RESOLVED that: (i) Cabinet approved the introduction of the permanent capital pipeline as set out in Appendix 1 to the report; (ii) Cabinet agreed that the schemes listed in Appendix 1 (Column A) were promoted from the pipeline to the main programme; (iii) Cabinet noted that in future, the remaining pipeline schemes would be individually moved to the main programme (and hence formally committed) when it was strategically and economically advantageous to do so but always subject to the submission of detailed business cases and Cabinet approval where applicable; and (iv) Cabinet agreed that in light of recommendation 2.2 above, the revised 3 year capital budget (Appendix 3) is adopted and presented to Council for approval as part of the Budget & Council Tax Report in February 2019.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1This report outlines the Council’s updated approach to prioritising future capital investment, ensuring it is in line with our aspirations and reflective of the priorities and circumstances within Brent. It also explains the framework within which the Council’s long-term capital investment plans have been prioritised and brought forward for consideration as part of the financial planning and budget setting process.
1.2These proposals will draw upon multiple funding sources. In particular as Strategic CIL receipts have now surpassed the levels required to begin to undertake major infrastructure projects the proposals in the report, if agreed, will eventually result in the allocation of in excess of £40m of CIL receipts, which represents 100% of total receipts as at 31 March 2018.
1.3It is worth noting that although this report is principally about codifying the process for bringing forward capital proposals from the pipeline to the main programme, other benefits could arise. These proposals will facilitate a more strategic approach to capital investment and avoid the risk of sub-optimal decision making caused by assessing capital proposals in isolation of wider considerations. At the same time, it could improve capital forecasting and reduce the instances of programme slippage as it provides an opportunity to pause before formally committing funds to the capital programme, allowing time to compile detailed business cases and more realistic project timelines. 1.4 As described in more detail in the report, the process to date has essentially been to encourage responsible officers to identify all their likely capital needs over the next four years or so. Inevitably, this means that the current list of possible projects is over subscribed. We are therefore proposing the introduction of a permanent pipeline that sits alongside the main programme. From this pipeline, capital schemes can then be promoted to the main programme when it is not only affordable, but strategically advantageous to do so.
1.5There is no fixed limit to the size of the capital programme. The Council can set it at whatever size it likes provided it is affordable (the technical definition of which is provided by the ‘prudential indicators’ agreed by Council each year). In the revenue budget growth for the cost of the capital programme – interest and debt repayment charges – has been assumed, based on the Councils long term capital aspirations. If the list of projects now identified in appendix 2 are approved it would add more revenue cost in future years, but at present this can be contained within our existing budget growth assumptions which assumes that a number of these proposals will generate ongoing revenue savings and attract grant funding.
2.0Recommendation(s)
2.1Cabinet approve the introduction of the permanent capital pipeline (as set out in Appendix 1).
2.2Cabinet agree that the schemes listed in Appendix 1 (Column A) are promoted from the pipeline to the main programme.
2.3Cabinet note that in future, the remaining pipeline schemes will be individually moved to the main programme (and hence formally committed) when it is strategically and economically advantageous to do so but always subject to the submission of detailed business cases and Cabinet approval where applicable.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.