Resolved
That the proposed process for developing a fully itemised and costed programme of fire safety work for Cabinet consideration and approval by October 2017 be noted.
Cabinet approved this item on Monday 24 July 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
That the proposed process for developing a fully itemised and costed programme of fire safety work for Cabinet consideration and approval by October 2017 be noted.
1.1The purpose of this report is to provide Cabinet with an update on the process for developing a detailed programme of fire safety works, following Council’s agreement of a £10million increase to the Council’s 2017/2018 Capital Programme, in order to meet the cost of enhancing the fire safety measures in the Council’s housing stock.
2.0Recommendation(s)
2.1Cabinet notes the proposed process for developing a fully itemised and costed programme of fire safety work for Cabinet consideration and approval by October 2017.
3.1On 10 July 2017, Council discussed a report which sets out fire safety arrangements for residential accommodation in Brent and specific measures which the Council and Brent Housing Partnership (BHP) are taking in response to the tragic fire at Grenfell Tower last month. 3.2 Council agreed that a £10million programme was required and resolved to ask the Government to meet this cost increase to the Council’s 2017/2018 Capital Programme, in order to meet the cost of enhancing the fire safety measures in the Council’s housing stock.
3.3Council agreed that the Chief Executive should write to the Government as a matter of urgency to request that the Government provide direct financial support to meet the costs that will be incurred. The letter has been sent to the Government requesting financial support, as well as requesting that the Government urgently consider revocation of the permitted development rights for office to residential conversions; that the Government review the building control laws which allow the use of building control teams from both the private sector and other local authorities to inspect buildings which can mean a total lack of oversight by local authority inspectors of the fire risk level in some privately owned high rise blocks and that the Government address whether licensing laws for landlords in the private sector are stringent enough to ensure that all dwellings are fit for human habitation.
3.4The draft minute recording Full Council’s decision (which has not been formally approved yet) is attached at Annex 1 and the letter is attached at Annex 2.
4.0Actions to develop the detailed work programme for enhanced fire measures in High-rise blocks
4.1A specification is in the process of being developed, which will outline the enhanced fire detection equipment that could be installed, over and above the required standard. In order to establish the exact works required, a suitably qualified specialist will carry out a survey of each building, and specify the schedule of works. This will be specific to each block, but may include detection systems localised alarms in communal areas and/or dwellings, fire suppression systems such as sprinklers, or smoke extraction systems.
4.2The appropriate procurement framework will be accessed in order to appoint the relevant specialists required in order to complete this preparatory work.
4.3Surveyors will visit all blocks between now and September in order to carry out these surveys, which will inform the detailed plan which will be brought back for consideration by Cabinet in October 2017.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Draft MinutesAppendix 1 | 203 KB | Download |
PDF |
Letter to SoSAppendix 2 | 356 KB | Download |
PDF |
Fire safety letter to residents with FAQsAppendix 3 | 687 KB | Download |
PDF |
Programme of Works to enhance Fire Safety in the Council’s Housing StockReport | 228 KB | DownloadRead as text |
Follow Cabinet at Brent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2026 | Apologies for AbsenceApologies for absence were received from Thomas Cattermole (Corporate Director Resident & Housing Services) with Spen... | Decided | Open |
| 9 Nov 2026 | Declarations of InterestCouncillor Grahl declared a personal interest in relation to Agenda Item 10 (Rent Setting Policy Statement) and Agend... | Decided | Open |
| 9 Nov 2026 | Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec... | Approved | Open |
| 9 Nov 2026 | Matters Arising (if any)None identified. | Decided | Open |
| 9 Nov 2026 | Petitions (if any)There were no petitions presented at the meeting. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.