Brentwood Borough Council
Council, Wednesday 10 December 2014 at 7.00pm

Old House

Agreed Committee 5 papers

Council agreed this item on Wednesday 10 December 2014. Below is the council's own wording, with the papers it was decided on.

Item323

Resolved

RESOLVED that: 1. Based on the Business Case presented, Members proceeded with damp, bat and structural surveys to support the proposal to convert to residential units. 2. Subject to no material changes to the financial viability arising from the survey works, to agree the appointment of consultants to undertake detailed designs in conjunction with English Heritage and the Essex County Council Historic Buildings Adviser, leading to the preparation of contract documents to maximise the number of units achievable on the site. 3. Following successful listed building consent and Planning approval, authority be given to the Leader of the Council, the Chair of the Asset and Enterprise Panel and (Acting) Chief Executive, to undertake a tender process and to appoint a suitable contractor to complete the refurbishment of the property and on completion, instruct letting agents to market the property. 4. Subject the approval of this project, Members endorsed the borrowing requirement of £1,080,000 and that until the budget for 2015/16 is finalised , provision for the Year 1 borrowing costs will be assumed to be funded from the General Fund Working Balance.
Word for word from the decision Brentwood published for this meeting. Source: brentwood.moderngov.co.uk

Follow this further

Built from Brentwood's papers

What the report saysPro

Report to Council

Executive summary

1.1This report acknowledges the “in principle” decision of the 15th July 2014 Asset & Enterprise Committee to proceed with the redevelopment of Old House into flats and to report to Full Council in order for Members to consider the financial implications for the Capital Programme.

1.2This report outlines the updated information received from the Architects, together with revised rental and sale value information for Members consideration.

2. Recommendation(s)

2.1That, based on the Business Case presented, Members proceed with damp, bat and structural surveys to support the proposal to convert Old House to residential units.

2.2That, subject to no material changes to the financial viability arising from the survey works, to agree the appointment of consultants to undertake detailed designs in conjunction with English Heritage and the Essex County Council Historic Buildings Adviser, leading to the preparation of contract documents to maximise the number of units achievable on the site.

2.3That following successful listed building consent and Planning approval, authority be given to the Leader of the Council, the Chair of the Asset and Enterprise Panel and (Acting) Chief Executive, to undertake a tender process and to appoint a suitable contractor to complete the refurbishment of the property and on completion, instruct letting agents to market the property. 2.4 That, subject the approval of this project, Members endorse the borrowing requirement of £1,080,000 and that until the budget for 2015/16 is finalised, provision for the Year 1 borrowing costs will be assumed to be funded from the General Fund Working Balance.

3 Introduction and Background

3.1Members are reminded that the history and background to this town centre property was set out in the report to the 15th July 2014 Asset and Enterprise Committee.

3.2In the Feasibility Study provided by the previous architects, comment was made that: “Seven apartments are possible but there this is in conflict with the requirements of Essex County Council (Conservation Department) and English Heritage” and is summed up in James Ross of Essex County Council’s letter dated 28th January 2013 ... and Sheila Stones of English Heritage letter dated 27th January 2013.... and would not achieve listed building consent”.

3.3The key concerns were:

o The need for further opening up and investigation to ascertain more detail relating to the existing structure and historic fabric.

o Further development of the design required in respect to new door openings and sub divisions

o The removal of the single storey 20th century extension.

o To avoid the lateral conversion into apartments but convert back to the original two town houses as originally built recreating the original internal layout.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 1.3 MB Download
PDF
Appendix BAppendix B 194 KB Download
PDF
Appendix CAppendix C 193 KB Download
PDF
Appendix DAppendix D 32 KB Download
PDF
Old HouseReport 123 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

46 of 53 attended
VD
Councillor Vicky DaviesChair, present
RK
Councillor Roger KeebleVice-Chair, present
BA
Councillor Barry AspinellCommittee Member, present
PB
Councillor Philip BakerCommittee Member, present
GB
Councillor Gareth BarrettCommittee Member, present
RC
Councillor Ross CarterCommittee Member, present
KC
Councillor Karen ChilversCommittee Member, present
GC
Councillor Graeme ClarkCommittee Member, present
JC
Councillor Jon ClokeCommittee Member, present
LC
Councillor Liz CohenCommittee Member, present
AC
Councillor Ann CoeCommittee Member, present
PF
Councillor Paul FaragherCommittee Member, present

All 53 on the meeting page

On this subject at Brentwood

Search all
  1. Old HouseThis decision
  2. Renewal of Communal Gas Central Heating, Hot and Boosted Cold Water Systems to Drake HouseApproved
  3. Old House RefurbishmentApproved
  4. Old HouseNoted
  5. Old House - Surveys and ProcurementNoted

More from Brentwood Council

All decisions
MeetingDecisionOutcome
15 Jul 2026 Appointment of representatives on Outside Organisations 2026/2027RESOLVED UNANIMOUSLY to: R1. That the Council approves the appointment of Members to Outside Organisations for 2026/2... Approved Open
15 Jul 2026 Annual Report 2025/26RESOLVED : R1 That Members note the Annual Report 2025-26 as set out in Appendix A of the report, which provides an u... Noted Open
15 Jul 2026 Mid Essex Unitary Authority - Joint Committee ProposalRESOLVED to: R1: Note the update provided on Local Government Reorganisation (LGR), including key developments and Br... Noted Open
15 Jul 2026 Withdrawal from the South Essex Council Joint CommitteeRESOLVED UNANIMOUSLY to: R1. That the Council agrees to withdraw for the SEC Joint Committee. R2. Formal written noti... Agreed Open
15 Jul 2026 Exclusion of press and publicIt was AGREED to move into private session to discuss the rest of the agenda items. The Mayor closed the meeting to t... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies