RESOLVED : To agree amendments to the Strategic Risk Register and that the risk scored recorded for each risk accurately represents the current status of each risk. Reasons for recommendation Risk Management continued to be embedded quarterly within the Senior Management Teams reports, where Service Heads discussed the top level risks for their service area to ensure that the risks were updated to reflect the ongoing changes. In addition the Risk & Insurance Officer would continue to work with risk managers to maintain the good progress to date and further develop a consistent application of risk management considerations across all operations of the Council.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
1.1The report updates members of the Audit & Scrutiny Committee on new, closed or changes to strategic risks.
2. Recommendation(s)
2.1To agree amendments to the Strategic Risk Register and that the risk scores recorded for each risk accurately represents the current status of each risk.
3. Introduction and Background
3.1The governance arrangements set out in the ‘Insurance & Risk Management Strategy’ require the Audit & Scrutiny Committee to review the strategic risks every quarter.
3.2The strategic risk registers are monitored quarterly by the Corporate Leadership Board (CLB) who consider the risks, the mitigations and agrees the content. It is the responsibility of the Audit & Scrutiny Committee to review the strategic risks and confirm they are confident that the risks associated within this register are those which are strategic and relevant to the organisation at this point in time and the considered future.
4. Issue, Options and Analysis of Options
Strategic Risks
4.1In accordance with the Council’s Insurance and Risk Management Strategy, risk owners have reviewed their risks and risk scores. These were discussed and agreed by CLB on 27 February 2017.
4.2Attached to this report at Appendix A is a summary showing the current status of each risk and any movement in risk score compared with previous monitoring periods, together with explanatory commentary on the key issues for each risk.
4.3As a result of the current risk review all risk scores have remained unchanged.
4.4There has been one new risk added to the Strategic Risk Register:
Green risk RSK14 – That outsourcing/shared service arrangements result in the Council’s democratic duties not being fulfilled or ignored, leading to a failure in the Council’s obligations. (row 13) This has been given a risk score of 2; 1 = likelihood, 2 = Impact
Risk Matrix
4.5The thirteen risks are plotted on the risk matrix in Table 1. The current assessment identifies that two risks will remain in the red area of the risk matrix. Table 1 – Risk Matrix
Negligible Minor Moderate Significant Major Negative Impact/Severity
No. Risk No. Risk 1 Finance Pressures 9 Lack of Strategic Direction Failure to Spend Capital 2 Local Development Plan 10 Receipts Disaster 3 Recover/Continuity 11 Roll out of Universal Credit Planning Extension of Right to Buy 4 Organisational Capacity 12 to registered provider tenants Information Management Failure to deliver key 5 13 and Security Corporate Projects 7 Commercial Activities 14 Outsourcing/shared services of democratic Contract/Partnership services 8 Failure
Reasons for recommendation
5.1Risk Management continues to be embedded quarterly within the Senior Management Team reports, where Service Heads discuss the top level risks for their service areas to ensure that the risks are updated to reflect the ongoing changes. 5.2 In addition the Risk & Insurance Officer will continue to work with risk managers to maintain the good progress to date and further develop a consistent application of risk management considerations across all operations of the Council.
Consultation
6.1None.
7. References to Corporate Plan
7.1Effective risk management arrangements will enable the Council to achieve its corporate priorities. The process will allow identification of risks and issues enabling informed decision making to remove or reduce them in order for the priorities to be achieved.
8. Implications
Financial Implications Name & Title: Ramesh Prashar, Financial Services Manager Tel & Email: 01277 312513 / [email protected]
8.1None arising specifically from this report, but control measures identified in risk registers could have financial or resource implications.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Internal Audit Plan and Operation PlanRESOLVED UNANIMOUSLY : That the Committee approves the Internal Audit Operational Plan for 2017/18. Reason for recomm...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.