London Borough of Brent
Cabinet, Monday 15 April 2019 at 4.00pm

Expansion of Elsley Primary School - Termination of Design and Build Contract

Noted Executive 1 paper

Cabinet noted this item on Monday 15 April 2019. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

i. Cabinet noted the current status and contractual position with Lakehouse Contracts Limited on the design and build contract for Elsley Primary School as set out in the report. ii. Cabinet approved the termination of the High Value Works Contract with Lakehouse Contracts Limited for expansion of Elsley Primary School. iii. Cabinet noted that subject to Recommendation 2.2 set out in the report, the Strategic Director of Resources would approve the award of one or more Low and/or Medium Value Works Contracts to enable outstanding works to be completed using powers delegated under the Constitution. iv. Cabinet noted that the school was and would continue to be operational whilst the steps outlined in the report recommendations be taken. v. Cabinet noted that Officers would review options for the recovery of any wasted or additional costs against Lakehouse Contracts Limited as described in Appendix 1. i. Cabinet noted the current status and contractual position with Lakehouse Contracts Limited on the design and build contract for Elsley Primary School as set out in the report. ii. Cabinet approved the termination of the High Value Works Contract with Lakehouse Contracts Limited for expansion of Elsley Primary School. iii. Cabinet noted that subject to Recommendation 2.2 set out in the report, the Strategic Director of Resources would approve the award of one or more Low and/or Medium Value Works Contracts to enable outstanding works to be completed using powers delegated under the Constitution. iv. Cabinet noted that the school was and would continue to be operational whilst the steps outlined in the report recommendations be taken. v. Cabinet noted that Officers would review options for the recovery of any wasted or additional costs against Lakehouse Contracts Limited as described in Appendix 1.
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1.1This report provides Cabinet with an update on the contractual position on the design and build contract for the expansion of Elsley Primary School and seeks authority to terminate the existing design and build contract.

2.0Recommendation(s)

That Cabinet:

2.1Note the current status and contractual position with Lakehouse Contracts Limited on the design and build contract for Elsley Primary School as set out in paragraphs 3.1 – 3.5 of the report. 2.2 Approve the termination of the High Value Works Contract with Lakehouse Contracts Limited for expansion of Elsley Primary School.

2.3Note that subject to Recommendation 2.2 above, the Strategic Director of Resources would approve the award of one or more Low and/or Medium Value Works Contracts to enable outstanding works to be completed using powers delegated under the Constitution.

2.4Note that the school is and will continue to be operational whilst the steps outlined in Recommendation 2.2 and 2.3 are taken.

2.5Note that Officers will review options for the recovery of any wasted or additional costs against Lakehouse Contracts Limited as described in Appendix 1.

3.0Detail

Current status and contractual position

3.1The Council entered into a design and build contract with Lakehouse Contracts Limited (“Lakehouse”) for works at Elsley Primary School on 20 May 2016. The contract was subsequently executed on 15 January 2018 at a value of £7,204,089.

3.2Practical completion (PC) of the construction works was certified in early July 2018, subject to the contractor completing a limited scope of outstanding works during the Summer holidays 2018. The majority of these works were not carried out as planned. The contractor cited financial issues as the reason it was unable to complete the works. These works are still outstanding. As PC was certified, no Liquidated and Ascertained Damages (LADs) could be imposed. At PC, some fees were withheld against a schedule of the incomplete works in addition to the retention monies being held by the Council.

3.3Verbally on 20 January and in writing on 23 January 2019 the contractor advised that it was their intention to complete the outstanding works and to provide a programme during that week. Some scheduling information was provided and the work was expected to be completed in February around the half term holiday. Some minor works were completed however the majority remains outstanding.

3.4On the 11 March 2019, there was a hearing at the High Court to determine an application by Lakehouse for administration. Judge Mullen made an administration order in respect of Lakehouse. An administrator for the company, Lane Gary Bednash of CMB Partners UK Limited has been appointed.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Expansion of Elsley Primary School: Termination of Design and Build ContractReport 100 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 15 attended
MB
Councillor Muhammed Butt Leader of the CouncilChair, present
MM
Councillor Margaret McLennan Deputy LeaderVice-Chair, present
AA
Councillor Amer Agha MB BS, MSc, PHCM Lead Member for Schools, Employment and SkillsCommittee Member, present
HF
Councillor Harbi Farah Lead Member for Adult Social CareCommittee Member, present
KH
Councillor Krupesh Hirani Lead Member for Public Health, Culture and LeisureCommittee Member, present
TM
Councillor Tom Miller Lead Member for Community SafetyCommittee Member, present
MP
Councillor Mili Patel Lead Member for Children's Safeguarding, Early Help and Social CareCommittee Member, present
KS
Councillor Krupa Sheth Lead Member for EnvironmentCommittee Member, present
ES
Councillor Eleanor Southwood Lead Member for Housing and Welfare ReformCommittee Member, present
ST
Councillor Shama Tatler Lead Member for Regeneration, Highways and PlanningCommittee Member, present
AA
Councillor Abdirazak AbdiCommittee Member, in attendance
BC
Councillor Bhagwanji ChohanCommittee Member, in attendance

All 15 on the meeting page

On this subject at Brent

Search all
  1. Expansion of Elsley Primary School - Termination of Design and Build ContractThis decision
  2. Expansion of Uxendon Manor & Elsley Primary Schools - Design & Build Contract UpdateNoted

More from Brent Cabinet

All decisions
MeetingDecisionOutcome
9 Nov 2026 Apologies for AbsenceApologies for absence were received from Thomas Cattermole (Corporate Director Resident & Housing Services) with Spen... Decided Open
9 Nov 2026 Declarations of InterestCouncillor Grahl declared a personal interest in relation to Agenda Item 10 (Rent Setting Policy Statement) and Agend... Decided Open
9 Nov 2026 Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec... Approved Open
9 Nov 2026 Matters Arising (if any)None identified. Decided Open
9 Nov 2026 Petitions (if any)There were no petitions presented at the meeting. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies