application for comprehensive redevelopment of Hereford House and Exeter Court by either: calling off the Greater London Authority (GLA) and Transport for London (TfL) Architecture , Design and Urbanism Panel (ADUP) or such other appropriate OJEU compliant framework; and evaluating those tenders in accordance with the relevant Framework; or alternatively inviting tenders using a Restricted procedure under the Public Contracts Regulations 2015 on the basis of the pre-tender considerations set out in paragraph 3.7 of this report and evaluating the tenders on the basis of the evaluation criteria set out in that paragraph. (ii) that the decision as to the procurement options details in (i) above be delegated to the Strategic Director of Regeneration and Environment; (iii) that the intention to report back to Cabinet to seek approval to award the proposed contract for an architecturally led multidisciplinary design team, once a preferred design team has been identified be noted.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1This report relates to Hereford House and Exeter Court (being part of ‘Phase 3A’ of the South Kilburn regeneration programme and as shown edged red on Appendix 1).
1.2This report seeks the Cabinet’s approval of a procurement strategy for an architecturally led multidisciplinary design team for the comprehensive redevelopment of Hereford House and Exeter Court, being part of Phase 3A of the South Kilburn regeneration programme.
Recommendations
2.1That the Cabinet approve the procurement of an architecturally led multidisciplinary design team to develop a detailed planning application for comprehensive redevelopment of Hereford House and Exeter Court by either: i) calling off the Greater London Authority (GLA) and Transport for London (TfL) Architecture, Design and Urbanism Panel (ADUP) or such other appropriate OJEU compliant framework; and evaluating those tenders in accordance with the relevant Framework; or alternatively ii) inviting tenders using a Restricted procedure under the Public Contracts Regulations 2015 on the basis of the pre-tender considerations set out in paragraph 3.7 of this report and evaluating the tenders on the basis of the evaluation criteria set out in that paragraph.
2.2That Cabinet delegate to the Strategic Director of Regeneration and Environment the decision as to the procurement options details in 2.1.
2.3That Cabinet note the intention to report back to Cabinet to seek approval to award the proposed contract for an architecturally led multidisciplinary design team, once a preferred design team has been identified.
3 Detail
Hereford House and Exeter Court – Design Team Procurement
Meeting: Cabinet Version: v0.2 Date: 25 July 2016 Date: 220616 3.1 A key principle of the phasing strategy for the South Kilburn regeneration programme is that the new affordable homes developed will, where the relevant needs are met, be made available to secure tenants within sites earmarked for development in the next phase. On this basis, the majority of secure tenants of Hereford House and Exeter Court are earmarked to move to the new affordable homes which are being developed on the site of the former Bronte House and Fielding House, Cambridge Road, London, NW6 (being part of ‘Phase 2a’) and ‘Site 11b’ (comprising the sites of the former Royal British Legion Clubhouse and of the Albert Road Day Centre, London, NW6, being part of “Phase 2a”), with the remainder of secure tenants earmarked to move to other identified sites. This in turn will ensure vacant possession of properties within Hereford House and Exeter Court, to enable further phases within the South Kilburn regeneration programme to be brought forward for redevelopment and move existing South Kilburn secure tenants to be re- housed in new high quality homes.
3.2As these two developments (former Bronte and Fielding, and Site 11b sites) will be completed this year, officers are now seeking to appoint an architecturally led multidisciplinary design team (design team) for the comprehensive redevelopment of Hereford House and Exeter Court.
3.3Officers intend to procure a design team to prepare a detailed planning application for the comprehensive redevelopment of Hereford House and Exeter Court to deliver a high quality residential development. This would ensure that there continues to be a pipeline of planning approved developments in South Kilburn, so the delivery of much needed new homes in South Kilburn can continue.
3.4Prior to appointing the design team officers will carry out feasibility work to refine the scope of the brief.
3.5The procurement of a design team to develop a detailed planning application for the comprehensive redevelopment of Hereford House and Exeter Court will be undertaken by either:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.