Audit, Scrutiny and Transformation Committee, Monday 7 March 2016 at 7.00pm

Strategic Risk Review

Decided Finance 2 papers

Audit, Scrutiny and Transformation Committee decided this item on Monday 7 March 2016. Below is the council's own wording, with the papers it was decided on.

Item374

Resolved

RESOLVED. 1. That the Strategic Risk Register and risk scores recorded for each risk accurately represented the current status of each risk. REASON FOR RECOMMENDATION Risk Management continues to be embedded quarterly within the Senior Management Team reports, where Heads of Service discuss the top level risks for their service areas to ensure that the risks are updated to reflect the ongoing changes. In addition the Risk and Insurance Officer will work with Managers to ensure that any new or emerging risks are identified, assessed and managed appropriately.
Word for word from the decision Brentwood published for this meeting. Source: brentwood.moderngov.co.uk

Follow this further

Built from Brentwood's papers

What the report saysPro

Report to Audit, Scrutiny and Transformation Committee

Executive summary

1.1The report updates members of the Audit, Scrutiny and Transformation Committee on new, closed or changes to strategic risks.

2. Recommendation(s)

2.1To agree the Strategic Risk Register and that the risk scores recorded for each risk accurately represents the current status of each risk.

3. Introduction and Background

3.1The governance arrangements set out in the ‘Insurance & Risk Management Strategy’ require the Audit Committee to review the strategic risks every quarter.

3.2The strategic risk register is monitored quarterly by the Corporate Leadership Board who consider the risks, the mitigations and agree the content. It will be the responsibility of the Audit Committee to review the strategic risks and confirm they are confident that the risks associated within this register are those which are strategic and relevant to the organisation at this point in time and the considered future.

3.3The Council’s insurance premium is discounted by £5,000, which is used to buy Risk Management Services from Zurich Municipal. 3.4 A meeting was held with Matthew Hillier, Strategic Risk Consultant, Zurich Municipal to discuss the support that Zurich will undertaking with the Council in the next financial year. This will include:-

 Strategic and Operational Risk Reporting Review  Business Continuity Planning – Scenario Test

4. Issue, Options and Analysis of Options

Strategic Risks

4.1In accordance with the Council’s Insurance and Risk Management Strategy, risk owners have reviewed their risks and risk scores, with the results discussed and agreed at CLB on 15 February 2016.

4.2Attached to this report at Appendix A is a summary showing the current status of each risk and any movement in risk score compared with previous monitoring periods, together with explanatory commentary on the key issues for each risk.

4.3As a result of the current risk review one risk has increased, one decreased and ten scores have remained unchanged.

4.4Risk Score Increased

 Red risk RSK1 – Financial Pressures (Row No. 1) This risk has been increased to the highest risk rating following the Provisional Local Government Finance Settlement 2016/17.

4.5Risk Score Reduced

 Green risk RSK9 – Lack of Strategic Direction (Row No. 12) This risk has been reduced with the approval of the Corporate Plan 2016-2019 at the Ordinary Council Committee meeting on 18 November 2015.

Risk Matrix

4.6The twelve risks are plotted on the risk matrix below. The current assessment identifies that three risks will remain in the red area of the risk matrix. 5 10 15 20 25 RSK1

4 8 12 16 20 RSK11 Likelihood/Probability RSK12

3 6 9 12 15 RSK4 RSK2 RSK5 RSK10 2 4 6 8 10 RSK3 RSK13 RSK7 RSK8 1 2 3 4 5 RSK9

Negligible Minor Moderate Significant Major Negative Impact/Severity

No. Risk No. Risk 1 Finance Pressures 8 Contract/Partnership Failure 2 Local Development Plan 9 Lack of Strategic Direction Disaster Recover/Continuity Failure to Spend Capital 3 10 Planning Receipts 4 Organisational Capacity 11 Roll out of Universal Credit Information Management Extension of Right to Buy to 5 12 and Security registered provider tenants Failure to deliver key 7 Commercial Activities 13 Corporate Projects

Reasons for recommendation

5.1Risk Management continues to be embedded quarterly within the Senior Management Team reports, where Heads of Service discuss the top level risks for their service areas to ensure that the risks are updated to reflect the ongoing changes.

5.2In addition the Risk & Insurance Officer will work with managers to ensure that any new or emerging risks are identified, assessed and managed appropriately. 6. Consultation

6.1None.

7. References to Corporate Plan

7.1Effective risk management arrangements will support the Council to achieve its corporate priorities. The process will enable identification of risks and issues enabling informed decision making to removed or reduce them in order for the priorities to be achieved.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 92 KB Download
PDF
Strategic Risk ReviewReport 91 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 18 attended
PF
Councillor Paul FaragherChair, apologies, sent representative
SM
Councillor Sheila MurphyVice-Chair, present
GB
Councillor Gareth BarrettCommittee Member, present
GC
Councillor Graeme ClarkCommittee Member, present
MN
Councillor Mrs Noelle HonesCommittee Member, present
PM
Councillor Philip MynottCommittee Member, present
JP
Cllr Jan PoundCommittee Member, present
MM
Councillor Mrs Mellissa SladeCommittee Member, apologies
WT
Councillor William TrumpCommittee Member, present
ZF
Zoey FoakesOfficer, expected
CL
Chris LeslieOfficer, present
RM
Rob ManserOfficer, expected

All 18 on the meeting page

On this subject at Brentwood

Search all
  1. Strategic Risk ReviewThis decision
  2. Strategic Risk Register and Risk Management Update – Quarter 1 2026/27Decided
  3. Strategic and Operational RiskAgreed
  4. Strategic and Operational Risk ReviewAgreed
  5. Strategic and Operational Risk ReviewAgreed
  6. Strategic & Operational Risk ReviewAgreed

More from Brentwood Audit, Scrutiny and Transformation Committee

All decisions
MeetingDecisionOutcome
7 Mar 2016 Appointment of the Vice-ChairRESOLVED UNANIMOUSLY. Decided Open
7 Mar 2016 Annual Certification Report 2014/2015RESOLVED UNANIMOUSLY. 1. That Members note the contents of the Certification of Claims and Returns Annual Report 2014... Noted Open
7 Mar 2016 External Audit Plan 2015/2016RESOLVED UNANIMOUSLY. 1. That Members note the External Audit Plan 2015/2016. REASON FOR RECOMMENDATION The Audit Pla... Noted Open
7 Mar 2016 Internal Audit Progress ReportRESOLVED UNANIMOUSLY. 1. That Members would receive and note the contents of the reports. REASON FOR RECOMMENDATION T... Noted Open
7 Mar 2016 Internal Audit Plan 2016/2017RESOLVED UNANIMOUSLY. 1. That the Committee approved the Internal Audit Plan for 2014/17 and the Operational Plan for... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies