( i ) that approval be given to the strategy for the procurement of works as set out in paragraph 3.16 of the report to deliver the Phase 3 School Expansion Programme of projects; (ii) that approval be given to the invite of tenders on the basis of the pre-tender considerations set out in paragraph 3.17 where this was considered by the Strategic Director of Regeneration and Growth in consultation with the Lead Member for Regeneration and Housing, the Director of Legal and Procurement and Chief Finance Officer as the most appropriate procurement route in accordance with the strategy for the procurement of works to deliver the Phase 3 School Expansion Programme; (iii) that in respect of paragraph (ii) above, approval be given to the evaluation of tenders on the basis of the evaluation criteria set out in paragraph 3.17 of the report. Following evaluation, Cabinet approval will be sought to award high value contracts in accordance with Council Standing Orders; (iv) that it be noted that officers would review a medium term procurement solution for the development and delivery of capital projects (including establishment of a Brent contractors framework) and report back to Cabinet early in the New Year, as described in paragraph 3.15.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
The Council has a challenging programme of school expansion designed to meet increased pressure for school places year on year and ensure that all children have access to a school place. The delivery of the school expansions to time and budget is becoming increasingly difficult, partly as a consequence of changes in the construction market which are making it more difficult to procure contractors to build the schools. This report seeks approval to a new strategy for the procurement of works contracts for the next phase of the school expansion programme (Phase 3), which aims to provide sufficient permanent school places to meet demand from September 2015. It is important to note that this procurement strategy, if agreed, will become the means of appointing building contractors for agreed school expansion projects. It will have no impact on normal consultation processes for determining which schools will expand. This report comes to Cabinet ahead of the final version of the School Place Planning Strategy which is scheduled for October in order to enable projects which have already been agreed to proceed on time.
Recommendations
The Cabinet is recommended to:
2.1Approve the strategy for the procurement of works as set out in paragraph 3.16 of this report to deliver the Phase 3 School Expansion Programme of
Meeting: Cabinet Version no.1.1 Date: 15 September 2014 Date: 04.09.2014 projects.
2.2Approve inviting tenders on the basis of the pre-tender considerations set out in paragraph 3.17 where this is considered by the Strategic Director of Regeneration and Growth in consultation with the Lead Member for Regeneration & Housing, the Director of Legal and Procurement and Chief Finance Officer as the most appropriate procurement route in accordance with the strategy for the procurement of works to deliver the Phase 3 School Expansion Programme.
2.3In respect of paragraph 2.2 above, approve the evaluation of tenders on the basis of the evaluation criteria set out in paragraph 3.17 of this report. Following evaluation, Cabinet approval will be sought to award high value contracts in accordance with Council Standing Orders.
2.4Note that officers will review a medium term procurement solution for the development and delivery of capital projects (including establishment of a Brent contractors framework) and report back to Cabinet early in the New Year, as described in paragraph 3.15.
3.0Detail
3.1In August 2012 Members approved a four year rolling School Expansion Programme to address the demand for primary school places up to 2016-17. Subsequent reports have provided updates including in November 2013 when projects within that overall Portfolio were more formally allocated to Programmes of expansion to provide additional school places in each academic year.
3.2The Phase 3 School Expansion Programme will generate additional permanent primary school places from September 2015 with capital project works anticipated to complete during that academic year. The programme of Phase 3 school expansion as approved by Members currently includes the following schools:
Project Description Notes/Status Expand by 1FE Funding recently Islamia Primary secured Elsley Primary Expand by 2FE Stonebridge Primary Expand by 1FE Malorees Infant & Junior Expand by 1-2FE Approved in Phase 2 Uxendon Manor Primary Expand by 2FE Programme but moved to Phase 3 Total 7-8 FE
3.3Each of these projects is at a different stage of development given the lengthy and sometimes complex process of securing schools’ sign up, undertaking the necessary statutory consultation on expansion as well as the planning process. At this stage Members should note that the Governing Bodies of
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.