i. Cabinet note the Council’s success in obtaining £222,500 of Cabinet Office funding under the One Public Estate (OPE) programme, and the arrangements in hand to successfully deliver the programme. ii. Cabinet considered and agreed the list of priority projects for further OPE bids as set out in the report. iii. Cabinet agreed the withdrawal of the Northwick Park Pavilion from the Community Asset Transfer Programme i. Cabinet note the Council’s success in obtaining £222,500 of Cabinet Office funding under the One Public Estate (OPE) programme, and the arrangements in hand to successfully deliver the programme. ii. Cabinet considered and agreed the list of priority projects for further OPE bids as set out in the report. iii. Cabinet agreed the withdrawal of the Northwick Park Pavilion from the Community Asset Transfer Programme
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1This Report provides: a briefing on the Council’s newly established One Public Estate Programme; governance arrangements; next steps: and proposals for evolving a common public sector estates strategy.
1.2Cabinet agreement is being sought on priorities for next phase OPE projects with a particular emphasis on the fit with delivering the Health Service Transformation Plan.
1.3A detailed summary of Brent’s OPE projects is provided, particularly the Northwick Park OPE project, with approval sought to vary the existing Cabinet decision to allow withdrawal of Northwick Park Pavilion from the CAT programme.
Recommendations
2.1To note the Council’s success in obtaining £222,500 of Cabinet Office funding under the One Public Estate (OPE) programme, and the arrangements in hand to successfully deliver the programme.
2.2To consider and agree the list of priority projects for further OPE bids as set out in the report.
2.3To agree the withdrawal of the Northwick Park Pavilion from the Community Asset Transfer Programme.
3.0Detail
3.1OPE is an initiative delivered in partnership by the Cabinet Office Government Property Unit (GPU) and the Local Government Association (LGA). It provides practical and technical support and funding to councils to deliver ambitious property-focused programmes in collaboration with central government and other public sector partners. 3.2 At its heart, the programme is about getting more from public sector collective assets with four core objectives:
1. creating economic growth (new homes and jobs) 2. more integrated, customer-focused services 3. generating capital receipts 4. reducing running costs
3.3Brent’s initial involvement with OPE was via the London Borough of Barnet OPE programme, where amongst a variety of projects, Barnet has been working with Harrow and Brent to look at synergies between public sector ownerships on Borough boundaries; and ways to improve highway and public realm in Burnt Oak and Colindale. This relationship continues.
3.4With some inspiration taken from the Barnet programme, Brent recognised the potential of the OPE programme to act as a catalyst to co-operative projects with our public sector partners in the Borough. Brent accordingly submitted a bid for OPE’s September 2016 funding round.
Brent has been awarded initial funding of £222,500 up to September 2017 with a further commitment of £138,000 from September 2017. The total sum of £360,500 is available in accordance with the table set out below:
Workstreams 2016/17 2017/18 2018/19 TOTAL OPE Programme £37,500 £37,500 £0 £75,000 Manager Northwick Park £66,250 £135,250 £69,000 £270,500 regeneration programme LB Brent Public £7,500 £7,500 £0 £15,000 Sector/Health Review TOTAL £111,250 £180,250 £69,000 £360,500
3.5Accepting this grant fits with the Council’s strategic priorities. The Council would likely have chosen to conduct such a programme to maximise the potential value within its buildings but there is now an opportunity to do the work to a higher standard. . Furthermore, One Public Estate’s strategic approach should allow partners to not only generate savings and receipts but should also enable re-development of some of the sites.
3.6Brent’s bid also included projects based around: Church End, Vale Farm, and Wembley. Whilst all were recognised by OPE as having considerable potential, they were not awarded funding at the present time, with OPE encouraging working up of more detailed bids, and submission at an appropriate time.
Governance
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.