To note that the full cost for undertaking the Town Hall Remodelling Project, as agreed at the September 2013 meeting of Extraordinary Council, exceeds the 5% budget tolerance level set at that meeting. 2. To approve the commencement of works for a revised scope for the Town Hall Remodelling Project within the previously agreed budget of £3.6m, which would ensure: I. Creation of a customer service area on the ground floor, suitable for joint use between Council services and partner organisations . II. Provision of modern, space efficient office layouts for all Council services based at the Town Hall. III. Availability of defined areas for commercial lease. IV. Completion of essential access and health and safety works as necessary to achieve joint occupation ... view the full minutes text for item 322.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
1.1A report on the Town Hall Remodelling Project was previously presented to the September 2013 meeting of Extraordinary Council. Since that meeting and the approval granted, the project has been progressing through the processes necessary to commence the remodelling works.
1.2These processes have examined the feasibility of the preferred Outline Business Case (OBC) option and resulted in a designed general arrangement for the building and an overall scope for the necessary remodelling works.
1.3The resulting general arrangement for the building contains a lower overall area for commercial lease and insufficient area to accommodate a dedicated hub of office space for community sector use.
1.4Final costings have been prepared for the remodelling works identified by the feasibility study. These indicate that undertaking the full scope of the specified remodelling works would require a capital investment of c. £5.3m for building works plus the continued requirement of £0.5m for associated ICT infrastructure.
1.5This investment is c. £2.2m greater than that previously approved. This financial variance, along with there being insufficient area for dedicated office space for community sector use, indicate that the objectives of the previously approved OBC are no longer being fully met.
1.6On that basis, the project has been reviewed to identify a revised scope that would meet the previously approved budget. 1.7 The resulting revised scope would ensure that key operational objectives of the project could be delivered but would necessitate the exclusion of certain elements of work relating to the building and services infrastructure. It is anticipated that these excluded elements would be subject to the development of separate business cases.
Recommendations
2.1To note that the full cost for undertaking the Town Hall Remodelling Project, as agreed at the September 2013 meeting of Extraordinary Council, exceeds the 5% budget tolerance level set at that meeting.
2.2To approve the commencement of works for a revised scope for the Town Hall Remodelling Project within the previously agreed budget of £3.6m, which would ensure:
I. Creation of a customer service area on the ground floor, suitable for joint use between Council services and partner organisations. II. Provision of modern, space efficient office layouts for all Council services based at the Town Hall. III. Availability of defined areas for commercial lease. IV. Completion of essential access and health and safety works as necessary to achieve joint occupation of the Town Hall.
2.3That the draft Heads of Terms agreed for the commercial lease of part of the Town Hall are reviewed to ensure they provide the Council with best value.
2.4To note that further business cases relating to the infrastructure of the Town Hall will be developed for consideration by the Asset and Enterprise Committee, anticipated to include:
• Sustainability measures for the Town Hall (incorporating sustainable solutions for heat, light and power) • Increased commercial use of the Civic areas of the Town Hall.
All of the above also assume that the allocated ICT budget of £0.5million remains. 3. Introduction and Background
3.1A report was presented to the Ordinary Council meeting of July 2011, which identified that the existing floor space of the Town Hall is in excess of what is required and that the building is not fit for purpose for its current usage.
3.2Having considered various options, the Council decided at that time to retain the Town Hall and an OBC was subsequently developed for the options relating to that decision. From this, it was agreed in July 2012 to pursue an option for part remodelling of the building allowing for a lease agreement with a third party tenant.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.