i. Cabinet noted that the preferred procurement route differs from that originally approved by Cabinet in June 2015. ii. Cabinet delegated authority to award a high value works contract to the Strategic Director of Regeneration and Environment in consultation with the Leader of the Council. i. Cabinet noted that the preferred procurement route differs from that originally approved by Cabinet in June 2015. ii. Cabinet delegated authority to award a high value works contract to the Strategic Director of Regeneration and Environment in consultation with the Leader of the Council.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1This report concerns the award of a high value works contract for the construction of a new accommodation block at the Gordon Brown Outdoor Education Centre.
1.2The Gordon Brown Outdoor Education Centre is owned by the London Borough of Brent and is set in twenty-five acres of a Conservation Area in rural Hampshire countryside. The Centre provides outdoor activities and learning through residential and day visits, contributing to children’s learning about environmental issues and the outdoors.
2.0Recommendation(s)
Cabinet is recommended to:
2.1Note that the preferred procurement route differs from that originally approved by Cabinet in June 2015.
2.2Delegate authority to award a high value works contract to the Strategic Director of Regeneration and Environment in consultation with the Leader of the Council. 3.0 Detail
Background to the Scheme
3.1The 29 June 2015, Cabinet approved the invest to save proposal put forward by the Strategic Director of Children and Young People to replace a poor condition accommodation block at the Gordon Brown Outdoor Education Centre (GBOEC). The GBOEC is a Brent Council owned and operated asset which is situated in Hampshire.
Revised Procurement Process and Timetable
3.2The June 2015 Cabinet report gave a purely indicative procurement timetable and no estimated dates for project completion. The procurement timetable in the 2015 report indicated that the procurement process would begin in July 2015 with adverts being placed two days after the Cabinet meeting. It was not until after the capital project delivery team was in place that it was noted that the development process for delivery required a different approach. Consequently, a detailed review by the Capital Programme Team found the procurement timetable to be unachievable. This was for two key reasons. Firstly because the feasibility study referred to in the June 2015 report was insufficiently detailed. Secondly because at the time of the June report no team had been appointed to provide professional services (design, M&E engineering, project management and cost consultancy) as the project finances had not been confirmed by Cabinet.
3.3Following a procurement process, a professional team has now been appointed. There was some project delay caused by early issues in maintaining consistency with this external resourcing. Project outputs had previously been agreed with the GBOEC staff; however, due to Centre staff changes, designs have been reviewed, amended and are now re-confirmed with the Centre staff. The project is now progressing with a firm plan and team in place.
3.4The Centre site and ecological surveys identified the immediate vicinity of the development site as being the habitat of Great Crested Newts which are a European protected species. These environmental conditions and the seasonal constraints on undertaking further surveys and subsequent works have impacted the programme. The current programme schedules a full planning application being submitted in early December 2016, subject to necessary approvals being in place, including a Natural England Licence. In addition, the GBOEC staff have requested a delay to the period in which construction takes place in order to maximise income opportunities for the Centre. This is accounted for within the timetable below. 3.5 The revised timelines, subject to necessary approvals being in place, for procurement and subsequent programme of works are as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.