Audit, Scrutiny and Transformation Committee decided this item on Monday 7 March 2016. Below is the council's own wording, with the papers it was decided on.
RESOLVED. 1. That the Strategic Risk Register and risk scores recorded for each risk accurately represented the current status of each risk. REASON FOR RECOMMENDATION Risk Management continues to be embedded quarterly within the Senior Management Team reports, where Heads of Service discuss the top level risks for their service areas to ensure that the risks are updated to reflect the ongoing changes. In addition the Risk and Insurance Officer will work with Managers to ensure that any new or emerging risks are identified, assessed and managed appropriately.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
Report to Audit, Scrutiny and Transformation Committee
Executive summary
1.1The report updates members of the Audit, Scrutiny and Transformation Committee on new, closed or changes to strategic risks.
2. Recommendation(s)
2.1To agree the Strategic Risk Register and that the risk scores recorded for each risk accurately represents the current status of each risk.
3. Introduction and Background
3.1The governance arrangements set out in the ‘Insurance & Risk Management Strategy’ require the Audit Committee to review the strategic risks every quarter.
3.2The strategic risk register is monitored quarterly by the Corporate Leadership Board who consider the risks, the mitigations and agree the content. It will be the responsibility of the Audit Committee to review the strategic risks and confirm they are confident that the risks associated within this register are those which are strategic and relevant to the organisation at this point in time and the considered future.
3.3The Council’s insurance premium is discounted by £5,000, which is used to buy Risk Management Services from Zurich Municipal. 3.4 A meeting was held with Matthew Hillier, Strategic Risk Consultant, Zurich Municipal to discuss the support that Zurich will undertaking with the Council in the next financial year. This will include:-
Strategic and Operational Risk Reporting Review Business Continuity Planning – Scenario Test
4. Issue, Options and Analysis of Options
Strategic Risks
4.1In accordance with the Council’s Insurance and Risk Management Strategy, risk owners have reviewed their risks and risk scores, with the results discussed and agreed at CLB on 15 February 2016.
4.2Attached to this report at Appendix A is a summary showing the current status of each risk and any movement in risk score compared with previous monitoring periods, together with explanatory commentary on the key issues for each risk.
4.3As a result of the current risk review one risk has increased, one decreased and ten scores have remained unchanged.
4.4Risk Score Increased
Red risk RSK1 – Financial Pressures (Row No. 1) This risk has been increased to the highest risk rating following the Provisional Local Government Finance Settlement 2016/17.
4.5Risk Score Reduced
Green risk RSK9 – Lack of Strategic Direction (Row No. 12) This risk has been reduced with the approval of the Corporate Plan 2016-2019 at the Ordinary Council Committee meeting on 18 November 2015.
Risk Matrix
4.6The twelve risks are plotted on the risk matrix below. The current assessment identifies that three risks will remain in the red area of the risk matrix. 5 10 15 20 25 RSK1
Negligible Minor Moderate Significant Major Negative Impact/Severity
No. Risk No. Risk 1 Finance Pressures 8 Contract/Partnership Failure 2 Local Development Plan 9 Lack of Strategic Direction Disaster Recover/Continuity Failure to Spend Capital 3 10 Planning Receipts 4 Organisational Capacity 11 Roll out of Universal Credit Information Management Extension of Right to Buy to 5 12 and Security registered provider tenants Failure to deliver key 7 Commercial Activities 13 Corporate Projects
Reasons for recommendation
5.1Risk Management continues to be embedded quarterly within the Senior Management Team reports, where Heads of Service discuss the top level risks for their service areas to ensure that the risks are updated to reflect the ongoing changes.
5.2In addition the Risk & Insurance Officer will work with managers to ensure that any new or emerging risks are identified, assessed and managed appropriately. 6. Consultation
6.1None.
7. References to Corporate Plan
7.1Effective risk management arrangements will support the Council to achieve its corporate priorities. The process will enable identification of risks and issues enabling informed decision making to removed or reduce them in order for the priorities to be achieved.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Audit, Scrutiny and Transformation Committee at Brentwood and we tell you when its next papers are published, before the meeting rather than after it.
Annual Certification Report 2014/2015RESOLVED UNANIMOUSLY. 1. That Members note the contents of the Certification of Claims and Returns Annual Report 2014...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.