Policy, Projects and Resources Committee noted this item on Monday 12 March 2018. Below is the council's own wording, with the papers it was decided on.
RESOLVED UNANIMOUSLY . 1. Note the Town Hall update within this paper. 2. To agree that the PPR Committee receives a further update report on progress of the Town Hall at the next PP & R Committee. 3. Progress the detailed work necessary to install a water misting system via an Automated Suppression System on the top two floors of the Town Hall. 4. That an increased capital budget of £200,000 with an ongoing revenue cost for maintenance of £5,000 per annum be identified for the provision of an automated suppression system. That should the overall projected costs look to be exceeding this amount the decision be referred back to Policy, Projects and Resources Committee. Reasons for Recommendation It was recommended to report back to Members at the next PP & R Committee so they are aware of progress generally and the latest financial position in terms of any changes relating to both expenditure and revenue.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
Report to Policy, Projects and Resources Committee
12th March 2018
Policy, Projects and Resources Committee
Town Hall Update and Automated Suppression System
Report of: Greg Campbell – Policy and Programme Manager
Wards Affected: All
This report is: Public
1. Executive Summary The Town Hall project is progressing in line with identified timescales.
This report provides a general update, progress on the Hub Groups and back office regarding the remodelled Town Hall.
The report provides information on the fire safety compliance of the scheme and the provision of an automated suppression system for members to consider following a motion at Ordinary Council (18.10.2017).
An automated suppression system is a general term given to systems which are activated automatically when a certain temperature is reached which in turn releases a liquid, substance or gas that reduces the impact or spread of a fire and/or smoke.
The report by Lawrence Webster Forrest (Fire Safety Compliance experts- see Appendix A attached) confirms that the current scheme (without any automated suppression system) meets the current standard. However, discussion with experts (including the Fire Brigade) state that risk is further mitigated if an Automated Suppression System is if installed on the top two floors of the Town Hall. 2. Recommendations
2.1Note the Town Hall update within this paper.
2.2To agree that the PPR Committee receives a further update report on progress of the Town Hall at the next PP & R Committee.
2.3Progress the detailed work necessary to install a water misting system via an Automated Suppression System on the top two floors of the Town Hall.
2.4That an increased capital budget of £200,000 with an ongoing revenue cost for maintenance of £5,000 per annum be identified for the provision of an automated suppression system. That should the overall projected costs look to be exceeding this amount the decision be referred back to Policy, Projects and Resources Committee.
3. Introduction and Background
This report updates Members on the progress of the Town Hall Remodelling project, including information received following the request for a review of the fire safety compliance of the proposal, which includes consideration of an automated suppression system.
Overall Progress Update The Town Hall Remodelling project is on schedule and continues to work towards a deadline of residential properties being habitable from the 1st April 2019. The completion of the remainder of the project is set for June 2019 when it is also envisaged that the Community Hub will be open for business. The Council’s back office services will begin to relocate back to the Town Hall during July 2019. A schedule of homecoming will be developed in early 2019 as the project develops.
The enablement work will be finished by the 5th March 2018, which will see the complete ‘strip out’ of the entire building leaving a shell in which the remodelling can begin. Contractors are presently being appointed following a procurement exercise that began back in June 2017. The remodelling work will begin during March 2018 at the conclusion of some valued engineering and signing of appropriate contracts. All appropriate due diligence has been undertaken, including financial and a site visit, satisfying us of the ability, approach and finished work of the company likely to undertake the remodelling.
The Hub The Hub is the focal point of all services being delivered for the community and will include Mind, Council for Voluntary Services, Citizens Advice, the Council and Job Centre Plus who are all committed to the hub. Heads of Terms have all been agreed with these groups and ‘Agreements to Lease’ are now in the process of being signed. The design is now in its final draft and work will continue with these groups throughout the life cycle of the project to not only ensure their space is ready but to also discuss how the groups will work together once in the hub.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Policy, Projects and Resources Committee at Brentwood and we tell you when its next papers are published, before the meeting rather than after it.
Asset Development Programme UpdateTo approve the direction of the Asset Development Programme. Reason for the Recommendation To update the Committee on...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.